Deck 1: Program and Project Management

Full screen (f)
exit full mode
Question
What are the two defining characteristics of a project?

A)Projects are ongoing and have repetitive tasks.
B)Projects are temporary and create a unique product.
C)Projects are ongoing and create a unique product.
D)Projects are temporary and have repetitive tasks.
Use Space or
up arrow
down arrow
to flip the card.
Question
What of the following is NOT a characteristic that both projects and operations share?

A)Both projects and operations have objectives.
B)Both projects and operations are managed.
C)Both projects and operations require resources, including funding and human resources.
D)Both projects and operations are temporary.
Question
Which of the following describes the definition of a functional organization?

A)Functional organizations have a traditional organizational structure, in which each
B)In functional organizations, each member of an individual department reports to the functional manager, who in turn reports to an executive.
C)For the most part, each department runs its projects entirely independent of the other organization's departments.
D)All of the above.
Question
In which of the following organizations does a project manager have the most authority?

A)Functional Organizations
B)Projectized Organizations
C)Matrix Organizations
D)Developmental Organizations
Question
Which of the following is a disadvantage to Matrix Management Organizations?

A)Organizational Synergy
B)Resource Optimization
C)Functional Gap
D)Information Sharing
Question
Which of the following is not one of the nine knowledge areas of project and/or program management?

A)Quality Management
B)Risk Management
C)Technical Management
D)Scope Management
Question
Which of the following is an example of a project?

A)Building a new zoo for the city
B)Running the city's Food Bank
C)Maintaining the collection at the local library
D)Running a farmer's market
Question
What is the main difference between project management and program management?

A)A project is focused on its product, service, or result; a program is focused on operations.
B)A project is focused on its product, service, or result; a program is focused on the benefits it will deliver in line with the organization's business strategy.
C)A project does not have stakeholders, whereas a program does.
D)There are no differences between project and program management.
Question
Which of the following is not true about a program?

A)As with projects, programs are ways of reaching an organization's goals and objectives. Programs, however, do this within the context of the organization's strategic plan.
B)Programs offer organizational benefits, including improving upon and adding to current systems.
C)A program never needs to be managed.
D)Programs may include work related to the program, but out of the scope of any individual projects included in the program.
Question
Microsoft Project is an acceptable Project Management Information System (PMIS).
Question
What are Key Performance Indicators used for at the strategic-plan level?

A)KPIs assess the current state of the organization and recommend appropriate actions.
B)KPIs monitor business activity in real time
C)KPIs measure otherwise-difficult activities, such as customer satisfaction and employee skill development.
D)All of the above
Question
Finn's boss asked him to put together a list of SMART key performance indicators for their organization, Iron Man, Inc. Which of the following lists correctly identifies SMART indicators?

A)Specific, Measurable, Achievable, Realistic, Timely
B)Solitary, Monetary, Accessible, Realistic, Timely
C)Strategic, Measurable, Authorized, Related, Targeted
D)Strong, Monetary, Achievable, Reactionary, Targeted
Question
Annika is a Program Manager for Serenity Now, Inc. which has recently launched a new program. Annika has been assigned to perform an analysis to verify that the metrics for the program are aligned with Serenity Now's strategic plan. Which analysis will she perform?

A)Alignment analysis
B)Stakeholder analysis
C)Gap analysis
D)Benefits analysis
Question
What is the metric that refers to organization earning called?

A)ROI
B)KPI
C)EBIT
D)Market share
Question
Boris is preparing to present his new program to the program board at Hiram Corp. As part of his pre-program setup, Boris is creating a high-level business plan that demonstrates of number of key attributes about his program. Which of the following attributes would Boris hope to demonstrate?

A)Feasibility
B)Justification
C)Need
D)All of the above
Question
Howard is a Program Manager and is preparing for an organization-wide kickoff meeting of his new program, Ferocious. Part of the kickoff will include a Q&A period about Ferocious, so Howard needs to gather some information about the program's potential risks. Which of the following is not a standard information-gathering technique that Howard could use?

A)Interviews
B)Internet Search
C)Delphi technique
D)SWOT Analysis
Question
While Howard is gathering information on potential risks for Ferocious, he decides to use a technique to reach a consensus among all the experts who are weighing in on the program. He facilitates a program for sharing ideas and information anonymously. What technique is Howard using?

A)SWOT Analysis
B)Brainstorming
C)Delphi technique
D)Surveys
Question
Howard's program, Ferocious, has been well-received at his company. Now, he needs to create a program charter. Which of the following will not be included in Howard's program charter to launch Ferocious?

A)Key objectives
B)List of high-level executives who will be involved in program planning
C)Expected benefits the program will deliver
D)The program vision
Question
What is the primary purpose of the pre-program setup phase?

A)To write a strategic plan for the organization
B)Write a scope statement for each project that will be part of the larger program
C)Prepare a detailed plan for program management
D)Gain approval for the new program
Question
Which of the following is not an output item of the Initiate Program phase?

A)Program management plan
B)Program benefits statement
C)Program charter
D)Business case
Question
Howard is using the standard Initiate Program process for his new program, Ferocious. What is the main document that will establish the feasibility of Ferocious called?

