Deck 17: Supplement J Operations Scheduling
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/123
Play
Full screen (f)
Deck 17: Supplement J Operations Scheduling
1
Why is flow time an important measure of performance?
Minimizing job flow times in a schedule tends to minimize work-in-process inventory and maximize utilization. In addition, flow times are related to the lead times (or cycle times) of products and have an influence on customer service.
2
Makespan is the time of completion of a group of jobs, plus the starting time of the first job.
False
3
Which of the following statements on an operations schedule is best?
A) It determines when employees work.
B) It assigns employees to tasks depending on availability.
C) It assigns customers to a definite time for order fulfillment.
D) It assigns jobs to workstations or employees to jobs for specified time periods.
A) It determines when employees work.
B) It assigns employees to tasks depending on availability.
C) It assigns customers to a definite time for order fulfillment.
D) It assigns jobs to workstations or employees to jobs for specified time periods.
D
4
Operations scheduling involves assigning jobs to workstations or employees to jobs for specific time periods.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
5
________ is the total amount of time required to complete a group of jobs.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
6
________ is the degree to which equipment, space, or the workforce is currently being used.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
7
________ scheduling assigns jobs to machines or employees to jobs.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
8
In the context of operations scheduling, total inventory is equal to:
A) scheduled receipts plus on-hand inventories.
B) received orders minus scheduled receipts.
C) on-hand inventories plus received orders.
D) None of these is equal to total inventory.
A) scheduled receipts plus on-hand inventories.
B) received orders minus scheduled receipts.
C) on-hand inventories plus received orders.
D) None of these is equal to total inventory.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
9
Describe the difference between front office and back office operations from the standpoint of scheduling customer jobs.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
10
Operations scheduling applies only to manufacturing, because services do not allow inventories.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
11
The sum of scheduled receipts for all items and the on-hand inventories for all items is ________.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
12
The percent of work time productively spent by an employee or a machine is called:
A) activation.
B) efficiency.
C) effectiveness.
D) utilization.
A) activation.
B) efficiency.
C) effectiveness.
D) utilization.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
13
An appropriate objective for a manufacturing firm is to maximize total inventory.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
14
A job's flow time at a single workstation is defined as the:
A) completion time of the job plus the time since it arrived at the workstation.
B) processing time to complete the job.
C) time of completion of the last job of a group minus the starting time of the first job.
D) amount of time by which a group of jobs missed their due dates.
A) completion time of the job plus the time since it arrived at the workstation.
B) processing time to complete the job.
C) time of completion of the last job of a group minus the starting time of the first job.
D) amount of time by which a group of jobs missed their due dates.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
15
In the context of operations scheduling, total inventory is the sum of the scheduled receipts for all items and the on-hand inventories for all items.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
16
A(n) ________ is the object receiving service or being manufactured.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
17
________ is the time a job spends in the service or manufacturing system.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
18
Utilization is the degree to which equipment, space, or the workforce is currently being used, measured as the ratio of average output rate to the maximum capacity.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
19
________ is the amount of time by which a job missed its due date.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
20
Makespan is the total amount of time to complete a single job or the first job in a group of jobs.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
21
When using the critical ratio (CR) priority sequencing rule:
A) a ratio of less than 1.0 implies that the job is ahead of schedule.
B) a ratio of less than 1.0 implies the job is behind schedule.
C) the job with the earliest due date is scheduled next.
D) the job with the highest CR is scheduled next.
A) a ratio of less than 1.0 implies that the job is ahead of schedule.
B) a ratio of less than 1.0 implies the job is behind schedule.
C) the job with the earliest due date is scheduled next.
D) the job with the highest CR is scheduled next.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
22
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the EDD rule, what is the average early time?
A) 0 days
B) greater than 0 but less than 1.5 days
C) greater than 2.5 but less than 2.5 days
D) greater than 2.5 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the EDD rule, what is the average early time?
A) 0 days
B) greater than 0 but less than 1.5 days
C) greater than 2.5 but less than 2.5 days
D) greater than 2.5 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
23
The fact that job shops routinely accept new orders at any time makes the scheduling environment dynamic.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
24
Which one of the following rules tends to perform well with respect to percentage of jobs past due and variance of hours past due, but performs relatively poorly with respect to average flow time?
A) earliest due date
B) shortest processing time
C) first-come, first-served
D) longest processing time
A) earliest due date
B) shortest processing time
C) first-come, first-served
D) longest processing time
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
25
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the EDD rule, what is the average flow time?
A) fewer than or equal to 25 days
B) greater than 25 days but fewer than or equal to 27 days
C) greater than 27 days but fewer than or equal to 29 days
D) greater than 29 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the EDD rule, what is the average flow time?
A) fewer than or equal to 25 days
B) greater than 25 days but fewer than or equal to 27 days
C) greater than 27 days but fewer than or equal to 29 days
D) greater than 29 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
26
A manufacturer's flow shop utilizes line or continuous flow processes.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
27
A job shop is accompanied by divergent flows and low-to-medium volume output rates.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
28
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the SPT rule, what is the average flow time?
A) fewer than or equal to 19 days
B) greater than 19 days but fewer than or equal to 21 days
C) greater than 21 days but fewer than or equal to 23 days
D) greater than 23 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the SPT rule, what is the average flow time?
A) fewer than or equal to 19 days
B) greater than 19 days but fewer than or equal to 21 days
C) greater than 21 days but fewer than or equal to 23 days
D) greater than 23 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
29
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

