Question
Which of these is not a characteristic of a project?

A) Unique
B) Temporary
C) Low variety
D) Cross functional
Use Space or
up arrow
down arrow
to flip the card.
Question
Which is the correct order of the four stages of a project life cycle?

A) Planning, Scoping, Implementation, Evaluation
B) Scoping, Planning, Implementation, Evaluation
C) Planning, Scoping, Evaluation, Implementation
D) Scoping, Implementation, Planning, Evaluation
Question
During which phase of a project life cycle is there the highest momentum of work activity?

A) Scoping
B) Planning
C) Implementation
D) Evaluation
Question
During which phase of a project life cycle is a work breakdown structure (WBS) developed?

A) Scoping
B) Planning
C) Implementation
D) Evaluation
Question
People or organizations affected by a project are called _____________?

A) Associates
B) Influencers
C) Customers
D) Stakeholders
Question
What is a Gantt Chart?

A) A chart which considers the time, quality and resources of a project
B) A chart which considers the cost, quality and resources of a project
C) A chart which considers the time, cost and resources of a project
D) A chart which considers the stakeholders, quality and resources of a project
Question
The technique whereby each task can be investigated by virtue of their most likely time to completion, their most optimistic time and most pessimistic time is referred to as ________________________?

A) The project analysis and review technique
B) The programme analysis and review technique
C) The project evaluation and review technique
D) The programme evaluation and review technique
Question
The two most used types of project management are the Waterfall Technique and ____________.

A) Lean project management
B) Agile project management
C) Efficient project management
D) Critical project management
Question
Project risk management can be broken down into five major stages. These are planning, identification, analysis, monitoring and control and ______________________?

A) Recovery
B) Response
C) Constraints
D) Compliance
Question
What is Business Continuity Management?

A) A way of planning to use best practice within an organization
B) A way of planning the best quality approach to the running of an organization
C) A plan to keep an organization working following a crisis
D) A plan to deliver sustainability within an organization
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/10
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 11: Managing Projects, Crises, and Business Cont
1
Which of these is not a characteristic of a project?

A) Unique
B) Temporary
C) Low variety
D) Cross functional
C
2
Which is the correct order of the four stages of a project life cycle?

A) Planning, Scoping, Implementation, Evaluation
B) Scoping, Planning, Implementation, Evaluation
C) Planning, Scoping, Evaluation, Implementation
D) Scoping, Implementation, Planning, Evaluation
B
3
During which phase of a project life cycle is there the highest momentum of work activity?

A) Scoping
B) Planning
C) Implementation
D) Evaluation
C
4
During which phase of a project life cycle is a work breakdown structure (WBS) developed?

A) Scoping
B) Planning
C) Implementation
D) Evaluation
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
5
People or organizations affected by a project are called _____________?

A) Associates
B) Influencers
C) Customers
D) Stakeholders
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
6
What is a Gantt Chart?

A) A chart which considers the time, quality and resources of a project
B) A chart which considers the cost, quality and resources of a project
C) A chart which considers the time, cost and resources of a project
D) A chart which considers the stakeholders, quality and resources of a project
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
7
The technique whereby each task can be investigated by virtue of their most likely time to completion, their most optimistic time and most pessimistic time is referred to as ________________________?

A) The project analysis and review technique
B) The programme analysis and review technique
C) The project evaluation and review technique
D) The programme evaluation and review technique
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
8
The two most used types of project management are the Waterfall Technique and ____________.

A) Lean project management
B) Agile project management
C) Efficient project management
D) Critical project management
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
9
Project risk management can be broken down into five major stages. These are planning, identification, analysis, monitoring and control and ______________________?

A) Recovery
B) Response
C) Constraints
D) Compliance
Unlock Deck
Unlock for access to all 10 flashcards in this deck.
Unlock Deck
k this deck
10
What is Business Continuity Management?

A) A way of planning to use best practice within an organization
B) A way of planning the best quality approach to the running of an organization
C) A plan to keep an organization working following a crisis
D) A plan to deliver sustainability within an organization