Deck 11: Project Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/142
Play
Full screen (f)
Deck 11: Project Management
1
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
True
2
A PERT/CPM network is a graphical display of a project that connects activities.
True
3
In CPM, crashing an activity that is not on the critical path increases the cost of the project.
True
4
Before drawing a PERT or CPM network, we must identify all activities and their predecessors.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
5
The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s)responsible is called PERT planning.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
6
The optimistic time is the greatest amount of time that could be required to complete an activity.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
7
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
8
In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
9
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
10
CPM is a probabilistic analysis of managing a project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
11
The first step in planning and scheduling a project is to develop the work breakdown structure.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
12
PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
13
The longest time path through a PERT/CPM network is called the critical path.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
14
PERT stands for Probabilistic Evaluation and Review Technique.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
15
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
16
The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
17
Given the assumptions in PERT, the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
18
With PERT, we are able to calculate the probability of finishing the project within a specified time.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
19
Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and replanning, rescheduling, and reallocating resources such as personnel and finances.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
20
Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
21
Once the crash cost per time period value is negative, no additional crashing should be performed.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
22
The critical path of a network is the
A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
23
Gantt charts and PERT diagrams provide the same information, just in different formats.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
24
When crashing a project, all critical paths must be shortened by the same amount for activity duration reductions to be cost-effective.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
25
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.
A)8
B)6
C)7
D)9
A)8
B)6
C)7
D)9
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
26
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.
A)14
B)12
C)11
D)13
A)14
B)12
C)11
D)13
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
27
The value of work completed is computed by multiplying budgeted cost by the percent completion.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
28
CPM
A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
29
Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
30
The first step in planning and scheduling a project is to develop the
A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
31
The expected time in PERT is
A)a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic, most likely, and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
A)a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic, most likely, and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
32
The activity crash cost is equal to the incremental cost of shortening the project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
33
The activity difference is the actual duration of an activity less the planned duration of that same activity.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
34
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.
A)6
B)7
C)9
D)5
A)6
B)7
C)9
D)5
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
35
Budgets are computed using only ES times.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
36
PERT
A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
37
For projects that have a daily fixed cost, it is not possible to reduce the overall duration once the cost of crashing exceeds the daily fixed cost.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
38
Slack time in a network is the
A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)amount of time that an activity can be delayed without delaying the entire project.
A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)amount of time that an activity can be delayed without delaying the entire project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
39
Which of the following is not a concept associated with CPM?
A)normal time
B)probability
C)normal cost
D)crash cost
A)normal time
B)probability
C)normal cost
D)crash cost
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
40
In a PERT network, the earliest (activity)start time is the
A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
41
Table 11-1
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, what is the minimum possible time required for completing the project?
A)8
B)14
C)25
D)10
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, what is the minimum possible time required for completing the project?
A)8
B)14
C)25
D)10
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
42
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.
A)2.33
B)5.44
C)8.00
D)64.00
A)2.33
B)5.44
C)8.00
D)64.00
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
43
Given the following small project, the critical path is ________ days. 
A)10
B)14
C)16
D)20

A)10
B)14
C)16
D)20
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
44
Table 11-2
The following represents a project with four activities.All times are in weeks.

According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?
A)2
B)4
C)8
D)12
The following represents a project with four activities.All times are in weeks.

According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?
A)2
B)4
C)8
D)12
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
45
Given the following small project, the critical path is ________ days. 
A)4
B)10
C)12
D)22

A)4
B)10
C)12
D)22
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
46
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)
A)0.98
B)0.48
C)0.50
D)0.02
A)0.98
B)0.48
C)0.50
D)0.02
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
47
Table 11-3

According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?
A)30 and 5.222
B)20 and 5.222
C)30 and 4.222
D)22.667 and 1.111

According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?
A)30 and 5.222
B)20 and 5.222
C)30 and 4.222
D)22.667 and 1.111
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
48
In a PERT network, the latest (activity)start time is the
A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
49
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?
A)108.0
B)110.4
C)89.6
D)85.0
A)108.0
B)110.4
C)89.6
D)85.0
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
50
Table 11-3

According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?
A)5.222
B)4.222
C)1.222
D)1.111

According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?
A)5.222
B)4.222
C)1.222
D)1.111
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
51
Table 11-1
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, compute the latest finish time for activity E.
A)4
B)10
C)14
D)25
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, compute the latest finish time for activity E.
A)4
B)10
C)14
D)25
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
52
Table 11-2
The following represents a project with four activities.All times are in weeks.

