Deck 3: Cost Assignment
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/52
Play
Full screen (f)
Deck 3: Cost Assignment
1
An activity-based costing system uses which of the following procedures?
A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
B
2
Figure 3-1
The Xiang plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 50,000 direct labour hours. The following data have been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.
-Refer to Figure 3-1. Using direct labour hours to assign overhead, the total cost of the potential job would be
A)£2,500.
B)£5,500.
C)£4,000.
D)£4,500.
The Xiang plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 50,000 direct labour hours. The following data have been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.
-Refer to Figure 3-1. Using direct labour hours to assign overhead, the total cost of the potential job would be
A)£2,500.
B)£5,500.
C)£4,000.
D)£4,500.
£4,500.
3
Refer to Figure 3-3. What is the amount of overhead cost to be assigned to Product X using machine hours as the activity driver in an activity-based costing system?
A)£12,000
B)£60,000
C)£48,000
D)£16,800
A)£12,000
B)£60,000
C)£48,000
D)£16,800
£12,000
4
Figure 3-4
Quint Manufacturing uses an activity-based costing system. The company produces Model 1 and Model 2. Information relating to the two products is as follows: The following costs are reported:
-Refer to Figure 3-4. Setup costs assigned to Model 2 are
A)£36,000.
B)£35,000.
C)£28,000.
D)£25,000.
Quint Manufacturing uses an activity-based costing system. The company produces Model 1 and Model 2. Information relating to the two products is as follows: The following costs are reported:
-Refer to Figure 3-4. Setup costs assigned to Model 2 are
A)£36,000.
B)£35,000.
C)£28,000.
D)£25,000.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
5
Zang Manufacturing Company manufactures two products (A and B). The overhead costs (£58,000) have been divided into three cost pools that use the following activity cost drivers:
What is the allocation rate per order using ABC?
A)£10,000
B)£2,320
C)£400
D)£58,000
What is the allocation rate per order using ABC?
A)£10,000
B)£2,320
C)£400
D)£58,000
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
6
Figure 3-4
Quint Manufacturing uses an activity-based costing system. The company produces Model 1 and Model 2. Information relating to the two products is as follows: The following costs are reported:
-Refer to Figure 3-4. Labour-related overhead costs assigned to Model 1 are
A)£60,000.
B)£58,000.
C)£54,400.
D)£48,000.
Quint Manufacturing uses an activity-based costing system. The company produces Model 1 and Model 2. Information relating to the two products is as follows: The following costs are reported:
-Refer to Figure 3-4. Labour-related overhead costs assigned to Model 1 are
A)£60,000.
B)£58,000.
C)£54,400.
D)£48,000.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
7
Figure 3-6
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead, the total amount of overhead allocated to the proposed job would be
A)£37,830.
B)£39,850.
C)£41,830.
D)£44,913.
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead, the total amount of overhead allocated to the proposed job would be
A)£37,830.
B)£39,850.
C)£41,830.
D)£44,913.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
8
Traditional-based product costing uses which of the following procedures?
A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
9
Refer to Figure 3-3. What is the allocation rate per packing order using activity-based costing?
A)£15,000
B)£60
C)£7,500
D)£200
A)£15,000
B)£60
C)£7,500
D)£200
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
10
When applied overhead exceeds actual overhead cost,
A)over-applied(absorbed) overhead is added to cost of goods sold.
B)overapplied overhead is deducted from cost of goods sold.
C)underapplied overhead is added to cost of goods sold.
D)underapplied overhead is deducted from cost of goods sold.
A)over-applied(absorbed) overhead is added to cost of goods sold.
B)overapplied overhead is deducted from cost of goods sold.
C)underapplied overhead is added to cost of goods sold.
D)underapplied overhead is deducted from cost of goods sold.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
11
When actual overhead cost exceeds overhead applied to production,
A)over-absorbed overhead is added to cost of goods sold.
B)over-absorbed overhead is deducted from cost of goods sold.
C)under-absorbed overhead is added to cost of goods sold.
D)under-absorbed overhead is deducted from cost of goods sold.
A)over-absorbed overhead is added to cost of goods sold.
B)over-absorbed overhead is deducted from cost of goods sold.
C)under-absorbed overhead is added to cost of goods sold.
D)under-absorbed overhead is deducted from cost of goods sold.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
12
Figure 3-7
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite, Inc., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 500 would be
A)£53.15.
B)£54.15.
C)£56.67.
D)£57.15.
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite, Inc., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 500 would be
A)£53.15.
B)£54.15.
C)£56.67.
D)£57.15.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
13
Figure 3-6
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead and the company's bid is full cost plus 10 per cent, the company's bid would be
A)£108,804.
