Deck 11: Activity-Based Costing

Full screen (f)
exit full mode
Question
If activity-based costing is used, setups would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Use Space or
up arrow
down arrow
to flip the card.
Question
All of the following are nonunit-based activity drivers EXCEPT

A)number of setups.
B)number of direct labour hours.
C)number of inspections.
D)number of material moves.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the unit-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)machining
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the facility-level activity(ies)?

A)providing utilities
B)providing space
C)inspecting
D)both a and b
Question
Figure 11-1
Ubben Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information relating to the two products is as follows:  Model X  Model Y  Units produced 20,00040,000 Machine hours 8,00010,000 Direct labour hours 14,00016,000 Engineering labour (hours) 1,0001,400 Setups 4060\begin{array}{lll}&\text { Model X } & \text { Model Y } \\\text { Units produced } & 20,000 & 40,000 \\\text { Machine hours } & 8,000 & 10,000 \\\text { Direct labour hours } & 14,000 & 16,000 \\\text { Engineering labour (hours) } & 1,000 & 1,400 \\\text { Setups } & 40 & 60\end{array} The following costs are reported:  Engineering £48,000 Setups 100,000 Machine-rel ated overhead 144,000\begin{array}{ll}\text { Engineering } & £ 48,000 \\\text { Setups } & 100,000 \\\text { Machine-rel ated overhead } & 144,000\end{array}

-Refer to Figure 11-1. Setups would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Question
Riley, SA., has identified the following overhead costs and activity drivers for next year:  Expected  Expected  Overhead Item  Cost  Activity Driver  Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array}{lclc}\text { Expected }&&\text { Expected }\\\text { Overhead Item }&\text { Cost } & \text { Activity Driver } & \text { Quantity }\\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year: Job AAJob BB  Direct materials £375£1,000 Direct labour £350£1,200 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\mathrm{Job} \text { AA} &\mathrm{Job} \text { BB }\\\text { Direct materials } & £ 375 & £ 1,000 \\\text { Direct labour } & £ 350 & £ 1,200 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array} The company's normal activity is 4,000 direct labour hours. If the activity drivers are used to allocate overhead costs, the unit cost (rounded to two decimal places) for Job BB would be

A)£21.40.
B)£26.56.
C)£26.95.
D)£27.03.
Question
All of the following are unit-based activity drivers EXCEPT

A)machine hours.
B)number of setups.
C)number of units.
D)direct labour hours.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the product-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)none of the above
Question
If activity-based costing is used, insurance on the plant would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Question
Maintenance of the production equipment would be classified as a

A)unit-level activity.
B)product-level activity.
C)cell-level activity.
D)facility-level activity.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool overhead rate for the unit-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Question
If activity-based costing is used, electricity usage would be an example of a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the batch-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Question
Which of the following quantities is an example of an activity driver in activity-based costing?

A)number of setups
B)number of orders placed
C)number of machine hours
D)all of the above
Question
If activity-based costing is used, product inspections would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Question
Figure 11-1
Ubben Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information relating to the two products is as follows:  Model X  Model Y  Units produced 20,00040,000 Machine hours 8,00010,000 Direct labour hours 14,00016,000 Engineering labour (hours) 1,0001,400 Setups 4060\begin{array}{lll}&\text { Model X } & \text { Model Y } \\\text { Units produced } & 20,000 & 40,000 \\\text { Machine hours } & 8,000 & 10,000 \\\text { Direct labour hours } & 14,000 & 16,000 \\\text { Engineering labour (hours) } & 1,000 & 1,400 \\\text { Setups } & 40 & 60\end{array} The following costs are reported:  Engineering £48,000 Setups 100,000 Machine-rel ated overhead 144,000\begin{array}{ll}\text { Engineering } & £ 48,000 \\\text { Setups } & 100,000 \\\text { Machine-rel ated overhead } & 144,000\end{array}

-Refer to Figure 11-1. Machine-related overhead would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the batch-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)all of the above
Question
The use of unit-based activity drivers to assign costs tends to

A)overcost low-volume products.
B)overcost high-volume products.
C)undercost all products.
D)overcost all products.
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the facility-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Question
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the product-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)none of the above
Question
Which of the following items would be classified as committed resources (short-term)?

A)salaried employees
B)depreciation on building
C)fuel to generate electricity internally
D)lease on machinery
Question
Resources that are only purchased precisely at the time the resource is needed are called

A)committed resources.
B)flexible resources.
C)scarce resources.
D)none of the above.
Question
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the training employees activity?

A)£27,500
B)£125,000
C)£31,250
D)£81,250
Question
The overhead rates of the traditional-based approach to product costing use

A)nonunit-based cost drivers.
B)unit-based cost drivers.
C)process costing.
D)job-order costing.
Question
What is the initial step in implementing an activity-based costing system?

A)assigning costs to activities
B)assigning costs to products
C)identifying activities and attributes
D)dividing activity costs by activity drivers
Question
Basing overhead allocation solely on volume

A)will undercost high-volume products and overcost low-volume products.
B)will overcost high-volume products and undercost low-volume products.
C)is the sole basis of the activity-based costing model.
D)All of the above are correct.
Question
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the improving processes activity?

A)£250,000
B)£25,000
C)£43,750
D)£51,000
Question
An example of a nonunit-level driver is

A)pounds of direct materials.
B)number of setups.
C)number of machine hours where each product manufactured requires one machine hour.
D)number of labour hours.
Question
An example of a production or unit-level driver is

A)pounds of direct materials.
B)number of setups.
C)number of batches.
D)number of product lines.
Question
Which of the following items would be classified as committed resources (long-term)?

A)salaried employees
B)depreciation on building
C)lease on machinery
D)both b and c
Question
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the creating BOMs activity?

A)£31,250
B)£7,500
C)£43,750
D)£125,000
Question
An activity-based cost system

A)differs from a traditional-based cost system in the nature and number of the cost drivers used.
B)uses both unit-based and nonunit-based cost drivers that reflect a cause-and-effect relationship.
C)can trace cost accurately to cost objects other than products.
D)does all of the above.
Question
Committed resources are

A)hard to purchase.
B)purchased precisely at the time the resource is needed and have no unused capacity.
C)supplied in advance of usage and may have unused capacity.
D)none of the above.
Question
An activity-based costing system uses which of the following procedures?

