Deck 5: Scope Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/116
Play
Full screen (f)
Deck 5: Scope Management
1
A comprehensive statement of work includes an estimate of time and costs,resource requirements,and the scope of the work to be performed.
True
2
Work authorization functions as the formal "It's OK to begin work," on the project.
True
3
The project closeout step requires project managers to consider the types of records and reports they and their clients will require at the completion of a project.
True
4
A work package may be composed of one or more subdeliverables.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
5
Controls can be established at any point during a project but should follow the maxim "more control is better."
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
6
Until a project has gone through work breakdown structure,it is impossible to determine the relationships among the constituent activities.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
7
________ divides a project into its component substeps in order to begin establishing interrelationships among its constituent activities.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
8
The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
9
Scope reporting not only identifies the type of information that will be reported,but also to whom it will be reported and with what frequency.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
10
________ is the process that addresses project objectives by finding the best ways to meet them.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
11
________ are formally defined as "any measurable,tangible,verifiable outcome,result,or item that must be produced to complete a project or part of a project."
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
12
A work package may consist of more than one milestone.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
13
Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
14
A baseline is the project's scope fixed at a specific point in time.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
15
________ are the lowest level in the work breakdown structure,composed of short duration tasks that have a defined beginning and end.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
16
The ________ is a detailed narrative description of the work required for a project.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
17
The terms lump-sum contract and turnkey contract are interchangeable.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
18
The statement of work is a detailed narrative description of the work required for a project.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
19
A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
20
Work content and expected outcomes are called ________ in project management.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
21
Scope management for a project begins with:
A)a work package.
B)an organization breakdown structure.
C)a statement of goals.
D)a configuration statement.
A)a work package.
B)an organization breakdown structure.
C)a statement of goals.
D)a configuration statement.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
22
Which statement about conceptual development is best?
A)A project goal of "significantly increase computer performance" is better than "improve processing speed 20%" because the team may exceed 20%.
B)It is vital that a best approach to solving a problem be locked in as soon as possible to save analysis time downstream.
C)Conceptual development begins with the process of reducing the project's overall complexity to a more basic level.
D)Project goals should be optimistic to the point of excess.
A)A project goal of "significantly increase computer performance" is better than "improve processing speed 20%" because the team may exceed 20%.
B)It is vital that a best approach to solving a problem be locked in as soon as possible to save analysis time downstream.
C)Conceptual development begins with the process of reducing the project's overall complexity to a more basic level.
D)Project goals should be optimistic to the point of excess.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
23
There were conceivably an infinite number of courses he could take during his final semester,but since he worked 8-5,Jake needed to take night classes.He also needed to ensure that the class was offered at the Edmond campus rather than Midwest City,so he could get home in time for his favorite programs.This whittled down the list of possibilities to Systems Analysis Design and Differential Equations."Neither of these courses is very attractive.I may have to rethink my priorities," Jake wondered aloud."The work schedule and wrestling schedule are significant:
A)scope statements."
B)alternatives."
C)constraints."
D)goals."
A)scope statements."
B)alternatives."
C)constraints."
D)goals."
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
24
One consequence of conceptual development that proceeds with a problem that is poorly understood is:
A)problem restatement.
B)cost overruns.
C)problem clarification.
D)task confusion.
A)problem restatement.
B)cost overruns.
C)problem clarification.
D)task confusion.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
25
The leader for team A isn't sure offhand who needs to approve the next step in their work package,but he knows that if he consults the ________,he can determine who has approval authority for the necessary purchase of that pair of weasels.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
26
Three years and $250,000 later,the homeowner's simple two-bedroom bungalow project had morphed into a state-of-the-art sprawling ranch.The construction manager was able to keep track of all the changes along the way and keep all subcontractors up-to-date thanks to meticulous ________.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
27
The ________ is a document that provides a summary description of each component of the project's goal.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
28
Restrictions that affect project development are:
A)problems.
B)constraints.
C)stop-limits.
D)limitations.
A)problems.