B)£105,413.
C)£103,235.
D)£101,013.
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead and the company's bid is full cost plus 10 per cent, the company's bid would be
A)£108,804.
B)£105,413.
C)£103,235.
D)£101,013.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
14
Figure 3-6
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead, the total cost of the proposed job would be
A)£98,913.
B)£95,830.
C)£93,850.
D)£91,830.
Ray Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 10 percent.
Estimates for the proposed job are as follows: The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers. Expected activity for the four activity-based cost drivers that would be used are as follows:
-Refer to Figure 3-6. If Ray Manufacturing used activity-based cost drivers to assign overhead, the total cost of the proposed job would be
A)£98,913.
B)£95,830.
C)£93,850.
D)£91,830.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
15
More accurate product costing information is produced by assigning costs using
A)volume-based, plantwide rates.
B)volume-based, departmental rates.
C)activity-based pool rates.
D)All of the above produce accurate product costing information.
A)volume-based, plantwide rates.
B)volume-based, departmental rates.
C)activity-based pool rates.
D)All of the above produce accurate product costing information.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
16
The calculation of unit costs is important for
A)inventory valuation.
B)income determination.
C)pricing.
D)all of the above.
A)inventory valuation.
B)income determination.
C)pricing.
D)all of the above.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
17
Figure 3-1
The Xiang plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 50,000 direct labour hours. The following data have been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.
-Refer to Figure 3-1. Using activity-based costing and the appropriate activity drivers, the total cost of the potential job would be
A)£1,200.
B)£1,800.
C)£3,700.
D)£3,875.
The Xiang plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 50,000 direct labour hours. The following data have been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.
-Refer to Figure 3-1. Using activity-based costing and the appropriate activity drivers, the total cost of the potential job would be
A)£1,200.
B)£1,800.
C)£3,700.
D)£3,875.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
18
Figure 3-5
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.
-Refer to Figure 3-5. Using direct labour hours to assign overhead, the total cost of the potential job would be
A)£9,500.
B)£6,000.
C)£3,000.
D)£1,600.
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.
-Refer to Figure 3-5. Using direct labour hours to assign overhead, the total cost of the potential job would be
A)£9,500.
B)£6,000.
C)£3,000.
D)£1,600.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
19
Figure 3-5
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.
-Refer to Figure 3-5. Using activity-based costing and the appropriate cost drivers, the total cost of the potential job would be
A)£9,230.
B)£8,180.
C)£2,250.
D)£1,680.
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job: Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.
-Refer to Figure 3-5. Using activity-based costing and the appropriate cost drivers, the total cost of the potential job would be
A)£9,230.
B)£8,180.
C)£2,250.
D)£1,680.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
20
Figure 3-7
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite, Inc., used activity-based cost drivers to allocate overhead costs, the total cost of Job 500 would be
A)£5,715.
B)£5,667.
C)£5,415.
D)£5,315.
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite, Inc., used activity-based cost drivers to allocate overhead costs, the total cost of Job 500 would be
A)£5,715.
B)£5,667.
C)£5,415.
D)£5,315.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
21
Support department costs are accounted for in which one of the following ways?
A)They are allocated directly to units of product.
B)They are allocated to producing departments and then allocated to units of product.
C)They are allocated to units of product and then allocated to the producing departments.
D)They are expensed as incurred.
A)They are allocated directly to units of product.
B)They are allocated to producing departments and then allocated to units of product.
C)They are allocated to units of product and then allocated to the producing departments.
D)They are expensed as incurred.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
22
The method of accounting for inventory that assigns all manufacturing costs to inventory is sometimes referred to as:
A)absorption costing.
B)FIFO.
C)the weighted average cost method.
D)conversion costing.
A)absorption costing.
B)FIFO.
C)the weighted average cost method.
D)conversion costing.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
23
A possible causal factor to use when allocating cafeteria costs would be
A)number of square feet.
B)number of direct labour hours.
C)number of employees.
D)appraised value of square footage.
A)number of square feet.
B)number of direct labour hours.
C)number of employees.
D)appraised value of square footage.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
24
Which of the following allocation methods fully recognizes services that support departments provide to each other?
A)direct method
B)sequential method
C)reciprocal method
D)all of the above
A)direct method
B)sequential method
C)reciprocal method
D)all of the above
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
25
Which of the following is a reason to accumulate and separately assign costs by departments?
A)The company wants to reduce the complexity of its cost accounting system.
B)The company is comprised of multiple departments, each of which exhibit unique cost behaviour patterns.
C)The company wishes to implement an activity based costing system.
