Exam 8: Managing Projects
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Table 3.1
Time (weeks)
Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A -1 1 2 3 B A 2 4 12 C A 1 2 3 D B 6 7 8 E B,C 10 12 14 F D 2 3 4 G E,F 1 5 15 H A 2 5 14
-Using Table 3.1,what is the earliest expected time of completion of the whole project?
(Multiple Choice)
4.8/5
(46)
________ is the maximum length of time that an activity can be delayed without delaying the entire project.
(Short Answer)
4.8/5
(38)
Table 3.2
Time (days)
Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A \@cdots 2 4 6 B \@cdots 1 4 7 C A 2 2 2 D B 1 7 10 E D 2 4 6 F E 1 2 3 G C 3 4 17 H D, G 3 7 11 I D 8 9 10 J F,H 4 5 6 K I 1 1 1
-Using Table 3.2,what is the earliest expected time of completion of the whole project?
(Multiple Choice)
4.8/5
(47)
An activity that includes writing final reports,completing remaining deliverables,and compiling the team's recommendations for improving the project process is called ________.
(Short Answer)
4.7/5
(38)
Project managers should be able to organize a set of disparate activities.
(True/False)
4.8/5
(36)
Table 3.5
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 6 B \@cdots 3 C A,B 2 D A 6 E C 2 F D,E 2 G C 8
-Using Table 3.5,how many weeks can activity B be delayed without changing the whole project's earliest completion time?
(Multiple Choice)
4.8/5
(36)
Table 3.6
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 9 C \@cdots 10 D A 4 E B 12 F C 5 G B,D 6 H E,F 7 I H 8
-Using Table 3.6,what is the slack for activity G?
(Multiple Choice)
4.8/5
(38)
The correct sequence of the four major phases in projects life cycle is; organization,planning,execution and closeout.
(True/False)
4.9/5
(43)
Table 3.9
All activity times for the project are in weeks.
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 \@cdots B 5 7 9 - C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C,D G 7 8 9 D,E H 2 6 10 F
-Using Table 3.9,what is the probability that the project will be completed in 24 weeks or less? You will need to refer to a standard normal table to answer the question.
(Multiple Choice)
4.8/5
(42)
The critical path method (CPM)is a network planning method initially developed as a means to schedule maintenance shutdowns at chemical plants.
(True/False)
5.0/5
(28)
Table 3.9
All activity times for the project are in weeks.
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 \@cdots B 5 7 9 - C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C,D G 7 8 9 D,E H 2 6 10 F
-Using Table 3.9,what is the expected time of completion of the project?
(Multiple Choice)
4.9/5
(40)
Which one of the following situations is more appropriate for the application of project management?
(Multiple Choice)
4.8/5
(37)
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks).
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B
-Using Table 3.10,what is the critical path and expected completion time for this project?
(Multiple Choice)
4.8/5
(38)
Which of the following statements concerning the critical path in project network is FALSE?
(Multiple Choice)
4.7/5
(36)
Scope creep refers to all activities that have yet to be completed in a project.
(True/False)
4.9/5
(41)
Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks).
Activity Expected Time Immediate Predecessor () 8 \@cdots- B 10 - C 7 A,B D 5 B E 12 C F 7 C,D G 6 E,F H 10 F
-Using Table 3.13,what is the critical path and the expected completion time for this project?
(Multiple Choice)
4.8/5
(34)