B)constraints.
C)stop-limits.
D)limitations.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
29
Which of these is NOT a typical element of a statement of work?
A)introduction and background
B)a list of activities needed to complete the project
C)technical description of the project
D)timeline and milestones
A)introduction and background
B)a list of activities needed to complete the project
C)technical description of the project
D)timeline and milestones
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
30
________ follows a formal reporting structure,including study and documentation of the project's performance in terms of cost,schedule adherence,and technical specifications as part of project closeout.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
31
A statement of work identifies:
A)a need.
B)a project organization.
C)members of the project team.
D)alternatives.
A)a need.
B)a project organization.
C)members of the project team.
D)alternatives.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
32
The statement of work should contain:
A)information on the key objectives for the project.
B)a brief and general description of the work to be performed.
C)expected project outcomes.
D)All of these are elements of a statement of work.
A)information on the key objectives for the project.
B)a brief and general description of the work to be performed.
C)expected project outcomes.
D)All of these are elements of a statement of work.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
33
The Scope Management chapter begins and ends with the quote,"It's a dream until you write it down.Then it's…"
A)"… etched in stone."
B)"… a scope statement."
C)"… a documented dream."
D)"… a goal."
A)"… etched in stone."
B)"… a scope statement."
C)"… a documented dream."
D)"… a goal."
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
34
________ includes procedures that monitor emerging project scope against original baseline scope.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
35
The type of information that will be reported regularly,who will receive it,and how the information will be collected and disseminated falls under the umbrella of ________.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
36
Conceptual development for a project concludes with:
A)project objectives.
B)alternative analysis.
C)project delivery.
D)team dissolution.
A)project objectives.
B)alternative analysis.
C)project delivery.
D)team dissolution.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
37
Which statement about scope management is best?
A)Scope management must take place during the conceptual development,full definition,execution,and termination phases.
B)Project goals don't matter in scope management as long as the budget is not exceeded.
C)Scope management is accomplished in a single step by any one project team member.
D)Scope management can begin once a project hits operational level.
A)Scope management must take place during the conceptual development,full definition,execution,and termination phases.
B)Project goals don't matter in scope management as long as the budget is not exceeded.
C)Scope management is accomplished in a single step by any one project team member.
D)Scope management can begin once a project hits operational level.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
38
The cat-skinning project management team considers the many ways to accomplish their objective before settling on one technique as part of their:
A)information gathering step.
B)need statement step.
C)project objectives step.
D)alternative analysis step.
A)information gathering step.
B)need statement step.
C)project objectives step.
D)alternative analysis step.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
39
As a highly successful college graduate you have no time to paint your house,so one of your old fraternity brothers offer to do the job for $2000.You have no idea what the actual cost of the materials might be,but $2000 seems reasonable and if the paint,brushes and dropcloths cost more,it comes out of his pocket.An added benefit is that it gets him off your couch in the afternoons,so you give him the go-ahead on this ________ contract between the two.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
40
When Marge agreed to help move her brother's worldly possessions from Omaha to Seattle she stipulated that at the end of the drive he would reimburse her for the truck rental,all gasoline,and road expenses and give her an additional $500,effectively creating a(n)________ contract between the two.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
41
The costs attached to subdeliverables:
A)are the summary of the work packages that support it.
B)are called phantom costs.
C)should be subtracted directly from deliverable costs.
D)are not recoverable unless explicitly stated in the work breakdown structure.
A)are the summary of the work packages that support it.
B)are called phantom costs.
C)should be subtracted directly from deliverable costs.
D)are not recoverable unless explicitly stated in the work breakdown structure.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
42
Expected commitments from other departments in support of the project would most likely be detailed in the:
A)approach section of the SOW.
B)risks and concerns section of the SOW.
C)acceptance criteria section of the SOW.
D)resource requirements section of the SOW.
A)approach section of the SOW.
B)risks and concerns section of the SOW.
C)acceptance criteria section of the SOW.
