Exam 13: Aggregate Planning and Sop
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
The aggregate planning process usually includes dispatching of individual jobs.
(True/False)
4.8/5
(37)
An aggregate plan satisfies forecast demand by potentially adjusting all EXCEPT which of the following?
(Multiple Choice)
4.8/5
(36)
A firm uses graphical techniques in its aggregate planning efforts.Over the next twelve months (its intermediate period),it estimates the sum of demands to be 105,000 units.The firm has 250 production days per year.In January,which has 22 production days,demand is estimated to be 11,000 units.A graph of demand versus level production will show that:
(Multiple Choice)
4.9/5
(36)
________ involves capacity decisions that determine the allocation of resources to maximize revenue or yield.
(Essay)
4.9/5
(35)
In the service sector,which of the following aggregate planning strategies might direct your client to a competitor?
(Multiple Choice)
4.8/5
(35)
Aggregate planning for service firms that provide intangible output deals mainly with:
(Multiple Choice)
4.8/5
(39)
Reddick's Specialty Electronics makes weatherproof surveillance systems for parking lots.Demand estimates for the next four quarters are 25,9,13,and 17 units.The firm is preparing an aggregate plan that uses inventory,regular time and overtime and back orders.Subcontracting is not allowed.Regular time capacity is 15 units for quarters 1 and 2,18 units for quarters 3 and 4.Overtime capacity is 3 units per quarter.Regular time cost is $2000 per unit,while overtime cost is $3000 per unit.Back order cost is $300 per unit per quarter;inventory holding cost is $100 per unit per quarter.Beginning inventory is zero.
The data inputs for this problem,and the optimal solution,generated by microcomputer software,appear below.Answer the following questions based on the scenario and the solution.
a.How many total units will be produced in quarter 1 for delivery in quarter 1?
b.How many units in total will be used to fill back orders over the four quarters?
c.What is the cost to produce one unit in Quarter 4 using overtime to deliver in quarter 1 (filling a back order)?
d.At the end of quarter 3,what is the ending inventory of finished systems?
e.What is the total cost of the solution?
f.What is the average cost per unit?
Reddick's Specialty Electronics
Reddick's Specialty Electronics Solution



(Essay)
4.8/5
(38)
Golden Eagle Machine Works has the following demand requirements and other data for the upcoming four quarters.
What is the total cost of pursuing a chase aggregate plan over the coming year?

(Essay)
4.8/5
(26)
A large consulting firm is deciding on if its workforce should be expanded,maintained,or decreased.Suppose that demand is given in week-long projects,and that a consultant can work on 3 projects each month (1 week off for personal leave and/or other duties such as conferences,etc).Currently there are 25 consultants.Ten consultants are trained for LEAN and 15 for Six Sigma,with 5 of those consultants being overlaps (the consultant is trained for BOTH LEAN and Six Sigma).Assume that all consultants can do the general work.Complete the table (the forecast period is an upcoming month)and prepare a recommendation.


(Essay)
4.8/5
(35)
A professional services firm is investigating revenue management as a means of taking advantage of unused capacity.Analysts for this firm estimate a demand curve for the firm's service,which is sold by the hour.Points on this demand curve include 9000 hours at the current rate of $60 per hour,9500 hours at $55,10,000 hours at $50,and 10,500 hours at $45.Based on this demand curve,what price point would be best for the firm,if its objective is maximum revenue?
(Essay)
4.7/5
(28)
Which of the following actions is consistent with the use of level scheduling?
(Multiple Choice)
4.9/5
(39)
Frito-Lay uses aggregate planning to match capacity with demand because of the ________ associated with its specialized processes.
(Multiple Choice)
4.9/5
(35)
Techniques for controlling the cost of labor in services include accurate scheduling of labor hours to assure quick response to customer demand,on-call labor for unexpected demand,flexibility of labor skills for reallocation of available labor,and flexibility in rate of output or hours of work to meet changing demand.
(True/False)
4.8/5
(34)
________ for developing aggregate plans work with a few variables at a time and are easy to understand and use.
(Essay)
4.9/5
(38)
________ is the process of breaking the aggregate plan into greater detail.
(Essay)
4.9/5
(42)
Which of the following characteristics makes revenue management UNATTRACTIVE to organizations that have perishable inventory?
(Multiple Choice)
4.7/5
(36)
A manager is applying the transportation model of linear programming to solve an aggregate planning problem.Demand in period 1 is 100 units,and in period 2,demand is 150 units.The manager has 125 hours of regular employment available for $10/hour each period.In addition,50 hours of overtime are available for $15/hour each period.If holding costs are $2 per unit each period,how many hours of regular employment should be used in period 1? (Assume demand must be met in both periods 1 and 2 for the lowest possible cost and that production is 1 unit per hour. )
(Multiple Choice)
4.8/5