A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
Question
Which of the following items would be classified as flexible resources?

A)salaried employees
B)depreciation on building
C)fuel to generate electricity internally
D)lease on machinery
Question
An activity cost driver is

A)a factor that causes variations in a cost.
B)another term for input measure.
C)the largest single category of cost in a company.
D)a variable cost.
Question
More accurate product costing information is produced by assigning costs using

A)volume-based, plantwide rates.
B)volume-based, departmental rates.
C)activity-based pool rates.
D)All of the above produce accurate product costing information.
Question
In an activity-based cost system, what types of drivers are used to describe cost behaviour?

A)activity drivers
B)production or unit-level drivers
C)nonunit-level drivers
D)both production (or unit-level) and nonunit-level drivers
Question
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the designing tooling activity?

A)£81,250
B)£33,000
C)£25,000
D)£125,000
Question
Figure 11-4
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:  Maintenance £120,000 Inspection £200,000\begin{array}{ll}\text { Maintenance } & £ 120,000 \\\text { Inspection } & £ 200,000\end{array} The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:  Direct materials £1,500 Direct labour £5,000 Machine hours 400 Number of inspections 6 Direct labour hours 750\begin{array}{ll}\text { Direct materials } & £ 1,500 \\\text { Direct labour } & £ 5,000 \\\text { Machine hours } & 400 \\\text { Number of inspections } & 6 \\\text { Direct labour hours } & 750\end{array} Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.

-Refer to Figure 11-4. Using direct labour hours to assign overhead, the total cost of the potential job would be

A)£9,500.
B)£6,000.
C)£3,000.
D)£1,600.
Question
Figure 11-5
Granite, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array} { l l l l } \text { Overhead Item } & \text { Expected Cost } & \text { Cost Driver } & \text { Expected Quantity } \\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 500 Job 501 Direct materials £1,500£2,000 Direct labour £1,400£2,400 Units completed 100160 Direct labour hours 100160 Number of setups 28 Number of orders 810 Machine hours 4050 Kilowatt hours 60100\begin{array}{lll}&\underline{\text { Job } 500}&\underline{\text { Job } 501}\\\text { Direct materials } & £ 1,500 & £ 2,000 \\\text { Direct labour } & £ 1,400 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 100 & 160 \\\text { Number of setups } & 2 & 8 \\\text { Number of orders } & 8 & 10 \\\text { Machine hours } & 40 & 50 \\\text { Kilowatt hours } & 60 & 100\end{array} The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-5. If Granite, SA., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 500 would be

A)£53.15.
B)£54.15.
C)£56.67.
D)£57.15.
Question
Figure 11-6
Peach, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost \multicolumn1c Cost Driver  Expected Quantity  Setup costs £200,000 Number of setups 500 Ordering costs 80,000 Number of orders 3,200 Maintenance 400,000 Machine hours 4,000 Power 40,000 Kilowatt hours 80,000\begin{array} { l c l l } \text { Overhead Item } & \text { Expected Cost } & \multicolumn{1}{c} { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 200,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 80,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 400,000 & \text { Machine hours } & 4,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 400 Job 401 Direct materials £750£2,000 Direct labour £700£2,400 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\underline{\text { Job } 400}&\underline{\text { Job } 401}\\\text { Direct materials } & £ 750 & £ 2,000 \\\text { Direct labour } & £ 700 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array}

The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-6. If Peach, SA., used direct labour hours to assign overhead, the unit cost for Job 401 would be

A)£117.50.
B)£111.88.
C)£105.00.
D)£102.50.
Question
Flanigan Manufacturing uses an activity-based cost system. The company produces Product R and Product X. Information concerning the two products is as follows:  Product R  Froduct X  Units produced 30,00050,000 Direct labour hours 24,00026,000 Engineering labour (hours) 4,0006,000 Setups 2030 Kilowatt hours 5,0007,000\begin{array}{lll}&\text { Product R } & \text { Froduct X } \\\text { Units produced } & 30,000 & 50,000 \\\text { Direct labour hours } & 24,000 & 26,000 \\\text { Engineering labour (hours) } & 4,000 & 6,000 \\\text { Setups } & 20 & 30 \\\text { Kilowatt hours } & 5,000 & 7,000\end{array} The following costs are reported:  Power £24,000 Engineering 140,000 Setups 120,000\begin{array}{ll}\text { Power } & £ 24,000 \\\text { Engineering } & 140,000 \\\text { Setups } & 120,000\end{array}
Question
Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates.<div style=padding-top: 35px> Activity drivers for each activity have been identified and their practical capacities listed: Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates.<div style=padding-top: 35px> The costs of facility-level activities are assigned using machine hours.
a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.
b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates.
c.Build an activity relational (i.e. cost) table.
d.Compute the cost pool rates.
Question
Holbrook, SA., has identified the following overhead costs and cost drivers for next year: Holbrook, SA., has identified the following overhead costs and cost drivers for next year:   The following are two of the jobs completed during the year:   The company's normal activity is 40,000 direct labour hours. a.Determine the unit cost for each job using direct labour hours to apply overhead. b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.) c.Which method produces the more accurate cost assignment? Why?<div style=padding-top: 35px> The following are two of the jobs completed during the year: Holbrook, SA., has identified the following overhead costs and cost drivers for next year:   The following are two of the jobs completed during the year:   The company's normal activity is 40,000 direct labour hours. a.Determine the unit cost for each job using direct labour hours to apply overhead. b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.) c.Which method produces the more accurate cost assignment? Why?<div style=padding-top: 35px> The company's normal activity is 40,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Question
Activity-based costing assigns costs to cost object by first