What is the average flow time for all assignments scheduled in an SPT sequence?
A) 28.65
B) 32.14
C) 35.92
D) 36.88
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

What is the average flow time for all assignments scheduled in an SPT sequence?
A) 28.65
B) 32.14
C) 35.92
D) 36.88
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
30
Slack is the difference between the time remaining until a job's due date and the total shop time remaining, excluding that of the operation being scheduled.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
31
When choosing a priority sequencing rule:
A) select multiple-dimension rules because they dominate single-dimension rules for all performance measures.
B) always select the rule that minimizes the amount of past-due jobs.
C) test a variety of rules before making a decision.
D) select CR or S/RO because they use more information.
A) select multiple-dimension rules because they dominate single-dimension rules for all performance measures.
B) always select the rule that minimizes the amount of past-due jobs.
C) test a variety of rules before making a decision.
D) select CR or S/RO because they use more information.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
32
Critical ratio (CR) is a single-dimension priority rule.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
33
Sequencing jobs does not affect tardiness, because processing times are unchanged with different sequences.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
34
The earliest due date (EDD) rule gives the job with the shortest processing time the highest priority.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
35
A first-come, first-served schedule minimizes the average flow time for all jobs.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
36
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Develop an SPT sequence and calculate the average number of assignments Stu has this semester.
A) 3.36
B) 3.52
C) 3.78
D) 3.94
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Develop an SPT sequence and calculate the average number of assignments Stu has this semester.
A) 3.36
B) 3.52
C) 3.78
D) 3.94
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
37
Determining a production sequence for a group of jobs in a two-station flow shop to minimize the makespan has the advantage of:
A) maximizing the utilization of the shop.
B) minimizing the percentage of jobs past due.
C) minimizing the flow time of jobs on the first machine.
D) minimizing the variance of past-due hours.
A) maximizing the utilization of the shop.
B) minimizing the percentage of jobs past due.
C) minimizing the flow time of jobs on the first machine.
D) minimizing the variance of past-due hours.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
38
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the FCFS rule, what is the average flow time?
A) fewer than or equal to 19 days
B) greater than 19 days but fewer than or equal to 21 days
C) greater than 21 days but fewer than or equal to 23 days
D) greater than 23 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the FCFS rule, what is the average flow time?
A) fewer than or equal to 19 days
B) greater than 19 days but fewer than or equal to 21 days
C) greater than 21 days but fewer than or equal to 23 days
D) greater than 23 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
39
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the SPT rule, what is the average past due?
A) 0 days
B) greater than 0 days but fewer than or equal to 5 days
C) greater than 5 days but fewer than or equal to 10 days
D) greater than 10 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the SPT rule, what is the average past due?
A) 0 days
B) greater than 0 days but fewer than or equal to 5 days
C) greater than 5 days but fewer than or equal to 10 days
D) greater than 10 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
40
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the FCFS rule, what is the average past due?
A) 0 days
B) greater than 0 days but fewer than or equal to 5.5 days
C) greater than 5.5 days but fewer than or equal to 10 days
D) greater than 10 days
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.1 and the FCFS rule, what is the average past due?
A) 0 days
B) greater than 0 days but fewer than or equal to 5.5 days
C) greater than 5.5 days but fewer than or equal to 10 days
D) greater than 10 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
41
Table J.7
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the S/RO rule, what is the average flow time at Workstation A?
A) fewer than or equal to 14.0 hours
B) greater than 14.0 but fewer than or equal to 14.5 hours
C) greater than 14.5 but fewer than or equal to 15.0 hours
D) greater than 15.0 hours
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the S/RO rule, what is the average flow time at Workstation A?
A) fewer than or equal to 14.0 hours
B) greater than 14.0 but fewer than or equal to 14.5 hours
C) greater than 14.5 but fewer than or equal to 15.0 hours
D) greater than 15.0 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
42
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The sequence of jobs using the slack per remaining operations (S/RO) rule, is:
A) 1-3-2
B) 3-2-1
C) 1-2-3
D) 2-3-1
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The sequence of jobs using the slack per remaining operations (S/RO) rule, is:
A) 1-3-2
B) 3-2-1
C) 1-2-3
D) 2-3-1
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
43
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

