Gantt charts show the planned and yet to be completed activities against total activities.

(True/False)
4.7/5
(37)

If the following jobs are sequenced according to the DDATE rule then job A would be completed on day (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then job A would be completed on day (assume zero for today's date)

(Multiple Choice)
4.9/5
(42)

If the work remaining is greater than the time remaining, the critical ratio (CR) will be

(Multiple Choice)
4.9/5
(42)

Finite scheduling will not load a resource beyond its fixed capacity.

(True/False)
4.9/5
(40)

Input/output control provides the information necessary to regulate work flow in a job shop environment.

(True/False)
4.7/5
(30)

What is the difference between infinite scheduling and finite scheduling?

(Essay)
4.8/5
(46)

Typically, there are more options available when scheduling employees because labor is a very flexible resource.

(True/False)
4.8/5
(44)

If the following jobs are sequenced according to the SLACK rule then job A would be completed on day (assume zero for today's date) If the following jobs are sequenced according to the SLACK rule then job A would be completed on day (assume zero for today's date)

(Multiple Choice)
4.8/5
(42)

If a job is ahead of schedule, then its critical ratio (CR) will be

(Multiple Choice)
4.8/5
(36)

The process of prioritizing jobs that have been assigned to a resource is called

(Multiple Choice)
4.8/5
(36)

If the following jobs are sequenced according to the LPT rule then job D would be completed on day (assume zero for today's date ) If the following jobs are sequenced according to the LPT rule then job D would be completed on day (assume zero for today's date )

(Multiple Choice)
4.8/5
(53)

If the following jobs are sequenced according to the DDATE rule then the mean tardiness (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)

(Multiple Choice)
4.9/5
(38)

If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days) for all jobs is (assume zero for today's date)

(Multiple Choice)
4.8/5
(26)

The wide variety of jobs in a job shop makes scheduling easy.

(True/False)
4.8/5
(43)

If the following jobs are sequenced according to the LPT rule then the mean completion time (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the LPT rule then the mean completion time (in days) for all jobs is (assume zero for today's date)

(Multiple Choice)
5.0/5
(32)

Four products (1, 2, 3, and 4) must be processed on one of four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below. Four products (1, 2, 3, and 4) must be processed on one of four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below.   If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 3 is assigned to If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 3 is assigned to

(Multiple Choice)
4.8/5
(32)

A ________ chart is used to show both planned and completed activities against a time scale.

(Multiple Choice)
4.8/5
(29)

If the following jobs are sequenced according to the FCFS rule, then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the FCFS rule, then the total number of jobs that would be late is (assume zero for today's date)

(Multiple Choice)
4.8/5
(40)

The dispatch list contains the order in which work is assigned to a productive resource.

(True/False)
4.8/5
(40)