Deck 38: Network Planning and Analysis

Full screen (f)
exit full mode
Question
Which of the following statements about float is NOT true?

A) Float is used to make sure that the total duration of the path fits with the expected completion date
B) Float may not be added to activities on the critical path without extending the critical path
C) Total float is the amount of time which can be added without creating a new critical path
D) Free float is the amount of time which can be added to an activity without affecting the float of subsequent activities
Use Space or
up arrow
down arrow
to flip the card.
Question
What is the basic process for calculating the event late time for an event in the middle of a network diagram?

A) Add the duration of the preceding activity (to the left) to its early time
B) Subtract the duration of the preceding activity (to the left) to its early time
C) Add the duration of the following activity (to the right) to its early time
D) Subtract the duration of the following activity (to the right) to its early time
Question
Which of the following statements concerning events and activities is NOT true?

A) All activities must start and end with an event
B) Activities are tasks which require some effort
C) Events are project milestones used to mark progress
D) All events can only be associated with one activity
Question
Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?

A) Activity F can start when Activity D is finished
B) Event 3 is complete when Activity B is complete
C) Activity E must wait for both Activity B and Activity C to finish
D) Activity B can start when half of Activity A is complete
Question
Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start? <strong>Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start?  </strong> A) 4 B) 6 C) 8 D) 14 <div style=padding-top: 35px>

A) 4
B) 6
C) 8
D) 14
Question
Which of the following options is the BEST definition of network planning?

A) Deciding the best way to set out processes in a factory
B) Breaking a project down into constituent processes to manage time efficiently
C) The design and implementation of an IT system
D) Optimising communications with business contacts to generate sales
Question
What is a precedence table?

A) A tabular summary of the network
B) A table showing the events in order of importance
C) A table showing the activities in order of duration
D) A tabular summary of resources needed to complete a network
Question
Which statement concerning dummy activities is NOT true?

A) Dummy activities are used to prevent an activity having the same start and end events
B) Dummy activities always have no time associated with them
C) Dummy activities may be used to preserve the correct order of activities
D) Dummy activities are used to ensure that skilled workers do the most important jobs
Question
Which of the following options is the BEST definition of a critical path?

A) The path through a network with the longest duration
B) The path through a network with the shortest duration
C) The path through a network with the most important duration
D) The path through a network where mistakes are most likely to occur
Question
How might the earliest activity finish time be calculated?

A) Latest start of beginning event + activity duration
B) Latest start of beginning event - activity duration
C) Earliest start of beginning event + activity duration
D) Earliest start of beginning event - activity duration
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/10
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 38: Network Planning and Analysis
1
Which of the following statements about float is NOT true?

A) Float is used to make sure that the total duration of the path fits with the expected completion date
B) Float may not be added to activities on the critical path without extending the critical path
C) Total float is the amount of time which can be added without creating a new critical path
D) Free float is the amount of time which can be added to an activity without affecting the float of subsequent activities
Float is used to make sure that the total duration of the path fits with the expected completion date
2
What is the basic process for calculating the event late time for an event in the middle of a network diagram?

A) Add the duration of the preceding activity (to the left) to its early time
B) Subtract the duration of the preceding activity (to the left) to its early time
C) Add the duration of the following activity (to the right) to its early time
D) Subtract the duration of the following activity (to the right) to its early time
Subtract the duration of the following activity (to the right) to its early time
3
Which of the following statements concerning events and activities is NOT true?

A) All activities must start and end with an event
B) Activities are tasks which require some effort
C) Events are project milestones used to mark progress
D) All events can only be associated with one activity
All events can only be associated with one activity
4
Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?

A) Activity F can start when Activity D is finished
B) Event 3 is complete when Activity B is complete
C) Activity E must wait for both Activity B and Activity C to finish
D) Activity B can start when half of Activity A is complete
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
5
Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start? <strong>Consider the event in a network diagram represented by the symbol below. What is the earliest time that this event can start?  </strong> A) 4 B) 6 C) 8 D) 14

A) 4
B) 6
C) 8
D) 14
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following options is the BEST definition of network planning?

A) Deciding the best way to set out processes in a factory
B) Breaking a project down into constituent processes to manage time efficiently
C) The design and implementation of an IT system
D) Optimising communications with business contacts to generate sales
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
7
What is a precedence table?

A) A tabular summary of the network
B) A table showing the events in order of importance
C) A table showing the activities in order of duration
D) A tabular summary of resources needed to complete a network
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
8
Which statement concerning dummy activities is NOT true?

A) Dummy activities are used to prevent an activity having the same start and end events
B) Dummy activities always have no time associated with them
C) Dummy activities may be used to preserve the correct order of activities
D) Dummy activities are used to ensure that skilled workers do the most important jobs
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following options is the BEST definition of a critical path?

A) The path through a network with the longest duration
B) The path through a network with the shortest duration
C) The path through a network with the most important duration
D) The path through a network where mistakes are most likely to occur
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
10
How might the earliest activity finish time be calculated?

A) Latest start of beginning event + activity duration
B) Latest start of beginning event - activity duration
C) Earliest start of beginning event + activity duration
D) Earliest start of beginning event - activity duration