What is the average flow time for all seven assignments if Stu schedules them using the critical ration criterion?
A) 38.17
B) 37.43
C) 36.67
D) 38.26
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

What is the average flow time for all seven assignments if Stu schedules them using the critical ration criterion?
A) 38.17
B) 37.43
C) 36.67
D) 38.26
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
44
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu decides to adopt an EDD sequence for the assignments, which seems like a very logical approach. Which assignments will he be submitting late?
A) C, D and F
B) B, C and F
C) B, E and G
D) F, E and G
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu decides to adopt an EDD sequence for the assignments, which seems like a very logical approach. Which assignments will he be submitting late?
A) C, D and F
B) B, C and F
C) B, E and G
D) F, E and G
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
45
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu schedules his assignments using the critical ratio criterion. How many assignments are late?
A) 3
B) 4
C) 5
D) 6
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu schedules his assignments using the critical ratio criterion. How many assignments are late?
A) 3
B) 4
C) 5
D) 6
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
46
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu decides to adopt an SPT sequence for the assignments, which at face value seems like an odd choice. Which assignments will he be submitting late?
A) C, D and F
B) B, C and F
C) B, E and G
D) F, E and G
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu decides to adopt an SPT sequence for the assignments, which at face value seems like an odd choice. Which assignments will he be submitting late?
A) C, D and F
B) B, C and F
C) B, E and G
D) F, E and G
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
47
Table J.6
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the average flow time at Workstation A for the critical ratio rule?
A) fewer than or equal to 8 hours
B) greater than 8 hours but fewer than or equal to 9 hours
C) greater than 9 hours but fewer than or equal to 10 hours
D) greater than 10 hours
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the average flow time at Workstation A for the critical ratio rule?
A) fewer than or equal to 8 hours
B) greater than 8 hours but fewer than or equal to 9 hours
C) greater than 9 hours but fewer than or equal to 10 hours
D) greater than 10 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
48
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The average past due using the slack per remaining operations (S/RO) rule is:
A) fewer than or equal to 9.0.
B) greater than 9.0 but fewer than or equal to 18.0.
C) greater than 18.0 but fewer than or equal to 27.0.
D) greater than 27.0.
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The average past due using the slack per remaining operations (S/RO) rule is:
A) fewer than or equal to 9.0.
B) greater than 9.0 but fewer than or equal to 18.0.
C) greater than 18.0 but fewer than or equal to 27.0.
D) greater than 27.0.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
49
Table J.7
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the critical ratio (CR) rule, what is the job sequence?
A) C-D-B-A
B) D-C-B-A
C) A-C-D-B
D) D-B-A-C
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the critical ratio (CR) rule, what is the job sequence?
A) C-D-B-A
B) D-C-B-A
C) A-C-D-B
D) D-B-A-C
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
50
Table J.7
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the CR rule, what is the average flow time at workstation A?
A) fewer than or equal to 14.0 hours
B) greater than 14.0 but fewer than or equal to 14.5 hours
C) greater than 14.5 but fewer than or equal to 15.0 hours
D) greater than 15.0 hours
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the CR rule, what is the average flow time at workstation A?
A) fewer than or equal to 14.0 hours
B) greater than 14.0 but fewer than or equal to 14.5 hours
C) greater than 14.5 but fewer than or equal to 15.0 hours
D) greater than 15.0 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
51
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The operations sequence of jobs, using the critical ratio (CR) rule, is
A) 3-1-2
B) 3-2-1
C) 1-2-3
D) 2-3-1
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The operations sequence of jobs, using the critical ratio (CR) rule, is
A) 3-1-2
B) 3-2-1
C) 1-2-3
D) 2-3-1
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
52
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the FCFS rule, what is the average days past due?
A) fewer than or equal to 5.0 days
B) greater than 5.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the FCFS rule, what is the average days past due?
A) fewer than or equal to 5.0 days
B) greater than 5.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
53
Table J.7
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the slack per remaining operations (S/RO) rule, what is the job sequence?
A) A-B-C-D
B) A-C-D-B
C) C-D-B-A
D) D-C-B-A
The following four jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Using the information in Table J.7 and the slack per remaining operations (S/RO) rule, what is the job sequence?
A) A-B-C-D
B) A-C-D-B
C) C-D-B-A
D) D-C-B-A
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
54
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The average past due using the ratio (CR) rule, is:
A) fewer than or equal to 9.0.
B) greater than 9.0 but fewer than or equal to 18.0.
C) greater than 18.0 but fewer than or equal to 27.0.
D) greater than 27.0.
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.5. The average past due using the ratio (CR) rule, is:
A) fewer than or equal to 9.0.
B) greater than 9.0 but fewer than or equal to 18.0.
C) greater than 18.0 but fewer than or equal to 27.0.
D) greater than 27.0.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
55
Table J.6
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the job sequence at Workstation A, using the critical ratio rule?
A) 3-2-1
B) 1-2-3
C) 1-3-2
D) 2-1-3
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the job sequence at Workstation A, using the critical ratio rule?
A) 3-2-1
B) 1-2-3
C) 1-3-2
D) 2-1-3
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
56
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu applies the critical ratio method to scheduling his assignments. Which assignment is the fourth one in his sequence?
A) E
B) G
C) C
D) D
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu applies the critical ratio method to scheduling his assignments. Which assignment is the fourth one in his sequence?
A) E
B) G
C) C
D) D
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
57
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu whips up a schedule based on the critical ratio criterion. What is the average number of assignments in the system?
A) 3.91
B) 3.71
C) 3.53
D) 3.14
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.

