Deck 6: Resource Utilization

Full screen (f)
exit full mode
Question
Resource leveling, or smoothing, levels the resources so that

A) equal number of resources is assigned to each task.
B) an equal number of tasks are completed each day by the resources on the project.
C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
D) the costs for the resources are even as possible across the project.
Use Space or
up arrow
down arrow
to flip the card.
Question
The start of noncritical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to

A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.
Question
In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?

A) Activities that use the same resource may not be able to occur in parallel to each other.
B) Activities that use different resources may be shown in a serial relationship.
C) The activities could be shown in a loop relationship.
D) Resources that are unlimited are not shown in a resource assignment.
Question
Why are activities drawn in a serial relationship in a network diagram?

A) The activities use different resources.
B) The activities are independent of each other.
C) From a technical standpoint, the activities must be performed in that sequence.
D) The order of completion doesn't matter.
Question
The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because

A) each of the activities are independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Question
Resource utilization charts based on each activity's latest start time are said to be based

A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Question
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.
What is the least amount of time that the project can be completed and how many resources are required to complete the work?

A) 16 days, 7 workers
B) 7 days, 5 workers
C) 5 days, 7 workers
D) 8 days, 3 workers
Question
Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.

A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.
Question
Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to

A) increase costs of all the activities in the project.
B) extend beyond the project completion time.
C) be completed ahead of schedule.
D) increase its requirements for additional resources for all activities.
Question
________ assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.

A) Project management information systems
B) Formulas and techniques
C) Trial and error techniques
D) Calendaring systems
Question
Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.
Question
In resource-limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the project?

A) The delaying of activities increases the costs of the project.
B) The delaying of activities decreases the acceptance of the project deliverable.
C) The delaying of activities may delay the project.
D) The delaying of activities helps give others more time on their tasks because they won't affect the project schedule.
Question
Resource utilization charts based on each activity's earliest start time are said to be based

A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Question
When several activities need the same limited resource at the same time, the activities with

A) the least slack have first priority.
B) the longest duration have first priority.
C) the near term have first priority.
D) use the most resources have first priority.
Question
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.
If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?

A) day 18
B) day 3
C) day 10
D) day 9
Question
If resources are to be considered in planning, it is necessary to

A) when each is taking vacation time or time off.
B) know the name of each resource on the project.
C) list all the projects to which the resources have been assigned.
D) indicate the amounts and types of resources needed to perform each activity.
Question
Resource leveling, or smoothing, is a method for

A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.
Question
Which of following would allow for level resources on the project?

A) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
B) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
C) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
D) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
Question
Resource-limited scheduling is a method for

A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
Question
A resource requirements plan illustrates

A) who is responsible for which activities.
B) the amount of labor expenses for the project.
C) the expected utilization of resources by time period during the time span of the project.
D) the budget for material and cost resources.
Question
This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
<strong>This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.  </strong> A) Paths would be 1,2,3,5 and 1,2,4 B) Paths would be 1,2,3,4 and 1,2,5 C) Paths would be 1,2 and 3,4,5 D) Path would be 1,2,3,4,5 <div style=padding-top: 35px>

A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/21
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Resource Utilization
1
Resource leveling, or smoothing, levels the resources so that

A) equal number of resources is assigned to each task.
B) an equal number of tasks are completed each day by the resources on the project.
C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
D) the costs for the resources are even as possible across the project.
C
2
The start of noncritical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to

A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.
D
3
In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?

A) Activities that use the same resource may not be able to occur in parallel to each other.
B) Activities that use different resources may be shown in a serial relationship.
C) The activities could be shown in a loop relationship.
D) Resources that are unlimited are not shown in a resource assignment.
A
4
Why are activities drawn in a serial relationship in a network diagram?

A) The activities use different resources.
B) The activities are independent of each other.
C) From a technical standpoint, the activities must be performed in that sequence.
D) The order of completion doesn't matter.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
5
The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because

A) each of the activities are independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
6
Resource utilization charts based on each activity's latest start time are said to be based

A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
7
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.
What is the least amount of time that the project can be completed and how many resources are required to complete the work?

A) 16 days, 7 workers
B) 7 days, 5 workers
C) 5 days, 7 workers
D) 8 days, 3 workers
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
8
Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.

A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
9
Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to

A) increase costs of all the activities in the project.
B) extend beyond the project completion time.
C) be completed ahead of schedule.
D) increase its requirements for additional resources for all activities.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
10
________ assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.

A) Project management information systems
B) Formulas and techniques
C) Trial and error techniques
D) Calendaring systems
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
11
Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
12
In resource-limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the project?

A) The delaying of activities increases the costs of the project.
B) The delaying of activities decreases the acceptance of the project deliverable.
C) The delaying of activities may delay the project.
D) The delaying of activities helps give others more time on their tasks because they won't affect the project schedule.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
13
Resource utilization charts based on each activity's earliest start time are said to be based

A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
14
When several activities need the same limited resource at the same time, the activities with

A) the least slack have first priority.
B) the longest duration have first priority.
C) the near term have first priority.
D) use the most resources have first priority.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
15
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.
If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?

A) day 18
B) day 3
C) day 10
D) day 9
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
16
If resources are to be considered in planning, it is necessary to

A) when each is taking vacation time or time off.
B) know the name of each resource on the project.
C) list all the projects to which the resources have been assigned.
D) indicate the amounts and types of resources needed to perform each activity.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
17
Resource leveling, or smoothing, is a method for

A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
18
Which of following would allow for level resources on the project?

A) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)
B) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)
C) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)
D) <strong>Which of following would allow for level resources on the project?</strong> A)   B)   C)   D)
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
19
Resource-limited scheduling is a method for

A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
20
A resource requirements plan illustrates

A) who is responsible for which activities.
B) the amount of labor expenses for the project.
C) the expected utilization of resources by time period during the time span of the project.
D) the budget for material and cost resources.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
21
This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
<strong>This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.  </strong> A) Paths would be 1,2,3,5 and 1,2,4 B) Paths would be 1,2,3,4 and 1,2,5 C) Paths would be 1,2 and 3,4,5 D) Path would be 1,2,3,4,5

A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5