A(n) ____ minimum vertical clearance is required above finished grade for sidewalks, or from any platform or projection from which overhead conductors (of 150 volts, or less, to ground) might be reached.

A) 9-ft (2.7-m)
B) 10-ft (3.0-m)
C) 11-ft (3.3-m)
D) 12-ft (3.7-m)
Use Space or
up arrow
down arrow
to flip the card.
Question
Ground-fault protection that functions to open the service disconnect will afford no protection from faults on the ____ of the protective element.

A) circuit side
B) panel box side
C) underside
D) line side
Question
Where the ungrounded supply conductors are larger than 1100 kcmil copper or 1750 kcmil aluminum, the supply-side bonding jumper shall have an area not less than ____ of the area of the largest ungrounded supply conductor or equivalent area for parallel supply conductors.

A) 10½%
B) 12½%
C) 15½%
D) 18½%
Question
According to the NEC , live parts of electric equipment operating at 50 to 1000 volts, nominal, shall be guarded against ____ by approved enclosures.

A) water damage
B) overvoltage
C) accidental contact
D) phase transformations
Question
The alternating current phase arrangement on 3-phase busses are ____ from front to back, top to bottom, or left to right, as viewed from the front of the switchboard, switchgear, or panelboard.

A) A, B, C
B) C, B, A
C) 1, 2, 3
D) 3, 2, 1
Question
Vertical wiring clearances apply to ____.

A) commercial services
B) residential services
C) all electrical feeder and service installations
D) dwellings over six stories
Question
No secondary overcurrent protection is required for certain transformers 1000 volts, nominal, or less with currents of at least 9 amperes and a maximum primary overcurrent protection of ____.

A) 75%
B) 100%
C) 125%
D) 150%
Question
The connection between the grounded circuit conductor (neutral) and the equipment grounding conductor at the service is the ____.

A) main switching lead
B) main bonding jumper
C) central lead
D) transverse bridge
Question
Where rear access is required to work on nonelectrical parts at the back of enclosed equipment, a minimum working space of ____ horizontally is required.

A) 20 in.(508 mm)
B) 30 in.(762 mm)
C) 36 in.(914 mm)
D) 40 in.(1 m)
Question
According to the NEC , where a panelboard is supplied through a transformer, the overcurrent protection required by 408.36 shall be located on the ____ side of the transformer.

A) top
B) bottom
C) primary
D) secondary
Question
Equipment rated ____ amperes (or more) and over 6 ft (1.8 m) wide requires an entrance to and egress from the required working space at least 24 in.(610 mm) wide and 6½ ft (2.0 m) high at each end of the working space.

A) 700
B) 1000
C) 1100
D) 1200
Question
Overcurrent protection for transformers over ____ volts, nominal, is required.

A) 300
B) 500
C) 600
D) 1000
Question
Service equipment in other than dwelling units shall be legibly marked in the field with the ____.

A) average impedance
B) minimum current
C) maximum available fault current
D) maximum average current
Question
A structural ceiling may not ____.

A) contain any wiring
B) contain any lighting
C) be a suspended or drop type
D) contain ductwork
Question
A drip loop's lowest point has a minimum vertical clearance of ____.

A) 9 ft (2.7 m)
B) 10 ft (3.0 m)
C) 11 ft (3.3 m)
D) 12 ft (3.7 m)
Question
The ____ phase must be that phase having the higher voltage to ground on 3-phase, 4-wire, delta-connected systems.

A) A
B) B
C) C
D) D
Question
All panelboards shall have a rating not less than the ____ required for the load calculated in accordance with Part III, IV, or V of Article 220.

A) minimum feeder capacity
B) maximum feeder capacity
C) 50% of maximum feeder capacity
D) 50% of minimum feeder capacity
Question
One access means to a working space is permitted where the location provides ____.

A) a continuous and unobstructed exit
B) adequate sprinkler coverage
C) balcony exits
D) adequate overhead clearance
Question
Where ungrounded conductors are increased in size for any reason other than as required in 310.15(B) or 310.15(C), wire-type equipment grounding conductors (where installed) shall be increased in size ____, according to the circular mil area of the ungrounded conductors.

A) proportionately
B) inversely
C) directly
D) indirectly
Question
A ____ is a large single panel, frame, or assembly of panels with front- or rear-mounted switches, protective devices (overcurrent, etc.), buses, and, usually, instruments.

A) panelboard
B) switchboard
C) circuit cabinet
D) panel cabinet
Question
Live generator parts operating at more than ____ volts ac to ground shall not be exposed to accidental contact by unqualified persons.

A) 25
B) 50
C) 75
D) 100
Question
The maximum rating for overcurrent protection on a primary unit is ____.

A) 125%
B) 250%
C) 300%
D) 350%
Question
All mechanical elements used to terminate a grounding electrode conductor or bonding jumper to a grounding electrode shall be ____.

A) painted
B) waterproof
C) accessible
D) lubricated
Question
A system that supplies a ____ and is derived from a transformer rated no more than 1000 volt-amperes does not require a grounding electrode conductor.

A) Class A, EE, AE circuit
B) main branch circuit
C) secondary circuit
D) Class 1, 2, or 3 circuit
Question
Premises wiring (system) is defined as ____, including power, lighting, control, and signal circuit wiring together with all their associated hardware, fittings, and wiring devices, both permanently and temporarily installed.

A) interior and exterior wiring
B) interior wiring
C) exterior wiring
D) main service wiring
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/25
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 14: Services Feeders and Equipment
1
A(n) ____ minimum vertical clearance is required above finished grade for sidewalks, or from any platform or projection from which overhead conductors (of 150 volts, or less, to ground) might be reached.