D)The company has a large amount of capital invested in human resource training.
A)The company wants to reduce the complexity of its cost accounting system.
B)The company is comprised of multiple departments, each of which exhibit unique cost behaviour patterns.
C)The company wishes to implement an activity based costing system.
D)The company has a large amount of capital invested in human resource training.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
26
Which of the following methods of assigning costs is based on convenience or some assumed linkage, and reduces the overall accuracy of the cost assignments?
A)direct tracing
B)cost driver tracing
C)allocation
D)all of the above
A)direct tracing
B)cost driver tracing
C)allocation
D)all of the above
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
27
Which of the following is a key consideration in selecting an allocation base?
A)The allocation base should have an indirect association with the cost objective.
B)The allocation base should be difficult to measure.
C)There should be logical association between the allocation base and the incidence of costs.
D)The allocation base should be out of the control of management.
A)The allocation base should have an indirect association with the cost objective.
B)The allocation base should be difficult to measure.
C)There should be logical association between the allocation base and the incidence of costs.
D)The allocation base should be out of the control of management.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
28
The optimal level in the trade-off between measurement and error costs is when
A)measurement costs are greater than error costs.
B)measurement costs are less than error costs.
C)measurement costs equal error costs.
D)the total of measurement costs and error costs are maximized.
A)measurement costs are greater than error costs.
B)measurement costs are less than error costs.
C)measurement costs equal error costs.
D)the total of measurement costs and error costs are maximized.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
29
Support departments
A)are responsible for manufacturing the products sold to customers.
B)work directly on the products of the firm.
C)provide services directly to customers.
D)provide essential services to the producing departments.
A)are responsible for manufacturing the products sold to customers.
B)work directly on the products of the firm.
C)provide services directly to customers.
D)provide essential services to the producing departments.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
30
Examples of producing departments include all of the following EXCEPT
A)mixing.
B)molding.
C)packaging.
D)accounting.
A)mixing.
B)molding.
C)packaging.
D)accounting.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
31
Examples of support departments include all of the following EXCEPT
A)maintenance.
B)personnel.
C)machining.
D)data processing.
A)maintenance.
B)personnel.
C)machining.
D)data processing.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
32
Oaks Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two producing departments, P1 and P2. The Maintenance Department costs of £30,000 are allocated on the basis of standard service used. The Personnel Department costs of £4,500 are allocated on the basis of number of employees. The direct costs of Departments P1 and P2 are £9,000 and £15,000, respectively. Data on standard service hours and number of employees are as follows: Using the sequential method, if the support department with the highest percentage of interdepartmental service is allocated first, the cost of the support departments allocated to Department P1 is
A)£12,750.
B)£24,000.
C)£20,295.
D)£21,750.
A)£12,750.
B)£24,000.
C)£20,295.
D)£21,750.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
33
Which of the following principles should be applied when the step method of allocating service department costs is used?
A)The sequence of allocation among departments should be randomly selected.
B)The sequence of allocation among departments should proceed from the largest department as measured by total assets to the smallest.
C)The sequence of allocation among departments should proceed from the largest provider of interdepartmental services to the smallest.
D)All possible sequences of service department allocations should be computed. The sequence that provides the largest allocation of service costs should then be selected.
A)The sequence of allocation among departments should be randomly selected.
B)The sequence of allocation among departments should proceed from the largest department as measured by total assets to the smallest.
C)The sequence of allocation among departments should proceed from the largest provider of interdepartmental services to the smallest.
D)All possible sequences of service department allocations should be computed. The sequence that provides the largest allocation of service costs should then be selected.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
34
____ is (are) a method of allocating service department costs that gives partial recognition to interdepartmental services by using a methodology that allocates service department costs sequentially both to the remaining service departments and the producing departments.
A)The direct method
B)The step method
C)The linear algebra method
D)The direct and step methods
A)The direct method
B)The step method
C)The linear algebra method
D)The direct and step methods
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following departments is NOT a support department?
A)food services
B)bottling
C)health services
D)security
A)food services
B)bottling
C)health services
D)security
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
36
Figure 3-7
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite's direct labour hours are used to assign overhead, the unit cost for Job 500 would be
A)£104.
B)£105.
C)£114.
D)£119.
Granite, Inc., has identified the following overhead costs and cost drivers for next year: The following are two of the jobs completed during the year: The company's normal activity is 4,000 direct labour hours.
-Refer to Figure 3-7. If Granite's direct labour hours are used to assign overhead, the unit cost for Job 500 would be
A)£104.
B)£105.
C)£114.