D)resource requirements section of the SOW.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
43
What are work breakdown structure elements that must be completed to conclude the project deliverables?
A)activities
B)tasks
C)work packages
D)milestones
A)activities
B)tasks
C)work packages
D)milestones
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
44
Which of these scope statement steps creates the all-important bureaucracy for a project?
A)the management plan
B)the work breakdown structure
C)the scope baseline
D)the project goal criteria
A)the management plan
B)the work breakdown structure
C)the scope baseline
D)the project goal criteria
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
45
Which of these statements about subdeliverables is best?
A)Subdeliverables have durations of their own.
B)Subdeliverables consume resources.
C)Subdeliverables have direct assignable costs.
D)Subdeliverables summarize the outcomes of work packages.
A)Subdeliverables have durations of their own.
B)Subdeliverables consume resources.
C)Subdeliverables have direct assignable costs.
D)Subdeliverables summarize the outcomes of work packages.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
46
The PMBoK definition stating,"a process that sets a project's scope by breaking down its overall mission into a cohesive set of synchronous,increasingly specific tasks," is for the:
A)project plan.
B)work breakdown structure.
C)deliverable statement.
D)scope expansion.
A)project plan.
B)work breakdown structure.
C)deliverable statement.
D)scope expansion.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
47
The new Magic Pan coming soon to your area usually serves 20,000 customers in the first year of operation.Construction plans include site selection,foundation,framing,finishing,egg-laying,and chicken acquisition.The scope statement step that determines relationships among these steps,e.g.does the chicken acquisition come before the egg laying,etc. ,is the:
A)project goal criteria.
B)management plan.
C)work breakdown structure.
D)scope baseline
A)project goal criteria.
B)management plan.
C)work breakdown structure.
D)scope baseline
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
48
Which of the following is NOT a project goal criteria?
A)cost
B)schedule
C)team membership
D)review and approval gates
A)cost
B)schedule
C)team membership
D)review and approval gates
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
49
Budget and schedule information for each activity in a project is contained in the:
A)project goal criteria.
B)management plan.
C)work breakdown structure.
D)scope baseline.
A)project goal criteria.
B)management plan.
C)work breakdown structure.
D)scope baseline.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
50
When a supporting document functions as a project control device throughout the project's development,it is not prepared in advance:
A)due to time constraints.
B)as it is a dynamic document.
C)since micromanaging can occur.
D)because control devices are left to project completion.
A)due to time constraints.
B)as it is a dynamic document.
C)since micromanaging can occur.
D)because control devices are left to project completion.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
51
A testing plan would be outlined in which section of a statement of work?
A)acceptance criteria
B)risks and concerns
C)description and scope
D)approach
A)acceptance criteria
B)risks and concerns
C)description and scope
D)approach
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
52
The highest level of work breakdown structure is the:
A)project.
B)deliverable.
C)subdeliverable.
D)work package.
A)project.
B)deliverable.
C)subdeliverable.
D)work package.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
53
The second level in work breakdown structure contains the:
A)projects.
B)deliverables.
C)subdeliverables.
D)work packages.
A)projects.
B)deliverables.
C)subdeliverables.
D)work packages.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
54
The final step in the process of systematically laying out all pre-work information is the creation of the:
A)scope baseline.
B)work breakdown structure.
C)management plan.
D)project goal criteria.
A)scope baseline.
B)work breakdown structure.
C)management plan.
D)project goal criteria.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
55
The mountaineers all agreed that their quest to build a bridge between the two peaks of Mount Kilimanjaro was a noble one,but they had no idea how long it would take to complete until they finished their:
A)project goal criteria.
B)work breakdown structure.
C)scope baseline.
D)management plan.
A)project goal criteria.
B)work breakdown structure.
C)scope baseline.
D)management plan.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
56
The organizational structure for the project team,including policies and procedures,is the:
A)work breakdown structure.
B)rules statement.
C)scope statement.
D)management plan.
A)work breakdown structure.
B)rules statement.
C)scope statement.