Stu whips up a schedule based on the critical ratio criterion. What is the average number of assignments in the system?
A) 3.91
B) 3.71
C) 3.53
D) 3.14
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
58
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the SPT rule, what is the average days past due?
A) fewer than or equal to 6.0 days
B) greater than 6.0 days but fewer than or equal to 7.0 days
C) greater than 7.0 days but fewer than or equal to 8.0 days
D) greater than 8.0 days
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the SPT rule, what is the average days past due?
A) fewer than or equal to 6.0 days
B) greater than 6.0 days but fewer than or equal to 7.0 days
C) greater than 7.0 days but fewer than or equal to 8.0 days
D) greater than 8.0 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
59
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the EDD rule, what is the average days past due?
A) fewer than or equal to 8.0 days
B) greater than 8.0 days but fewer than or equal to 9.5 days
C) greater than 9.5 but fewer than or equal to 11.0 days
D) greater than 11.0 days
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8 and the EDD rule, what is the average days past due?
A) fewer than or equal to 8.0 days
B) greater than 8.0 days but fewer than or equal to 9.5 days
C) greater than 9.5 but fewer than or equal to 11.0 days
D) greater than 11.0 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
60
Table J.6
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the average past due time at Workstation A for the critical ratio rule?
A) 0 hours
B) greater than 0 hours but fewer than or equal to 5 hours
C) greater than 5 hours but fewer than or equal to 10 hours
D) greater than 10 hours
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.