A)tracing costs to products and then tracing costs to cost objects.
B)tracing costs to departments and then tracing costs to products.
C)tracing costs to activities and then tracing costs to cost objects.
D)tracing costs to customers and then tracing costs to products.
Question
Hunter Company manufactures two products (XX and YY). The overhead costs have been divided into four cost pools that use the following activity drivers:  Number of  Number of  Number oflabour  Labour  Product  Orders  Setups  Transactions  Hours XX6020502,000YY208070500 Cost per pool £16,000£13,000£2,400£20,000\begin{array}{ccccc}& \text { Number of } & \text { Number of } & \text { Number oflabour } & \text { Labour } \\\text { Product } & \text { Orders } & \text { Setups } & \text { Transactions } & \text { Hours }\\X X & 60 & 20 & 50 & 2,000 \\Y Y & 20 & 80 & 70 & 500\\\\\text { Cost per pool } & £ 16,000 & £ 13,000 & £ 2,400 & £ 20,000\end{array}
a.Compute the allocation rates for each of the activity drivers listed.
b.Allocate the overhead costs to Products XX and YY using activity-based costing.
c.Compute the overhead rate using labour hours under the traditional functional-based costing system.
d.Allocate the overhead costs to Products XX and YY using the traditional functional-based costing system overhead rate calculated in part (c).
Question
Figure 11-5
Granite, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array} { l l l l } \text { Overhead Item } & \text { Expected Cost } & \text { Cost Driver } & \text { Expected Quantity } \\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 500 Job 501 Direct materials £1,500£2,000 Direct labour £1,400£2,400 Units completed 100160 Direct labour hours 100160 Number of setups 28 Number of orders 810 Machine hours 4050 Kilowatt hours 60100\begin{array}{lll}&\underline{\text { Job } 500}&\underline{\text { Job } 501}\\\text { Direct materials } & £ 1,500 & £ 2,000 \\\text { Direct labour } & £ 1,400 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 100 & 160 \\\text { Number of setups } & 2 & 8 \\\text { Number of orders } & 8 & 10 \\\text { Machine hours } & 40 & 50 \\\text { Kilowatt hours } & 60 & 100\end{array} The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-5. If Granite, SA., used activity-based cost drivers to allocate overhead costs, the total cost of Job 500 would be

A)£5,715.
B)£5,667.
C)£5,415.
D)£5,315.
Question
Batch-related costs are added to which of the following costs in break-even analysis?

A)variable
B)fixed
C)mixed
D)none of the above
Question
Ernest, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £320,000 Number of setups 4,000 Ordering costs 120,000 Number of orders 20,000 Maintenance 480,000 Machine hours 24,000 Power 40,000 Kilowatt hours 160,000\begin{array} { l l l c } \text { Overhead Item } & \text { Expected Cost } & { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 320,000 & \text { Number of setups } & 4,000 \\\text { Ordering costs } & 120,000 & \text { Number of orders } & 20,000 \\\text { Maintenance } & 480,000 & \text { Machine hours } & 24,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 160,000\end{array} The following are two of the jobs completed during the year:  Job 320 Job 321 Direct materials £8,000£19,000 Direct labour £6,400£12,000 Units completed 8001,600 Direct labour hours 240500 Number of setups 1220 Number of orders 2040 Machine hours 400600 Kilowatt hours 280400\begin{array}{lll}&\text { Job } 320& \text { Job } 321\\\text { Direct materials } & £ 8,000 & £ 19,000 \\\text { Direct labour } & £ 6,400 & £ 12,000 \\\text { Units completed } & 800 & 1,600 \\\text { Direct labour hours } & 240 & 500 \\\text { Number of setups } & 12 & 20 \\\text { Number of orders } & 20 & 40 \\\text { Machine hours } & 400 & 600 \\\text { Kilowatt hours } & 280 & 400\end{array} The company's normal activity is 32,000 direct labour hours. (Round amounts to two decimal places.)
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers.
c.Which method produces the more accurate cost assignment? Why?
Question
Figure 11-4
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:  Maintenance £120,000 Inspection £200,000\begin{array}{ll}\text { Maintenance } & £ 120,000 \\\text { Inspection } & £ 200,000\end{array} The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:  Direct materials £1,500 Direct labour £5,000 Machine hours 400 Number of inspections 6 Direct labour hours 750\begin{array}{ll}\text { Direct materials } & £ 1,500 \\\text { Direct labour } & £ 5,000 \\\text { Machine hours } & 400 \\\text { Number of inspections } & 6 \\\text { Direct labour hours } & 750\end{array} Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.

-Refer to Figure 11-4 above. Using activity-based costing and the appropriate cost drivers, the total cost of the potential job would be

A)£9,230.
B)£8,180.
C)£2,250.
D)£1,680.
Question
Figure 11-6
Peach, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost \multicolumn1c Cost Driver  Expected Quantity  Setup costs £200,000 Number of setups 500 Ordering costs 80,000 Number of orders 3,200 Maintenance 400,000 Machine hours 4,000 Power 40,000 Kilowatt hours 80,000\begin{array} { l c l l } \text { Overhead Item } & \text { Expected Cost } & \multicolumn{1}{c} { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 200,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 80,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 400,000 & \text { Machine hours } & 4,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 400 Job 401 Direct materials £750£2,000 Direct labour £700£2,400 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\underline{\text { Job } 400}&\underline{\text { Job } 401}\\\text { Direct materials } & £ 750 & £ 2,000 \\\text { Direct labour } & £ 700 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array}

The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-6. If Peach, SA., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 401 would be (round to two decimal places)