D)£119.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
37
Staff Company allocates common Building Department costs to producing departments (P1 and P2) based on space occupied, and it allocates common Personnel Department costs based on the number of employees. Space occupancy and employee data are as follows: If Staff Company uses the sequential allocation method and the support department with the highest percentage of interdepartmental services is allocated first, the ratio representing the portion of Personnel Department costs allocated to Department P2 is
A)50/146.
B)90/140.
C)50/140.
D)50/130.
A)50/146.
B)90/140.
C)50/140.
D)50/130.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
38
Service departments:
A)are responsible for manufacturing the products sold to customers.
B)work directly on the firm's products.
C)provide services directly to customers.
D)provide support services to the producing departments.
A)are responsible for manufacturing the products sold to customers.
B)work directly on the firm's products.
C)provide services directly to customers.
D)provide support services to the producing departments.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
39
Which of the following characteristics is a consequence of the implementation of a plant-wide allocation rate?
A)The uniqueness of individual departments is not reflected in the cost numbers.
B)Allocations are first conducted among departments, and then aggregated for the plant as a whole.
C)Downstream costs are not measured at all.
D)Managers have absolutely no incentive to control costs.
A)The uniqueness of individual departments is not reflected in the cost numbers.
B)Allocations are first conducted among departments, and then aggregated for the plant as a whole.
C)Downstream costs are not measured at all.
D)Managers have absolutely no incentive to control costs.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
40
Which of the following accurately describes advantages and disadvantages of employing a system of allocation that uses a plant-wide rate?
A)The plant-wide rate approach is the simplest to apply, but it is also the most costly to implement.
B)The plant-wide rate approach is the simplest to apply, but most likely provides the least accurate product costs.
C)The plant-wide rate may be straightforward, but it is not appropriate for small businesses that offer a single service or product.
D)The plant-wide rate really offers no advantage whatsoever.
A)The plant-wide rate approach is the simplest to apply, but it is also the most costly to implement.
B)The plant-wide rate approach is the simplest to apply, but most likely provides the least accurate product costs.
C)The plant-wide rate may be straightforward, but it is not appropriate for small businesses that offer a single service or product.
D)The plant-wide rate really offers no advantage whatsoever.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
41
The support departments typically found in manufacturing and nonmanufacturing organizations are as follows: Cafeteria
Personnel
Maintenance
Purchasing
Accounting
Personnel
Maintenance
Purchasing
Accounting
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
42
Parkes Manufacturing has four categories of overhead. The four categories and the expected overhead costs for each category for next year are as follows: Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labour hours. For next year, 100,000 direct labour hours are budgeted.
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 25 per cent.
Estimates for the proposed job are as follows: In the past, full manufacturing cost has been calculated by allocating overhead using a traditional volume-based cost driver system--direct labour hours. The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers.
Expected activity for the four activity-based cost drivers that would be used are as follows:
a.Determine the amount of overhead that would be allocated to the proposed job if direct labour hours are used as the cost driver.Determine the total cost of the proposed job.Determine the company's bid if the bid is based upon full manufacturing cost plus 25 per cent.
b.Determine the amount of overhead that would be applied to the proposed project if activity-based costing is used.Determine the total cost of the proposed job if activity-based costing is used.Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 25 per cent.
c.Which product costing method produces the more competitive bid?
The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually bids are based upon full manufacturing cost plus 25 per cent.
Estimates for the proposed job are as follows: In the past, full manufacturing cost has been calculated by allocating overhead using a traditional volume-based cost driver system--direct labour hours. The plant manager has heard of a new way of applying overhead that uses cost pools and cost drivers.
Expected activity for the four activity-based cost drivers that would be used are as follows:
a.Determine the amount of overhead that would be allocated to the proposed job if direct labour hours are used as the cost driver.Determine the total cost of the proposed job.Determine the company's bid if the bid is based upon full manufacturing cost plus 25 per cent.
b.Determine the amount of overhead that would be applied to the proposed project if activity-based costing is used.Determine the total cost of the proposed job if activity-based costing is used.Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 25 per cent.
c.Which product costing method produces the more competitive bid?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
43
Although adding more activity cost pools to an activity-based costing system may improve the accuracy of product costing, this increase in accuracy must be judged against:
A)the cost of the product.
B)the price of the product.
C)the cost of developing and maintaining the additional cost pools.
D)all of the above.
A)the cost of the product.
B)the price of the product.
C)the cost of developing and maintaining the additional cost pools.
D)all of the above.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
44
Rounders Company used the following information when determining the appropriate overhead rates to use in its two production departments:
Two of the products in the product line were as follows:
a.Assume that Rounders applies overhead using a plantwide rate based on direct labour hours. Determine the unit cost of Products 1 and 2.
b.Assume that Rounders uses direct labour hours to apply overhead in the Fabrication Department and machine hours to apply overhead in the Assembly Department. Determine the unit cost of Products 1 and 2.