Use the information in Table J.6. What is the average past due time at Workstation A for the critical ratio rule?
A) 0 hours
B) greater than 0 hours but fewer than or equal to 5 hours
C) greater than 5 hours but fewer than or equal to 10 hours
D) greater than 10 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
61
Table J.18

Use the information Table J.18 and sequence the jobs using the SPT rule. What is the average past due?
A) fewer than or equal to 29 hours
B) greater than 29 hours but fewer than or equal to 31 hours
C) greater than 31 hours but fewer than or equal to 33 hours
D) greater than 33 hours

Use the information Table J.18 and sequence the jobs using the SPT rule. What is the average past due?
A) fewer than or equal to 29 hours
B) greater than 29 hours but fewer than or equal to 31 hours
C) greater than 31 hours but fewer than or equal to 33 hours
D) greater than 33 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
62
A(n) ________ specializes in medium- to high-volume production and uses line or continuous flow processes.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
63
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the critical ratio rule, what should be the sequence of jobs processed at Q45?
A) A-B-C-D
B) D-A-C-B
C) D-C-B-A
D) B-C-A-D
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the critical ratio rule, what should be the sequence of jobs processed at Q45?
A) A-B-C-D
B) D-A-C-B
C) D-C-B-A
D) B-C-A-D
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
64
Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the slack per remaining operation (S/RO) rule, what is the average days past due?
A) fewer than or equal to 6.0 days
B) greater than 6.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the slack per remaining operation (S/RO) rule, what is the average days past due?
A) fewer than or equal to 6.0 days
B) greater than 6.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
65
Table J.10
A workstation has six jobs waiting to be processed. They arrived at the end of Day 0 and it is now the beginning of Day 1. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.10 and the earliest due date (EDD) rule, which job(s) will be completed on or before their due dates?
A) F only
B) A and F only
C) B, A, and E only
D) E and B only
A workstation has six jobs waiting to be processed. They arrived at the end of Day 0 and it is now the beginning of Day 1. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.10 and the earliest due date (EDD) rule, which job(s) will be completed on or before their due dates?
A) F only
B) A and F only
C) B, A, and E only
D) E and B only
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
66
________ is a priority sequencing rule that determines priority by dividing the difference between the due date and today's date less the processing time remaining by the number of processing steps left to complete the job.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
67
Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the slack per remaining operations (S/RO) rule, what should be the sequence of jobs processed at Workstation 1?
A) A-B-C
B) B-C-A
C) C-B-A
D) B-A-C
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the slack per remaining operations (S/RO) rule, what should be the sequence of jobs processed at Workstation 1?
A) A-B-C
B) B-C-A
C) C-B-A
D) B-A-C
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
68
Table J.18

Use the information in Table J.18 and sequence the jobs using the SPT rule. What is the average flow time?
A) fewer than or equal to 52 hours
B) greater than 52 hours but fewer than or equal to 54 hours
C) greater than 54 hours but fewer than or equal to 56 hours
D) greater than 56 hours

Use the information in Table J.18 and sequence the jobs using the SPT rule. What is the average flow time?
A) fewer than or equal to 52 hours
B) greater than 52 hours but fewer than or equal to 54 hours
C) greater than 54 hours but fewer than or equal to 56 hours
D) greater than 56 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
69
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the critical ratio rule, what is the flow time of job B?
A) fewer than or equal to 10 hours
B) greater than 10 hours but fewer than or equal to 20 hours
C) greater than 20 hours but fewer than or equal to 30 hours
D) greater than 30 hours
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the critical ratio rule, what is the flow time of job B?
A) fewer than or equal to 10 hours
B) greater than 10 hours but fewer than or equal to 20 hours
C) greater than 20 hours but fewer than or equal to 30 hours
D) greater than 30 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
70
A(n) ________ specializes in low- to medium-volume production using job or batch processes.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
71
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8, and either the FCFS, SPT or EDD rule, what is the fewest number of late jobs possible?
A) no late jobs
B) one late job
C) two late jobs
D) three late jobs
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.