A)£42.81.
B)£53.13.
C)£53.91.
D)£54.06.
Question
Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates.<div style=padding-top: 35px> Activity drivers for each activity have been identified and their practical capacities listed: Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates.<div style=padding-top: 35px> The costs of facility-level activities are assigned using machine hours.
a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.
b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates.
c.Build an activity relational (i.e. cost) table.
d.Compute the cost pool rates.
Question
Books Company manufactures and sells two products: Soft Cover (S) and Hard Cover (H). The firm's activities have been analyzed and placed into a hierarchy of activity costs. Presented is information on activity cost drivers and costs per unit of cost driver at each activity level.  Activity Level  Activity  Cost  Unit level X11, S acquire direct materials b11,£6X12, H acquire direct materials b12,£10X13, S other manufacturing costs b1,£2X14, H other manufacturing costs b14,£4 Batch level X21, S setup b21,£200X2, H setup b22,£300 Product level X31, S advertising b31,£20,000X32, H advertising b32,£30,000 Facility level X41, Rent b41,£10,000\begin{array} { l l l } \text { Activity Level } & \text { Activity } & \text { Cost } \\\text { Unit level } & X _ { 11 } , \text { S acquire direct materials } & b _ { 11 } , £ 6 \\& X _ { 12 } , \text { H acquire direct materials } & b _ { 12 } , £ 10 \\& X _ { 13 } , \text { S other manufacturing costs } & b _ { 1 } , £ 2 \\& X _ { 14 } , \text { H other manufacturing costs } & b _ { 14 } , £ 4 \\\text { Batch level } & X _ { 21 } , \text { S setup } & b _ { 21 } , £ 200 \\& X _ { 2 } , \text { H setup } & b _ { 22 } , £ 300 \\\text { Product level } & X _ { 31 } , \text { S advertising } & b _ { 31 } , £ 20,000 \\& X _ { 32 } , \text { H advertising } & b _ { 32 } , £ 30,000 \\\text { Facility level } & X _ { 41 } , \text { Rent } & b _ { 41 } , £ 10,000\end{array} During January 2012, Books Company produced 10,000 units of Soft Covers and 5,000 units of Hard Covers. Each batch of products includes 1,000 units of Soft Covers or 1,000 units of Hard Covers.
Question
Hill Manufacturing uses an activity-based costing system. The company produces Model A and Model B. Information concerning the two products is as follows:  Model A  Model B  Units produced 30,00050,000 Direct labour hours 24,00026,000 Engineering labour (hours) 4,0006,000 Setups 2030 Kilowatt hours 5,0007,000\begin{array} { l l l } & \text { Model A } & \text { Model B } \\ \text { Units produced } & 30,000 & 50,000 \\ \text { Direct labour hours } & 24,000 & 26,000 \\ \text { Engineering labour (hours) } & 4,000 & 6,000 \\ \text { Setups } & 20 & 30 \\ \text { Kilowatt hours } & 5,000 & 7,000 \end{array}


The following costs are reported:

 Power £12,000 labour-related overhead 70,000 Setups 60,000\begin{array}{ll}\text { Power } & £ 12,000 \\\text { labour-related overhead } & 70,000 \\\text { Setups } & 60,000\end{array}
a.Classify the following overhead activities as unit-level activities, batch-level activities, or product-level activities:PowerEngineeringSetups
b.Calculate the following:A cost pool rate for powerA cost pool rate for setupsA cost pool rate for engineering
c.Calculate the following:Power costs assigned to Model BSetups costs assigned to Model AEngineering costs assigned to Model A
Question
Lyons, SA., has identified the following overhead costs and activity drivers for next year:  Overhead Item  Expected Cost  Activity Driver  Expected Qty.  Setup costs £150,000 Number of setups 1,200 Ordering costs 40,000 Number of orders 10,000 Maintenance 200,000 Machine hours 16,000 Power 20,000 Kilowatt hours 100,000\begin{array} { l c l c } \text { Overhead Item } & \text { Expected Cost } & \text { Activity Driver } & \text { Expected Qty. } \\\text { Setup costs } & £ 150,000 & \text { Number of setups } & 1,200 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 10,000 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 16,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 100,000\end{array} The following are two of the jobs completed during the year:  Job XX Job YY Direct materials £2,250£2,500 Direct labour 3,0001,875 Units completed 375300 Direct labour hours 90110 Number of setups 68 Number of orders 815 Machine hours 180150 Kilowatt hours 90120\begin{array}{lll}&\underline{\text { Job XX}} &\underline{\text { Job YY} }\\\text { Direct materials } & £ 2,250 & £ 2,500 \\\text { Direct labour } & 3,000 & 1,875 \\\text { Units completed } & 375 & 300 \\\text { Direct labour hours } & 90 & 110 \\\text { Number of setups } & 6 & 8 \\\text { Number of orders } & 8 & 15 \\\text { Machine hours } & 180 & 150 \\\text { Kilowatt hours } & 90 & 120\end{array}
The company's normal activity is 20,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four activity drivers. (Round amounts to 2 decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/56
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 11: Activity-Based Costing
1
If activity-based costing is used, setups would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
B
2
All of the following are nonunit-based activity drivers EXCEPT

A)number of setups.
B)number of direct labour hours.
C)number of inspections.
D)number of material moves.
B
3
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the unit-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)machining
machining
4
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the facility-level activity(ies)?

A)providing utilities
B)providing space
C)inspecting
D)both a and b
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
5
Figure 11-1
Ubben Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information relating to the two products is as follows:  Model X  Model Y  Units produced 20,00040,000 Machine hours 8,00010,000 Direct labour hours 14,00016,000 Engineering labour (hours) 1,0001,400 Setups 4060\begin{array}{lll}&\text { Model X } & \text { Model Y } \\\text { Units produced } & 20,000 & 40,000 \\\text { Machine hours } & 8,000 & 10,000 \\\text { Direct labour hours } & 14,000 & 16,000 \\\text { Engineering labour (hours) } & 1,000 & 1,400 \\\text { Setups } & 40 & 60\end{array} The following costs are reported:  Engineering £48,000 Setups 100,000 Machine-rel ated overhead 144,000\begin{array}{ll}\text { Engineering } & £ 48,000 \\\text { Setups } & 100,000 \\\text { Machine-rel ated overhead } & 144,000\end{array}

-Refer to Figure 11-1. Setups would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
6
Riley, SA., has identified the following overhead costs and activity drivers for next year:  Expected  Expected  Overhead Item  Cost  Activity Driver  Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array}{lclc}\text { Expected }&&\text { Expected }\\\text { Overhead Item }&\text { Cost } & \text { Activity Driver } & \text { Quantity }\\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year: Job AAJob BB  Direct materials £375£1,000 Direct labour £350£1,200 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\mathrm{Job} \text { AA} &\mathrm{Job} \text { BB }\\\text { Direct materials } & £ 375 & £ 1,000 \\\text { Direct labour } & £ 350 & £ 1,200 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array} The company's normal activity is 4,000 direct labour hours. If the activity drivers are used to allocate overhead costs, the unit cost (rounded to two decimal places) for Job BB would be