According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)
A)0.07
B)0.93
C)0.43
D)0.77
The following represents a project with four activities.All times are in weeks.

According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)
A)0.07
B)0.93
C)0.43
D)0.77
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
53
Table 11-2
The following represents a project with four activities.All times are in weeks.

According to the data in Table 11-2, what is the minimum expected completion time for the project?
A)18
B)19
C)37
D)11
The following represents a project with four activities.All times are in weeks.

According to the data in Table 11-2, what is the minimum expected completion time for the project?
A)18
B)19
C)37
D)11
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
54
The critical path of a network is the
A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
55
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity.
A)2
B)4
C)5
D)15
A)2
B)4
C)5
D)15
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
56
Table 11-3

According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?
A)A-C-E
B)B-D
C)A-B-C-D
D)B-E

According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?
A)A-C-E
B)B-D
C)A-B-C-D
D)B-E
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
57
Table 11-1
The following represents a project with known activity times.All times are in weeks.

According to Table 11-1, compute the slack time for activity D.
A)0
B)5
C)3
D)6
The following represents a project with known activity times.All times are in weeks.

According to Table 11-1, compute the slack time for activity D.
A)0
B)5
C)3
D)6
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
58
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.
A)3
B)6
C)9
D)18
A)3
B)6
C)9
D)18
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
59
Table 11-2
The following represents a project with four activities.All times are in weeks.

According to the data in Table 11-2, what is the critical path?
A)A-B
B)A-C
C)B-D
D)A-B-C-D
The following represents a project with four activities.All times are in weeks.

According to the data in Table 11-2, what is the critical path?
A)A-B
B)A-C
C)B-D
D)A-B-C-D
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
60
Table 11-1
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?
A)0
B)4
C)8
D)10
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?
A)0
B)4
C)8
D)10
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
61
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.
A)3
B)4
C)5
D)6
A)3
B)4
C)5
D)6
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
62
The project described by:
is best represented by which of the following networks?
A)

B)

C)

D)


A)

B)

C)

D)

Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
63
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, what is the minimum possible time required for completing the project?
A)8
B)12
C)18
D)10
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, what is the minimum possible time required for completing the project?
A)8
B)12
C)18
D)10
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
64
The project described by
has a critical path length of:
A)21 days.
B)14 days.
C)23 days.
D)32 days.

A)21 days.
B)14 days.
C)23 days.
D)32 days.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
65
CPM stands for
A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
66
The two common techniques for drawing PERT networks are
A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
67
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?
A)0
B)4
C)8
D)10
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?
A)0
B)4
C)8
D)10
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
68
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.
A)4
B)3
C)8
D)6
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.
A)4
B)3
C)8
D)6
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
69
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?
A)108.0
B)160.4
C)166.5
D)135.0
A)108.0
B)160.4
C)166.5
D)135.0
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
70
Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)
A)0.68
B)0.78
C)0.22
D)0.32
A)0.68
B)0.78
C)0.22
D)0.32
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
71
PERT stands for
A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
72
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, compute the latest finish time for activity E.
A)4
B)10
C)14
D)25
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, compute the latest finish time for activity E.
A)4
B)10
C)14
D)25
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
73
In PERT, we assume that
A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
74
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.
A)5
B)6
C)7
D)12
A)5
B)6
C)7
D)12
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
75
The project described by:
has a critical path of length of
A)15 days.
B)20 days.
C)17 days.
D)18 days.

A)15 days.
B)20 days.
C)17 days.
D)18 days.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
76
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?
A)4
B)0
C)8
D)5
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?
A)4
B)0
C)8
D)5
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
77
In PERT analysis, the probability of the optimistic time occurring should be on the order of
A)1/3.
B)1/6.
C)1/10.
D)1/100.
A)1/3.
B)1/6.
C)1/10.
D)1/100.
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
78
Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity.
A)10
B)12
C)9
D)11
A)10
B)12
C)9
D)11
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
79
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.
A)3
B)1
C)9
D)6
A)3
B)1
C)9
D)6
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck
80
Table 11-4
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, compute the slack time for activity D.
A)0
B)5
C)3
D)6
The following represents a project with known activity times.All times are in weeks.

Using the data in Table 11-4, compute the slack time for activity D.
A)0
B)5
C)3
D)6
Unlock Deck
Unlock for access to all 142 flashcards in this deck.
Unlock Deck
k this deck