D)management plan.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
57
The description and scope section of a statement of work would contain statements regarding:
A)environmental risks.
B)termination of project information.
C)expected benefits.
D)major milestones.
A)environmental risks.
B)termination of project information.
C)expected benefits.
D)major milestones.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
58
Any measurable,tangible,verifiable outcome,result,or item that must be produced to complete a project or part of a project is a:
A)product.
B)deliverable.
C)tangible.
D)work product.
A)product.
B)deliverable.
C)tangible.
D)work product.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
59
In order to allocate costs more precisely,a company will assign:
A)bar codes to each activity.
B)activity codes to each subdeliverable.
C)WBS codes to each activity.
D)level 4 codes to each package element.
A)bar codes to each activity.
B)activity codes to each subdeliverable.
C)WBS codes to each activity.
D)level 4 codes to each package element.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
60
The lowest level in work breakdown structure contains the:
A)atoms.
B)activities.
C)finite elements.
D)work packages.
A)atoms.
B)activities.
C)finite elements.
D)work packages.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
61
Organizational breakdown structure (OBS)allows companies to:
A)assign the duties of tracking costs to the customer's accounting function.
B)circumvent the onerous task of work breakdown structure.
C)issue a preliminary TPS report.
D)define the work to be accomplished.
A)assign the duties of tracking costs to the customer's accounting function.
B)circumvent the onerous task of work breakdown structure.
C)issue a preliminary TPS report.
D)define the work to be accomplished.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
62
Which pair of statements is best?
A)Cost-plus contracts are prone to budget overruns while turnkey contracts are typically underbid by the contractor.
B)Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically underbid by the contractor.
C)Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically overbid by the contractor.
D)Cost-plus contracts are prone to budget overruns while turnkey contracts are typically overbid by the contractor.
A)Cost-plus contracts are prone to budget overruns while turnkey contracts are typically underbid by the contractor.
B)Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically underbid by the contractor.
C)Cost-plus contracts are prone to a budget surplus while turnkey contracts are typically overbid by the contractor.
D)Cost-plus contracts are prone to budget overruns while turnkey contracts are typically overbid by the contractor.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
63
Updates on how the project is performing against milestones can be accomplished by issuing a report containing:
A)S-curves.
B)schedule status.
C)earned value.
D)technical performance.
A)S-curves.
B)schedule status.
C)earned value.
D)technical performance.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
64
In the case of projects developed for external clients,work authorization typically addresses:
A)budget linkage.
B)audit trail establishment.
C)resource requirements.
D)contractual obligations.
A)budget linkage.
B)audit trail establishment.
C)resource requirements.
D)contractual obligations.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
65
Systems for monitoring the project's scope,schedule,and costs during the design stage fall under the heading of:
A)configuration control.
B)acquisition control.
C)design control.
D)specification control.
A)configuration control.
B)acquisition control.
C)design control.
D)specification control.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
66
The section of the contractual documentation that identifies what are the excusable delays,allowable costs,and criteria for inspection is called the:
A)bylaws.
B)amendments.
C)contracted terms.
D)dissolution factors.
A)bylaws.
B)amendments.
C)contracted terms.
D)dissolution factors.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
67
The exchange that is specified by the contractual documentation documents is:
A)the terms.
B)valid consideration.
C)reciprocity.
D)fair and unencumbered.
A)the terms.
B)valid consideration.
C)reciprocity.
D)fair and unencumbered.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
68
An earned value report shows:
A)how much money has actually been spent so far on the project.
B)slippages in performance measures for the work product.
C)the budgeted value of work performed.
D)slippages in time against planned measures.
A)how much money has actually been spent so far on the project.
B)slippages in performance measures for the work product.
C)the budgeted value of work performed.
D)slippages in time against planned measures.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
69
Project team members can identify who should be notified of task completion status by checking the:
A)control account.
B)linear responsibility chart.
C)statement of work.
D)monthly joint review report.
A)control account.
B)linear responsibility chart.
C)statement of work.