A)£21.40.
B)£26.56.
C)£26.95.
D)£27.03.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
7
All of the following are unit-based activity drivers EXCEPT

A)machine hours.
B)number of setups.
C)number of units.
D)direct labour hours.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
8
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the product-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)none of the above
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
9
If activity-based costing is used, insurance on the plant would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
10
Maintenance of the production equipment would be classified as a

A)unit-level activity.
B)product-level activity.
C)cell-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
11
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool overhead rate for the unit-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
12
If activity-based costing is used, electricity usage would be an example of a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
13
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the batch-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
14
Which of the following quantities is an example of an activity driver in activity-based costing?

A)number of setups
B)number of orders placed
C)number of machine hours
D)all of the above
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
15
If activity-based costing is used, product inspections would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
16
Figure 11-1
Ubben Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information relating to the two products is as follows:  Model X  Model Y  Units produced 20,00040,000 Machine hours 8,00010,000 Direct labour hours 14,00016,000 Engineering labour (hours) 1,0001,400 Setups 4060\begin{array}{lll}&\text { Model X } & \text { Model Y } \\\text { Units produced } & 20,000 & 40,000 \\\text { Machine hours } & 8,000 & 10,000 \\\text { Direct labour hours } & 14,000 & 16,000 \\\text { Engineering labour (hours) } & 1,000 & 1,400 \\\text { Setups } & 40 & 60\end{array} The following costs are reported:  Engineering £48,000 Setups 100,000 Machine-rel ated overhead 144,000\begin{array}{ll}\text { Engineering } & £ 48,000 \\\text { Setups } & 100,000 \\\text { Machine-rel ated overhead } & 144,000\end{array}

-Refer to Figure 11-1. Machine-related overhead would be classified as a

A)unit-level activity.
B)batch-level activity.
C)product-level activity.
D)facility-level activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
17
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is(are) the batch-level activity(ies)?

A)engineering
B)setups
C)inspecting
D)all of the above
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
18
The use of unit-based activity drivers to assign costs tends to

A)overcost low-volume products.
B)overcost high-volume products.
C)undercost all products.
D)overcost all products.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
19
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the facility-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)£97.20 per machine hour
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
20
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:  Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000\begin{array}{ll}\text { Engineering } & £ 1,000,000 \\\text { Setups } & 900,000 \\\text { Machining } & 2,000,000 \\\text { Inspection } & 800,000 \\\text { Providing space } & 250,000 \\\text { Providing utilities } & 180,000\end{array} Activity drivers for each activity have been identified and their practical capacities listed:  Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500\begin{array}{ll}\text { Machine hours } & 25,000 \\\text { Setups } & 200 \\\text { Engineering hours } & 5,000 \\\text { Inspection hours } & 2,500\end{array} The costs of facility-level activities are assigned using machine hours.

-Refer to Figure 11-2. What is the cost pool rate for the product-level activities?

A)£80.00 per machine hour
B)£13,500.00 per setup
C)£17.20 per machine hour
D)none of the above
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
21
Which of the following items would be classified as committed resources (short-term)?

A)salaried employees
B)depreciation on building
C)fuel to generate electricity internally
D)lease on machinery
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
22
Resources that are only purchased precisely at the time the resource is needed are called

A)committed resources.
B)flexible resources.
C)scarce resources.
D)none of the above.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
23
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the training employees activity?

A)£27,500
B)£125,000
C)£31,250
D)£81,250
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
24
The overhead rates of the traditional-based approach to product costing use

A)nonunit-based cost drivers.
B)unit-based cost drivers.
C)process costing.
D)job-order costing.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
25
What is the initial step in implementing an activity-based costing system?

A)assigning costs to activities
B)assigning costs to products
C)identifying activities and attributes
D)dividing activity costs by activity drivers
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
26
Basing overhead allocation solely on volume

A)will undercost high-volume products and overcost low-volume products.
B)will overcost high-volume products and undercost low-volume products.
C)is the sole basis of the activity-based costing model.
D)All of the above are correct.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
27
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the improving processes activity?

A)£250,000
B)£25,000
C)£43,750
D)£51,000
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
28
An example of a nonunit-level driver is

A)pounds of direct materials.
B)number of setups.
C)number of machine hours where each product manufactured requires one machine hour.
D)number of labour hours.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
29
An example of a production or unit-level driver is

A)pounds of direct materials.
B)number of setups.
C)number of batches.
D)number of product lines.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
30
Which of the following items would be classified as committed resources (long-term)?

A)salaried employees
B)depreciation on building
C)lease on machinery
D)both b and c
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
31
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the creating BOMs activity?

A)£31,250
B)£7,500
C)£43,750
D)£125,000
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
32
An activity-based cost system

A)differs from a traditional-based cost system in the nature and number of the cost drivers used.
B)uses both unit-based and nonunit-based cost drivers that reflect a cause-and-effect relationship.
C)can trace cost accurately to cost objects other than products.
D)does all of the above.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
33
Committed resources are

A)hard to purchase.
B)purchased precisely at the time the resource is needed and have no unused capacity.
C)supplied in advance of usage and may have unused capacity.
D)none of the above.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
34
An activity-based costing system uses which of the following procedures?

A)Overhead costs are traced to departments, then costs are traced to products.
B)Overhead costs are traced to activities, then costs are traced to products.
C)Overhead costs are traced directly to products.
D)All overhead costs are expensed as incurred.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following items would be classified as flexible resources?

A)salaried employees
B)depreciation on building
C)fuel to generate electricity internally
D)lease on machinery
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
36
An activity cost driver is

A)a factor that causes variations in a cost.
B)another term for input measure.
C)the largest single category of cost in a company.
D)a variable cost.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
37
More accurate product costing information is produced by assigning costs using

A)volume-based, plantwide rates.
B)volume-based, departmental rates.
C)activity-based pool rates.
D)All of the above produce accurate product costing information.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
38
In an activity-based cost system, what types of drivers are used to describe cost behaviour?