A) 9-ft (2.7-m)
B) 10-ft (3.0-m)
C) 11-ft (3.3-m)
D) 12-ft (3.7-m)
B
2
Ground-fault protection that functions to open the service disconnect will afford no protection from faults on the ____ of the protective element.

A) circuit side
B) panel box side
C) underside
D) line side
D
3
Where the ungrounded supply conductors are larger than 1100 kcmil copper or 1750 kcmil aluminum, the supply-side bonding jumper shall have an area not less than ____ of the area of the largest ungrounded supply conductor or equivalent area for parallel supply conductors.

A) 10½%
B) 12½%
C) 15½%
D) 18½%
B
4
According to the NEC , live parts of electric equipment operating at 50 to 1000 volts, nominal, shall be guarded against ____ by approved enclosures.

A) water damage
B) overvoltage
C) accidental contact
D) phase transformations
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
5
The alternating current phase arrangement on 3-phase busses are ____ from front to back, top to bottom, or left to right, as viewed from the front of the switchboard, switchgear, or panelboard.

A) A, B, C
B) C, B, A
C) 1, 2, 3
D) 3, 2, 1
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
6
Vertical wiring clearances apply to ____.

A) commercial services
B) residential services
C) all electrical feeder and service installations
D) dwellings over six stories
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
7
No secondary overcurrent protection is required for certain transformers 1000 volts, nominal, or less with currents of at least 9 amperes and a maximum primary overcurrent protection of ____.

A) 75%
B) 100%
C) 125%
D) 150%
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
8
The connection between the grounded circuit conductor (neutral) and the equipment grounding conductor at the service is the ____.

A) main switching lead
B) main bonding jumper
C) central lead
D) transverse bridge
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
9
Where rear access is required to work on nonelectrical parts at the back of enclosed equipment, a minimum working space of ____ horizontally is required.

A) 20 in.(508 mm)
B) 30 in.(762 mm)
C) 36 in.(914 mm)
D) 40 in.(1 m)
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
10
According to the NEC , where a panelboard is supplied through a transformer, the overcurrent protection required by 408.36 shall be located on the ____ side of the transformer.

A) top
B) bottom
C) primary
D) secondary
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
11
Equipment rated ____ amperes (or more) and over 6 ft (1.8 m) wide requires an entrance to and egress from the required working space at least 24 in.(610 mm) wide and 6½ ft (2.0 m) high at each end of the working space.

A) 700
B) 1000
C) 1100
D) 1200
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
12
Overcurrent protection for transformers over ____ volts, nominal, is required.

A) 300
B) 500
C) 600
D) 1000
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
13
Service equipment in other than dwelling units shall be legibly marked in the field with the ____.

A) average impedance
B) minimum current
C) maximum available fault current
D) maximum average current
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
14
A structural ceiling may not ____.

A) contain any wiring
B) contain any lighting
C) be a suspended or drop type
D) contain ductwork
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
15
A drip loop's lowest point has a minimum vertical clearance of ____.

A) 9 ft (2.7 m)
B) 10 ft (3.0 m)
C) 11 ft (3.3 m)
D) 12 ft (3.7 m)
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
16
The ____ phase must be that phase having the higher voltage to ground on 3-phase, 4-wire, delta-connected systems.

A) A
B) B
C) C
D) D
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
17
All panelboards shall have a rating not less than the ____ required for the load calculated in accordance with Part III, IV, or V of Article 220.

A) minimum feeder capacity
B) maximum feeder capacity
C) 50% of maximum feeder capacity
D) 50% of minimum feeder capacity
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
18
One access means to a working space is permitted where the location provides ____.

A) a continuous and unobstructed exit
B) adequate sprinkler coverage
C) balcony exits
D) adequate overhead clearance
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
19
Where ungrounded conductors are increased in size for any reason other than as required in 310.15(B) or 310.15(C), wire-type equipment grounding conductors (where installed) shall be increased in size ____, according to the circular mil area of the ungrounded conductors.

A) proportionately
B) inversely
C) directly
D) indirectly
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
20
A ____ is a large single panel, frame, or assembly of panels with front- or rear-mounted switches, protective devices (overcurrent, etc.), buses, and, usually, instruments.

A) panelboard
B) switchboard
C) circuit cabinet
D) panel cabinet
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
21
Live generator parts operating at more than ____ volts ac to ground shall not be exposed to accidental contact by unqualified persons.

A) 25
B) 50
C) 75
D) 100
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
22
The maximum rating for overcurrent protection on a primary unit is ____.

A) 125%
B) 250%
C) 300%
D) 350%
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
23
All mechanical elements used to terminate a grounding electrode conductor or bonding jumper to a grounding electrode shall be ____.

A) painted
B) waterproof
C) accessible
D) lubricated
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
24
A system that supplies a ____ and is derived from a transformer rated no more than 1000 volt-amperes does not require a grounding electrode conductor.

A) Class A, EE, AE circuit
B) main branch circuit
C) secondary circuit
D) Class 1, 2, or 3 circuit
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
25
Premises wiring (system) is defined as ____, including power, lighting, control, and signal circuit wiring together with all their associated hardware, fittings, and wiring devices, both permanently and temporarily installed.

A) interior and exterior wiring
B) interior wiring
C) exterior wiring
D) main service wiring
Unlock Deck
Unlock for access to all 25 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 25 flashcards in this deck.