Deck 5: Measuring Concrete Work

Full screen (f)
exit full mode
Question
Vertical finishes are measured in _______ of exposed surface of concrete.

A)cubic feet
B)linear feet
C)cubic meters
D)square feet
Use Space or
up arrow
down arrow
to flip the card.
Question
The estimator measures the surface area of the concrete that comes into contact with the forms; this is known as the ____.

A)contact area
B)displacement area
C)adsorption area
D)footing area
Question
Grout to anchor bolts and base plates is measured in cubic feet or cubic meters.
Question
Screeds can be measured in square feet or square meters as the plan area of the slab, though some estimators prefer to measure the length of the individual screed strips.
Question
Do not adjust the quantity of concrete for reinforcing steel and insets which displace concrete.
Question
Slab finishes are measured in ____.

A)square inches of plan area
B)square inches of exposed surface
C)square feet or square meters of plan area
D)square feet or square meters of exposed surface
Question
In general, you should calculate the volume of concrete from the dimensions given on the drawings with adjustments for "add-on" factors.
Question
Concrete is classified in terms of the use to which the concrete is put.
Question
Where there is an opening in a form system of less than 100 square feet, a deduction is made from the total area of the forms.
Question
Welded wire mesh shall be measured in plan area with an additional ____% included for overlaps.

A)5
B)10
C)15
D)20
Question
Expansion joints are measured in ____, stating the size of joint and the type of material used.

A)linear feet or linear meters
B)cubic feet or cubic meters
C)linear inches
D)cubic inches
Question
Linear inserts such as waterstops are measured in cubic feet or cubic meters.
Question
Finishes are first classified in terms of what is being finished; they are then separated by type of finish.
Question
Because only the ____ of formwork is measured, the estimator does not have to be concerned about the design of the forms at the time of the takeoff.

A)depth
B)height
C)volume
D)area
Question
Deduct for openings in the concrete that are less than one cubic foot (0.05 cubic meters)of volume.
Question
Preparing a quantity takeoff of concrete work requires the estimator to measure a combination of items-some of which are shown on the drawings, while others are to be inferred from the drawings.
Question
Saw cuts for concrete are measured in ____.

A)linear feet or linear meters
B)cubic feet or cubic meters
C)linear inches
D)cubic inches
Question
Concrete shall be measured in ____ net in place.

A)cubic feet
B)cubic yards
C)metric tons
D)linear feet
Question
Because the concrete is detailed on the drawings, it makes sense to begin the takeoff by measuring the volume of concrete in an item.
Question
Bulkhead forms are measured to the perimeter of the window openings, and they are the same width as the wall.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/20
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Measuring Concrete Work
1
Vertical finishes are measured in _______ of exposed surface of concrete.

A)cubic feet
B)linear feet
C)cubic meters
D)square feet
D
2
The estimator measures the surface area of the concrete that comes into contact with the forms; this is known as the ____.

A)contact area
B)displacement area
C)adsorption area
D)footing area
A
3
Grout to anchor bolts and base plates is measured in cubic feet or cubic meters.
True
4
Screeds can be measured in square feet or square meters as the plan area of the slab, though some estimators prefer to measure the length of the individual screed strips.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
5
Do not adjust the quantity of concrete for reinforcing steel and insets which displace concrete.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
6
Slab finishes are measured in ____.

A)square inches of plan area
B)square inches of exposed surface
C)square feet or square meters of plan area
D)square feet or square meters of exposed surface
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
7
In general, you should calculate the volume of concrete from the dimensions given on the drawings with adjustments for "add-on" factors.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
8
Concrete is classified in terms of the use to which the concrete is put.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
9
Where there is an opening in a form system of less than 100 square feet, a deduction is made from the total area of the forms.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
10
Welded wire mesh shall be measured in plan area with an additional ____% included for overlaps.

A)5
B)10
C)15
D)20
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
11
Expansion joints are measured in ____, stating the size of joint and the type of material used.

A)linear feet or linear meters
B)cubic feet or cubic meters
C)linear inches
D)cubic inches
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
12
Linear inserts such as waterstops are measured in cubic feet or cubic meters.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
13
Finishes are first classified in terms of what is being finished; they are then separated by type of finish.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
14
Because only the ____ of formwork is measured, the estimator does not have to be concerned about the design of the forms at the time of the takeoff.

A)depth
B)height
C)volume
D)area
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
15
Deduct for openings in the concrete that are less than one cubic foot (0.05 cubic meters)of volume.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
16
Preparing a quantity takeoff of concrete work requires the estimator to measure a combination of items-some of which are shown on the drawings, while others are to be inferred from the drawings.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
17
Saw cuts for concrete are measured in ____.

A)linear feet or linear meters
B)cubic feet or cubic meters
C)linear inches
D)cubic inches
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
18
Concrete shall be measured in ____ net in place.

A)cubic feet
B)cubic yards
C)metric tons
D)linear feet
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
19
Because the concrete is detailed on the drawings, it makes sense to begin the takeoff by measuring the volume of concrete in an item.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
20
Bulkhead forms are measured to the perimeter of the window openings, and they are the same width as the wall.
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 20 flashcards in this deck.