A)activity drivers
B)production or unit-level drivers
C)nonunit-level drivers
D)both production (or unit-level) and nonunit-level drivers
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
39
Figure 11-3
Moss Ltd. has the following activities: creating bills of materials (BOM), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tooling. The general ledger accounts reveal the following expenditures for manufacturing engineering:
 Salaries £75,000 Equipment 40,000 Supplies 10,000 Total £125,000\begin{array}{ll}\text { Salaries } & £ 75,000 \\\text { Equipment } & 40,000 \\\text { Supplies } & 10,000 \\\quad \text { Total } &£ 125,000\\\end{array}

-Refer to Figure 11-3. What is the cost assigned to the designing tooling activity?

A)£81,250
B)£33,000
C)£25,000
D)£125,000
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
40
Figure 11-4
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:  Maintenance £120,000 Inspection £200,000\begin{array}{ll}\text { Maintenance } & £ 120,000 \\\text { Inspection } & £ 200,000\end{array} The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:  Direct materials £1,500 Direct labour £5,000 Machine hours 400 Number of inspections 6 Direct labour hours 750\begin{array}{ll}\text { Direct materials } & £ 1,500 \\\text { Direct labour } & £ 5,000 \\\text { Machine hours } & 400 \\\text { Number of inspections } & 6 \\\text { Direct labour hours } & 750\end{array} Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.

-Refer to Figure 11-4. Using direct labour hours to assign overhead, the total cost of the potential job would be

A)£9,500.
B)£6,000.
C)£3,000.
D)£1,600.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
41
Figure 11-5
Granite, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array} { l l l l } \text { Overhead Item } & \text { Expected Cost } & \text { Cost Driver } & \text { Expected Quantity } \\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 500 Job 501 Direct materials £1,500£2,000 Direct labour £1,400£2,400 Units completed 100160 Direct labour hours 100160 Number of setups 28 Number of orders 810 Machine hours 4050 Kilowatt hours 60100\begin{array}{lll}&\underline{\text { Job } 500}&\underline{\text { Job } 501}\\\text { Direct materials } & £ 1,500 & £ 2,000 \\\text { Direct labour } & £ 1,400 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 100 & 160 \\\text { Number of setups } & 2 & 8 \\\text { Number of orders } & 8 & 10 \\\text { Machine hours } & 40 & 50 \\\text { Kilowatt hours } & 60 & 100\end{array} The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-5. If Granite, SA., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 500 would be

A)£53.15.
B)£54.15.
C)£56.67.
D)£57.15.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
42
Figure 11-6
Peach, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost \multicolumn1c Cost Driver  Expected Quantity  Setup costs £200,000 Number of setups 500 Ordering costs 80,000 Number of orders 3,200 Maintenance 400,000 Machine hours 4,000 Power 40,000 Kilowatt hours 80,000\begin{array} { l c l l } \text { Overhead Item } & \text { Expected Cost } & \multicolumn{1}{c} { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 200,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 80,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 400,000 & \text { Machine hours } & 4,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 400 Job 401 Direct materials £750£2,000 Direct labour £700£2,400 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\underline{\text { Job } 400}&\underline{\text { Job } 401}\\\text { Direct materials } & £ 750 & £ 2,000 \\\text { Direct labour } & £ 700 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array}

The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-6. If Peach, SA., used direct labour hours to assign overhead, the unit cost for Job 401 would be

A)£117.50.
B)£111.88.
C)£105.00.
D)£102.50.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
43
Flanigan Manufacturing uses an activity-based cost system. The company produces Product R and Product X. Information concerning the two products is as follows:  Product R  Froduct X  Units produced 30,00050,000 Direct labour hours 24,00026,000 Engineering labour (hours) 4,0006,000 Setups 2030 Kilowatt hours 5,0007,000\begin{array}{lll}&\text { Product R } & \text { Froduct X } \\\text { Units produced } & 30,000 & 50,000 \\\text { Direct labour hours } & 24,000 & 26,000 \\\text { Engineering labour (hours) } & 4,000 & 6,000 \\\text { Setups } & 20 & 30 \\\text { Kilowatt hours } & 5,000 & 7,000\end{array} The following costs are reported:  Power £24,000 Engineering 140,000 Setups 120,000\begin{array}{ll}\text { Power } & £ 24,000 \\\text { Engineering } & 140,000 \\\text { Setups } & 120,000\end{array}
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
44
Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates. Activity drivers for each activity have been identified and their practical capacities listed: Godwin Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates. The costs of facility-level activities are assigned using machine hours.
a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.
b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates.
c.Build an activity relational (i.e. cost) table.
d.Compute the cost pool rates.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
45
Holbrook, SA., has identified the following overhead costs and cost drivers for next year: Holbrook, SA., has identified the following overhead costs and cost drivers for next year:   The following are two of the jobs completed during the year:   The company's normal activity is 40,000 direct labour hours. a.Determine the unit cost for each job using direct labour hours to apply overhead. b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.) c.Which method produces the more accurate cost assignment? Why? The following are two of the jobs completed during the year: Holbrook, SA., has identified the following overhead costs and cost drivers for next year:   The following are two of the jobs completed during the year:   The company's normal activity is 40,000 direct labour hours. a.Determine the unit cost for each job using direct labour hours to apply overhead. b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.) c.Which method produces the more accurate cost assignment? Why? The company's normal activity is 40,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers. (Round amounts to two decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
46
Activity-based costing assigns costs to cost object by first