D)monthly joint review report.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
70
When work is organized into cost control accounts:
A)the work no longer needs to be tracked by the project manager.
B)the subdeliverables become cost centers instead of profit centers for the project.
C)these are assigned to the units performing project activities.
D)these budgets can then be assigned back to the project manager's department.
A)the work no longer needs to be tracked by the project manager.
B)the subdeliverables become cost centers instead of profit centers for the project.
C)these are assigned to the units performing project activities.
D)these budgets can then be assigned back to the project manager's department.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
71
Procedures that monitor emerging project scope against the original baseline scope are called:
A)configuration control.
B)design control.
C)trend monitoring.
D)document control.
A)configuration control.
B)design control.
C)trend monitoring.
D)document control.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
72
A young professor becomes obsessed with the latest release of Halo and completely loses sight of his research commitment to his colleagues,falling hopelessly behind schedule and consuming 80% of the department's computing budget.Addictive behavior notwithstanding,this sad tale would never have happened had:
A)configuration controls been established.
B)trend monitoring been regularly performed.
C)design controls been appropriately deployed.
D)document control been conducted assiduously.
A)configuration controls been established.
B)trend monitoring been regularly performed.
C)design controls been appropriately deployed.
D)document control been conducted assiduously.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
73
The reporting frequency,report recipients,and content required during project execution is laid out by:
A)the organizational breakdown structure.
B)scope reporting.
C)the information system architecture.
D)a need-to-know basis.
A)the organizational breakdown structure.
B)scope reporting.
C)the information system architecture.
D)a need-to-know basis.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
74
As the 80th change order floated across his desk,the project manager wished that he had kept the first 79.What money he had saved in scrap paper might well be lost in charges that could never be recouped from the client."What I need is better:
A)trend monitoring," muttered the manager.
B)configuration control," sighed the manager.
C)specification control," fumed the manager.
D)document control," whimpered the manager.
A)trend monitoring," muttered the manager.
B)configuration control," sighed the manager.
C)specification control," fumed the manager.
D)document control," whimpered the manager.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
75
A project management firm that promises to do everything for a major project and hand over a fully functional,ready-to-use deliverable is performing under a(n):
A)umbrella contract.
B)all-inclusive contract.
C)cost-plus contract.
D)turnkey contract.
A)umbrella contract.
B)all-inclusive contract.
C)cost-plus contract.
D)turnkey contract.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
76
Your professor moonlights to make ends meet during the summer months and has a knack for painting houses.You agree to pay $500 over whatever the materials and equipment rental cost for the job and delight in sipping lemonade in the shade watching your poor professor perform under a(n):
A)cost-plus contract.
B)lump-sum contract.
C)time and material contract.
D)fixed wage contract.
A)cost-plus contract.
B)lump-sum contract.
C)time and material contract.
D)fixed wage contract.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
77
A project manager can identify personnel who will be directly responsible for each task in the project's development by using a(n):
A)responsibility assignment matrix.
B)milestone designation chart.
C)Merrill report.
D)work package report.
A)responsibility assignment matrix.
B)milestone designation chart.
C)Merrill report.
D)work package report.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
78
The step that reflects the formal "go ahead" given to the project to commence once the scope definition,planning documents,and other contractual documents have been prepared and approved is the:
A)go ahead.
B)send off.
C)work authorization.
D)work release.
A)go ahead.
B)send off.
C)work authorization.
D)work release.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
79
All projects are promised in terms of the specific functionality or performance criteria they will meet.The key feature of the contractual documentation that specifies this functionality or criteria is the:
A)contractual requirements.
B)valid consideration.
C)contracted terms.
D)contractual performance.
A)contractual requirements.
B)valid consideration.
C)contracted terms.
D)contractual performance.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck
80
An S-curve report does NOT contain information on:
A)time.
B)cost.
C)budget.
D)quality.
A)time.
B)cost.
C)budget.
D)quality.
Unlock Deck
Unlock for access to all 116 flashcards in this deck.
Unlock Deck
k this deck