Exam 9: Resource Allocation
Exam 1: Projects in Contemporary Organizations41 Questions
Exam 5: The Project in the Organizational Structure49 Questions
Exam 2: Strategic Management and Project Selection39 Questions
Exam 3: The Project Manager44 Questions
Exam 4: Negotiation and the Management of Conflict44 Questions
Exam 6: Project Activity Planning39 Questions
Exam 7: Budgeting and Cost Estimation40 Questions
Exam 8: Scheduling50 Questions
Exam 9: Resource Allocation46 Questions
Exam 10: Monitoring and Information Systems53 Questions
Exam 11: Project Control41 Questions
Exam 12: Project Auditing52 Questions
Select questions type
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.
(Multiple Choice)
4.9/5
(32)
__________ are tasks that logically follow a particular task in time.
(Short Answer)
5.0/5
(32)
Economically speaking, crashing a project creates a technology change in the __________ for an activity.
(Multiple Choice)
4.8/5
(38)
The __________ technique overlaps the design and build phases of a project to expedite its completion.
(Multiple Choice)
4.8/5
(39)
The two fundamental approaches to constrained allocation problems are __________.
(Multiple Choice)
4.8/5
(49)
The tasks that logically precede a particular task in time are referred to as __________.
(Multiple Choice)
4.7/5
(30)
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
(Short Answer)
4.7/5
(40)
The points between the extreme points of the relationship between time use and resource use represent __________.
(Multiple Choice)
5.0/5
(35)
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.
(Multiple Choice)
4.8/5
(36)
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
(Short Answer)
4.9/5
(39)
List some of the common priority rules utilized when following heuristic solution methods.
(Essay)
4.8/5
(39)
Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.
(Multiple Choice)
4.9/5
(36)
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.
(Multiple Choice)
4.9/5
(36)
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.
(Multiple Choice)
5.0/5
(28)
When using heuristic solutions to build a schedule, __________ will always take precedence.
(Multiple Choice)
4.9/5
(36)
When we change technology, we may also be changing the level of __________ in carrying out the activity.
(Short Answer)
4.7/5
(27)
Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
(Short Answer)
5.0/5
(36)
Showing 21 - 40 of 46
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)