A)tracing costs to products and then tracing costs to cost objects.
B)tracing costs to departments and then tracing costs to products.
C)tracing costs to activities and then tracing costs to cost objects.
D)tracing costs to customers and then tracing costs to products.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
47
Hunter Company manufactures two products (XX and YY). The overhead costs have been divided into four cost pools that use the following activity drivers:  Number of  Number of  Number oflabour  Labour  Product  Orders  Setups  Transactions  Hours XX6020502,000YY208070500 Cost per pool £16,000£13,000£2,400£20,000\begin{array}{ccccc}& \text { Number of } & \text { Number of } & \text { Number oflabour } & \text { Labour } \\\text { Product } & \text { Orders } & \text { Setups } & \text { Transactions } & \text { Hours }\\X X & 60 & 20 & 50 & 2,000 \\Y Y & 20 & 80 & 70 & 500\\\\\text { Cost per pool } & £ 16,000 & £ 13,000 & £ 2,400 & £ 20,000\end{array}
a.Compute the allocation rates for each of the activity drivers listed.
b.Allocate the overhead costs to Products XX and YY using activity-based costing.
c.Compute the overhead rate using labour hours under the traditional functional-based costing system.
d.Allocate the overhead costs to Products XX and YY using the traditional functional-based costing system overhead rate calculated in part (c).
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
48
Figure 11-5
Granite, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £100,000 Number of setups 500 Ordering costs 40,000 Number of orders 3,200 Maintenance 200,000 Machine hours 4,000 Power 20,000 Kilowatt hours 80,000\begin{array} { l l l l } \text { Overhead Item } & \text { Expected Cost } & \text { Cost Driver } & \text { Expected Quantity } \\\text { Setup costs } & £ 100,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 4,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 500 Job 501 Direct materials £1,500£2,000 Direct labour £1,400£2,400 Units completed 100160 Direct labour hours 100160 Number of setups 28 Number of orders 810 Machine hours 4050 Kilowatt hours 60100\begin{array}{lll}&\underline{\text { Job } 500}&\underline{\text { Job } 501}\\\text { Direct materials } & £ 1,500 & £ 2,000 \\\text { Direct labour } & £ 1,400 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 100 & 160 \\\text { Number of setups } & 2 & 8 \\\text { Number of orders } & 8 & 10 \\\text { Machine hours } & 40 & 50 \\\text { Kilowatt hours } & 60 & 100\end{array} The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-5. If Granite, SA., used activity-based cost drivers to allocate overhead costs, the total cost of Job 500 would be

A)£5,715.
B)£5,667.
C)£5,415.
D)£5,315.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
49
Batch-related costs are added to which of the following costs in break-even analysis?

A)variable
B)fixed
C)mixed
D)none of the above
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
50
Ernest, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost  Cost Driver  Expected Quantity  Setup costs £320,000 Number of setups 4,000 Ordering costs 120,000 Number of orders 20,000 Maintenance 480,000 Machine hours 24,000 Power 40,000 Kilowatt hours 160,000\begin{array} { l l l c } \text { Overhead Item } & \text { Expected Cost } & { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 320,000 & \text { Number of setups } & 4,000 \\\text { Ordering costs } & 120,000 & \text { Number of orders } & 20,000 \\\text { Maintenance } & 480,000 & \text { Machine hours } & 24,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 160,000\end{array} The following are two of the jobs completed during the year:  Job 320 Job 321 Direct materials £8,000£19,000 Direct labour £6,400£12,000 Units completed 8001,600 Direct labour hours 240500 Number of setups 1220 Number of orders 2040 Machine hours 400600 Kilowatt hours 280400\begin{array}{lll}&\text { Job } 320& \text { Job } 321\\\text { Direct materials } & £ 8,000 & £ 19,000 \\\text { Direct labour } & £ 6,400 & £ 12,000 \\\text { Units completed } & 800 & 1,600 \\\text { Direct labour hours } & 240 & 500 \\\text { Number of setups } & 12 & 20 \\\text { Number of orders } & 20 & 40 \\\text { Machine hours } & 400 & 600 \\\text { Kilowatt hours } & 280 & 400\end{array} The company's normal activity is 32,000 direct labour hours. (Round amounts to two decimal places.)
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four cost drivers.
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
51
Figure 11-4
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:  Maintenance £120,000 Inspection £200,000\begin{array}{ll}\text { Maintenance } & £ 120,000 \\\text { Inspection } & £ 200,000\end{array} The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:  Direct materials £1,500 Direct labour £5,000 Machine hours 400 Number of inspections 6 Direct labour hours 750\begin{array}{ll}\text { Direct materials } & £ 1,500 \\\text { Direct labour } & £ 5,000 \\\text { Machine hours } & 400 \\\text { Number of inspections } & 6 \\\text { Direct labour hours } & 750\end{array} Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.

-Refer to Figure 11-4 above. Using activity-based costing and the appropriate cost drivers, the total cost of the potential job would be

A)£9,230.
B)£8,180.
C)£2,250.
D)£1,680.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
52
Figure 11-6
Peach, SA., has identified the following overhead costs and cost drivers for next year:  Overhead Item  Expected Cost \multicolumn1c Cost Driver  Expected Quantity  Setup costs £200,000 Number of setups 500 Ordering costs 80,000 Number of orders 3,200 Maintenance 400,000 Machine hours 4,000 Power 40,000 Kilowatt hours 80,000\begin{array} { l c l l } \text { Overhead Item } & \text { Expected Cost } & \multicolumn{1}{c} { \text { Cost Driver } } & \text { Expected Quantity } \\\text { Setup costs } & £ 200,000 & \text { Number of setups } & 500 \\\text { Ordering costs } & 80,000 & \text { Number of orders } & 3,200 \\\text { Maintenance } & 400,000 & \text { Machine hours } & 4,000 \\\text { Power } & 40,000 & \text { Kilowatt hours } & 80,000\end{array} The following are two of the jobs completed during the year:  Job 400 Job 401 Direct materials £750£2,000 Direct labour £700£2,400 Units completed 100160 Direct labour hours 5080 Number of setups 14 Number of orders 45 Machine hours 2025 Kilowatt hours 3050\begin{array}{lll}&\underline{\text { Job } 400}&\underline{\text { Job } 401}\\\text { Direct materials } & £ 750 & £ 2,000 \\\text { Direct labour } & £ 700 & £ 2,400 \\\text { Units completed } & 100 & 160 \\\text { Direct labour hours } & 50 & 80 \\\text { Number of setups } & 1 & 4 \\\text { Number of orders } & 4 & 5 \\\text { Machine hours } & 20 & 25 \\\text { Kilowatt hours } & 30 & 50\end{array}

The company's normal activity is 4,000 direct labour hours.