Two of the products in the product line were as follows:
a.Assume that Rounders applies overhead using a plantwide rate based on direct labour hours. Determine the unit cost of Products 1 and 2.
b.Assume that Rounders uses direct labour hours to apply overhead in the Fabrication Department and machine hours to apply overhead in the Assembly Department. Determine the unit cost of Products 1 and 2.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
45
Ernest, Inc., has identified the following overhead costs and cost drivers for next year:
The following are two of the jobs completed during the year:
The company's normal activity is 32,000 direct labour hours. (Round amounts to two decimal places.)
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers.
c.Which method produces the more accurate cost assignment? Why?


a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers.
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
46
Fox Company has two support departments (S1 and S2) and two producing departments (P1 and P2). Estimated direct costs and percentages of services used by these departments are as follows:
a.Prepare a schedule allocating the support department costs to the producing departments using the direct allocation method.
b.Prepare a schedule allocating the support department costs to the producing departments using the sequential allocation method.
a.Prepare a schedule allocating the support department costs to the producing departments using the direct allocation method.
b.Prepare a schedule allocating the support department costs to the producing departments using the sequential allocation method.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
47
Lyons, Inc., has identified the following overhead costs and activity drivers for next year:
The following are two of the jobs completed during the year:
The company's normal activity is 20,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four activity drivers. (Round amounts to 2 decimal places.)
c.Which method produces the more accurate cost assignment? Why?


a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four activity drivers. (Round amounts to 2 decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
48
Manchester Ltd. uses a job-order costing system and a predetermined overhead rate based on machine hours.
At the beginning of the year, the company estimated manufacturing overhead for the year would be £135,000 and 9,000 machine hours would be used.
The following information pertains to December of the current year: Actual manufacturing overhead costs incurred in December were £31,000.
a.Compute the predetermined overhead application rate.
b.Determine the total cost associated with each job.
At the beginning of the year, the company estimated manufacturing overhead for the year would be £135,000 and 9,000 machine hours would be used.
The following information pertains to December of the current year: Actual manufacturing overhead costs incurred in December were £31,000.
a.Compute the predetermined overhead application rate.
b.Determine the total cost associated with each job.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
49
Hunter Company manufactures two products (XX and YY). The overhead costs have been divided into four cost pools that use the following activity drivers:
a.Compute the allocation rates for each of the activity drivers listed.
b.Allocate the overhead costs to Products XX and YY using activity-based costing.
c.Compute the overhead rate using labour hours under the traditional functional-based costing system.
d.Allocate the overhead costs to Products XX and YY using the traditional functional-based costing system overhead rate calculated in part (c).
a.Compute the allocation rates for each of the activity drivers listed.
b.Allocate the overhead costs to Products XX and YY using activity-based costing.
c.Compute the overhead rate using labour hours under the traditional functional-based costing system.
d.Allocate the overhead costs to Products XX and YY using the traditional functional-based costing system overhead rate calculated in part (c).
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
50
Gray Enterprises has two support departments (S1 and S2) and two producing departments (A and B). The distribution of services by the support departments is as follows:
Total department costs for the support and producing departments are as follows:
Total department costs for the support and producing departments are as follows:
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
51
The Jewell plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: The plant currently applies overhead using direct labour hours and expected capacity of 100,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job. Bid prices are calculated as full manufacturing cost plus a 20 per cent markup. Total expected machine hours for all jobs during the year is 60,000, and the total expected number of inspections is 4,000.
a.Compute the total cost of the potential job using direct labour hours to assign overhead.Determine the bid price for the potential job.
b.Compute the total cost of the job using activity-based costing and the appropriate activity drivers.Determine the bid price if activity-based costing is used.
c.Prepare a memorandum to the plant manager recommending a bid price for the potential job. Support your recommendation by explaining which costing method best reflects the actual cost of the job.
a.Compute the total cost of the potential job using direct labour hours to assign overhead.Determine the bid price for the potential job.
b.Compute the total cost of the job using activity-based costing and the appropriate activity drivers.Determine the bid price if activity-based costing is used.
c.Prepare a memorandum to the plant manager recommending a bid price for the potential job. Support your recommendation by explaining which costing method best reflects the actual cost of the job.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
52
Holbrook, Inc., has identified the following overhead costs and cost drivers for next year:
The following are two of the jobs completed during the year:
The company's normal activity is 40,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.)
c.Which method produces the more accurate cost assignment? Why?


a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck