Deck 10: Warranties

Full screen (f)
exit full mode
Question
A Contractor should check the Contract to determine the Actual Authority of the Design Professionals
Use Space or
up arrow
down arrow
to flip the card.
Question
Related to warranty periods

A) The Contract Administrator should make sure manufacturer's agreed warranties coincide with the project requirements
B) The Contract Administrator should pass on only those warranties that are still in place
C) Never pay more for what is required in the Contract warranty period
D) The Contract Administrator should begin all warranties at the time of Substantial completion
Question
Expressed authority is

A) Usually detailed at the first project meeting so everyone clearly understands who has what authority
B) Is delineated in the contract
C) Is an verbal directive issued by the Owner
D) Is any verbal directive issued by either the Owner or the Owner's agent (e.g. Architect)
Question
The Owner reserves the right in regard to uncorrected work to

A) Remove the Contractor from the project
B) Make corrections and backcharge the Contractor
C) Withhold payment
D) All of these
Question
When it comes to quality

A) The Architect is the only inspector that counts
B) We can all be inspectors
C) The Owner will usually hire a special person
D) Whoever is in charge of safety can't be involved in quality
Question
The process of project closeout

A) Begins upon substantial completion
B) Is up to the Owner
C) Begins when the Contract Administrator finishes reading the Contract
D) Is dictated by the Architect
Question
Final payment guarantees the Constructor that everything has been done correctly
Question
Apparent authority of the Design Professional comes from actions taken that are not denied or contradicted by the Owner
Question
Commissioning a building is a new process brought about by new technologies
Question
Approving payment requests gives the Design Professional the implied authority to also reject portions of the payment request
Question
Staying past final acceptance to maintain the complicated equipment within a building is known as

A) Watchdogging
B) Commissioning
C) Total Quality Management
D) Contract compliance
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/11
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Warranties
1
A Contractor should check the Contract to determine the Actual Authority of the Design Professionals
True
2
Related to warranty periods

A) The Contract Administrator should make sure manufacturer's agreed warranties coincide with the project requirements
B) The Contract Administrator should pass on only those warranties that are still in place
C) Never pay more for what is required in the Contract warranty period
D) The Contract Administrator should begin all warranties at the time of Substantial completion
A
3
Expressed authority is

A) Usually detailed at the first project meeting so everyone clearly understands who has what authority
B) Is delineated in the contract
C) Is an verbal directive issued by the Owner
D) Is any verbal directive issued by either the Owner or the Owner's agent (e.g. Architect)
B
4
The Owner reserves the right in regard to uncorrected work to

A) Remove the Contractor from the project
B) Make corrections and backcharge the Contractor
C) Withhold payment
D) All of these
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
5
When it comes to quality

A) The Architect is the only inspector that counts
B) We can all be inspectors
C) The Owner will usually hire a special person
D) Whoever is in charge of safety can't be involved in quality
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
6
The process of project closeout

A) Begins upon substantial completion
B) Is up to the Owner
C) Begins when the Contract Administrator finishes reading the Contract
D) Is dictated by the Architect
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
7
Final payment guarantees the Constructor that everything has been done correctly
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
8
Apparent authority of the Design Professional comes from actions taken that are not denied or contradicted by the Owner
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
9
Commissioning a building is a new process brought about by new technologies
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
10
Approving payment requests gives the Design Professional the implied authority to also reject portions of the payment request
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
11
Staying past final acceptance to maintain the complicated equipment within a building is known as

A) Watchdogging
B) Commissioning
C) Total Quality Management
D) Contract compliance