-Refer to Figure 11-6. If Peach, SA., used activity-based cost drivers to allocate overhead costs, the unit cost for Job 401 would be (round to two decimal places)

A)£42.81.
B)£53.13.
C)£53.91.
D)£54.06.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
53
Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates. Activity drivers for each activity have been identified and their practical capacities listed: Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:   Activity drivers for each activity have been identified and their practical capacities listed:   The costs of facility-level activities are assigned using machine hours. a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level. b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates. c.Build an activity relational (i.e. cost) table. d.Compute the cost pool rates. The costs of facility-level activities are assigned using machine hours.
a.Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.
b.Create homogeneous cost pools. Identify the activities that belong to each pool and the activity driver that will be used for computing pool rates.
c.Build an activity relational (i.e. cost) table.
d.Compute the cost pool rates.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
54
Books Company manufactures and sells two products: Soft Cover (S) and Hard Cover (H). The firm's activities have been analyzed and placed into a hierarchy of activity costs. Presented is information on activity cost drivers and costs per unit of cost driver at each activity level.  Activity Level  Activity  Cost  Unit level X11, S acquire direct materials b11,£6X12, H acquire direct materials b12,£10X13, S other manufacturing costs b1,£2X14, H other manufacturing costs b14,£4 Batch level X21, S setup b21,£200X2, H setup b22,£300 Product level X31, S advertising b31,£20,000X32, H advertising b32,£30,000 Facility level X41, Rent b41,£10,000\begin{array} { l l l } \text { Activity Level } & \text { Activity } & \text { Cost } \\\text { Unit level } & X _ { 11 } , \text { S acquire direct materials } & b _ { 11 } , £ 6 \\& X _ { 12 } , \text { H acquire direct materials } & b _ { 12 } , £ 10 \\& X _ { 13 } , \text { S other manufacturing costs } & b _ { 1 } , £ 2 \\& X _ { 14 } , \text { H other manufacturing costs } & b _ { 14 } , £ 4 \\\text { Batch level } & X _ { 21 } , \text { S setup } & b _ { 21 } , £ 200 \\& X _ { 2 } , \text { H setup } & b _ { 22 } , £ 300 \\\text { Product level } & X _ { 31 } , \text { S advertising } & b _ { 31 } , £ 20,000 \\& X _ { 32 } , \text { H advertising } & b _ { 32 } , £ 30,000 \\\text { Facility level } & X _ { 41 } , \text { Rent } & b _ { 41 } , £ 10,000\end{array} During January 2012, Books Company produced 10,000 units of Soft Covers and 5,000 units of Hard Covers. Each batch of products includes 1,000 units of Soft Covers or 1,000 units of Hard Covers.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
55
Hill Manufacturing uses an activity-based costing system. The company produces Model A and Model B. Information concerning the two products is as follows:  Model A  Model B  Units produced 30,00050,000 Direct labour hours 24,00026,000 Engineering labour (hours) 4,0006,000 Setups 2030 Kilowatt hours 5,0007,000\begin{array} { l l l } & \text { Model A } & \text { Model B } \\ \text { Units produced } & 30,000 & 50,000 \\ \text { Direct labour hours } & 24,000 & 26,000 \\ \text { Engineering labour (hours) } & 4,000 & 6,000 \\ \text { Setups } & 20 & 30 \\ \text { Kilowatt hours } & 5,000 & 7,000 \end{array}


The following costs are reported:

 Power £12,000 labour-related overhead 70,000 Setups 60,000\begin{array}{ll}\text { Power } & £ 12,000 \\\text { labour-related overhead } & 70,000 \\\text { Setups } & 60,000\end{array}
a.Classify the following overhead activities as unit-level activities, batch-level activities, or product-level activities:PowerEngineeringSetups
b.Calculate the following:A cost pool rate for powerA cost pool rate for setupsA cost pool rate for engineering
c.Calculate the following:Power costs assigned to Model BSetups costs assigned to Model AEngineering costs assigned to Model A
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
56
Lyons, SA., has identified the following overhead costs and activity drivers for next year:  Overhead Item  Expected Cost  Activity Driver  Expected Qty.  Setup costs £150,000 Number of setups 1,200 Ordering costs 40,000 Number of orders 10,000 Maintenance 200,000 Machine hours 16,000 Power 20,000 Kilowatt hours 100,000\begin{array} { l c l c } \text { Overhead Item } & \text { Expected Cost } & \text { Activity Driver } & \text { Expected Qty. } \\\text { Setup costs } & £ 150,000 & \text { Number of setups } & 1,200 \\\text { Ordering costs } & 40,000 & \text { Number of orders } & 10,000 \\\text { Maintenance } & 200,000 & \text { Machine hours } & 16,000 \\\text { Power } & 20,000 & \text { Kilowatt hours } & 100,000\end{array} The following are two of the jobs completed during the year:  Job XX Job YY Direct materials £2,250£2,500 Direct labour 3,0001,875 Units completed 375300 Direct labour hours 90110 Number of setups 68 Number of orders 815 Machine hours 180150 Kilowatt hours 90120\begin{array}{lll}&\underline{\text { Job XX}} &\underline{\text { Job YY} }\\\text { Direct materials } & £ 2,250 & £ 2,500 \\\text { Direct labour } & 3,000 & 1,875 \\\text { Units completed } & 375 & 300 \\\text { Direct labour hours } & 90 & 110 \\\text { Number of setups } & 6 & 8 \\\text { Number of orders } & 8 & 15 \\\text { Machine hours } & 180 & 150 \\\text { Kilowatt hours } & 90 & 120\end{array}
The company's normal activity is 20,000 direct labour hours.
a.Determine the unit cost for each job using direct labour hours to apply overhead.
b.Determine the unit cost for each job using the four activity drivers. (Round amounts to 2 decimal places.)
c.Which method produces the more accurate cost assignment? Why?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 56 flashcards in this deck.