Using the information in Table J.8, and either the FCFS, SPT or EDD rule, what is the fewest number of late jobs possible?
A) no late jobs
B) one late job
C) two late jobs
D) three late jobs
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
72
Table J.18

Use the information in the table and sequence the jobs using the EDD rule. What is the average past due?
A) fewer than or equal to 32 hours
B) greater than 32 hours but fewer than or equal to 34 hours
C) greater than 34 hours but fewer than or equal to 36 hours
D) greater than 36 hours

Use the information in the table and sequence the jobs using the EDD rule. What is the average past due?
A) fewer than or equal to 32 hours
B) greater than 32 hours but fewer than or equal to 34 hours
C) greater than 34 hours but fewer than or equal to 36 hours
D) greater than 36 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
73
________ specify the job processing sequence when several jobs are waiting in line at a workstation.
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
74
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the shortest processing time (SPT) rule, what should be the sequence of jobs processed at Q45?
A) C-D-A-B
B) D-A-C-B
C) A-D-B-C
D) B-A-D-C
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the shortest processing time (SPT) rule, what should be the sequence of jobs processed at Q45?
A) C-D-A-B
B) D-A-C-B
C) A-D-B-C
D) B-A-D-C
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
75
Table J.18

Use the information in Table J.18 and sequence the jobs using the EDD rule. What is the average flow time?
A) fewer than or equal to 48 hours
B) greater than 48 hours but fewer than or equal to 50 hours
C) greater than 50 hours but fewer than or equal to 52 hours
D) greater than 52 hours

Use the information in Table J.18 and sequence the jobs using the EDD rule. What is the average flow time?
A) fewer than or equal to 48 hours
B) greater than 48 hours but fewer than or equal to 50 hours
C) greater than 50 hours but fewer than or equal to 52 hours
D) greater than 52 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
76
Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the critical ratio rule, what is the average flow time?
A) fewer than or equal to 9.0 days
B) greater than 9.0 days but fewer than or equal to 10.0 days
C) greater than 10.0 days but fewer than or equal to 11.0 days
D) greater than 11.0 days
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the critical ratio rule, what is the average flow time?
A) fewer than or equal to 9.0 days
B) greater than 9.0 days but fewer than or equal to 10.0 days
C) greater than 10.0 days but fewer than or equal to 11.0 days
D) greater than 11.0 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
77
Table J.10
A workstation has six jobs waiting to be processed. They arrived at the end of Day 0 and it is now the beginning of Day 1. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.10 and the earliest due date (EDD) rule, what is the average flow time?
A) fewer than or equal to 20 days
B) greater than 20 days but fewer than or equal to 22 days
C) greater than 22 days but fewer than or equal to 24 days
D) greater than 24 days
A workstation has six jobs waiting to be processed. They arrived at the end of Day 0 and it is now the beginning of Day 1. It is now time zero. Times are expressed in terms of days.

Using the information in Table J.10 and the earliest due date (EDD) rule, what is the average flow time?
A) fewer than or equal to 20 days
B) greater than 20 days but fewer than or equal to 22 days
C) greater than 22 days but fewer than or equal to 24 days
D) greater than 24 days
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
78
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the slack per remaining operations (S/RO) rule, what should be the sequence of jobs processed at Q45?
A) D-C-A-B
B) A-B-C-D
C) D-A-C-B
D) B-C-A-D
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the slack per remaining operations (S/RO) rule, what should be the sequence of jobs processed at Q45?
A) D-C-A-B
B) A-B-C-D
C) D-A-C-B
D) B-C-A-D
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
79
Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the critical ratio rule, what should be the sequence of jobs processed at Workstation 1?
A) C-B-A
B) B-A-C
C) A-B-C
D) B-C-A
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.

Using the information in Table J.9 and the critical ratio rule, what should be the sequence of jobs processed at Workstation 1?
A) C-B-A
B) B-A-C
C) A-B-C
D) B-C-A
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck
80
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the slack per remaining operations ratio (S/RO) rule, what is the average past due?
A) fewer than or equal to 10 hours
B) greater than 10 hours but fewer than or equal to 20 hours
C) greater than 20 hours but fewer than or equal to 30 hours
D) greater than 30 hours
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.

Using the information in Table J.11 and the slack per remaining operations ratio (S/RO) rule, what is the average past due?
A) fewer than or equal to 10 hours
B) greater than 10 hours but fewer than or equal to 20 hours
C) greater than 20 hours but fewer than or equal to 30 hours
D) greater than 30 hours
Unlock Deck
Unlock for access to all 123 flashcards in this deck.
Unlock Deck
k this deck