A)Statement of work
B)Program charter
C)Benefits realization plan
D)Feasibility Management plan
Question
Lori is a program manager for OMG Awesome Toys. OMG Awesome Toys uses matrix management. Where can matrix management be used?

A)In program management
B)In project management
C)In both program and project management
D)At the executive level only
Question
Choose the answer that is not part of a program.

A)Projects
B)Operations
C)Project schedules
D)Project portfolio
Question
As a program manager, Dixon must interview candidates for project manager positions for his program. Dixon's bosses at Eureka Binary Farms have told him to make sure the candidates are informed of the culture of their organization. The organizational culture of Eureka Binary Farms is reflected by:

A)Values, norms, and strategic plan
B)Policies, annual revenue, and values
C)Authority levels of the managers, policies, values, and work environment
D)Beliefs, norms, and employee turnover rate
Question
The program life cycle is defined as:

A)A combination of nine knowledge areas
B)A combination of seven phases
C)A combination of five phases
D)A combination of five process groups
Question
You are taking a class on Program Management with Professor Wrothgar. Wrothgar's seminar, "Themes of program management that run through the program cycle," would discuss the following themes:

A)PMO, benefits management, and program stakeholder management
B)Program governance, program stakeholder management, and benefits management
C)Program control, benefits management, and program governance
D)Program governance, program stakeholder management, and benefits realization
Question
Suzanne has been putting in long hours and her program has finally reached the execution stage. Her manager, Finn, has called her in on a Saturday to produce a list of the program's key stakeholders. This list would include:

A)Customers, project team members, and project managers
B)Facility managers, program sponsors, and program team members
C)(CIO) chief information officer, program director, and program team members
D)Database administrator, program governance board, and program manager
Question
Program Initiating is which of the following?

A)A phase
B)A process group
C)A knowledge area
D)A process
Question
The first phase of a program life cycle is called:

A)Program setup
B)Initiating
C)Planning
D)Pre-program setup
Question
Howard is about to initiate a program for Start Up! Blow Up! Candies. What would Howard's program Initiating process group include?

A)Authorize Program, Initiate Team, and Initiate Program
B)Initiate Program, Initiate Team, and Authorize Projects
C)Scope Definition, Initiate Program, and Initiate Team
D)Develop Program Charter, Authorize Projects, and Initiate Program
Question
Which of the following are appointments either made or identified during the Initiate Program phase?

A)Program manager, sponsor, and principle team members
B)Sponsor and principle team members
C)Program manager and sponsor
D)Program manager and principle team members
Question
Finn is preparing for a kick-off meeting of his new program at Iron Man, Inc. Which of the following is the main goal of his upcoming kick-off?

A)Finn wants to familiarize everyone at Iron Man, Inc. with his new program.
B)Finn can only schedule one kickoff meeting
C)Finn's main goal is to raise money for the new program.
D)Finn's main goal is to gather and introduce all of the principle team members.
Question
Lori's boss has asked her to establish the selection criteria for projects in the program she is managing, DePaolo. Which process will she perform?

A)Select Project
B)Initiate Program
C)Initiate Principle Team
D)Authorize Project
Question
Benjamin is performing the resource planning process for the Frescata program. Which of the following is not a tool or technique that Benjamin can use for this process?

A)Pareto diagram
B)Project-management software
C)Expert judgment
D)Alternative identification
Question
You are launching a brand new program at your company. Listed below are a set of processes that you will be performing for your program for the first time. Which of the processes will you perform first?

A)Create PWBS
B)Cost Estimating/Budgeting
C)Schedule Development
D)Resource Planning
Question
Lori is all fired up and at a stage to initiate a program for OMG Awesome Toys. But her manager Rudy Ninibocker pops his head into Lori's office and says, "Now hold on, Lori, don't forget to work on the business case before performing this process." What process is Ninibocker referring to?

A)Initiate Team
B)Initiate Program
C)Authorize Projects
D)Develop Program Charter
Question
Which is NOT an output item of the Initiate Program process?

A)Project Selection criteria
B)Program charter
C)Benefits realization plan
D)Detailed program scope statement
Question
Which process determines the program reporting requirements for the projects?

A)Authorize Programs
B)Authorize Projects
C)Initiate Projects
D)Initiate Program
Question
Finnian is the program manager of a program called Too Cute for Comfort. Annika's Pink Emporium, the program's sponsor, is asking for the program team directory. Which process does Finnian need to perform to create this document?

A)Initiate Program
B)Initiate Projects
C)Initiate Team
D)Authorize Projects
Question
Which is NOT a tool or technique common to most of the program management process?

A)Delphi
B)Expert judgment
C)Policies and procedures
D)Meetings
Question
Bovary McHumphrey is making a list of the techniques and tools she will need to perform the Initiate Program. Her list should include:

A)Expert judgment, benefits analysis, and benefits realization plan
B)Expert judgment, benefits analysis, and project selection methods
C)Expert judgment, benefits analysis, and project selection criteria
D)Expert judgment, benefits analysis, and Ishikawa diagram
Question
What is a program scope management plan?

A)A document that contains the program vision, benefits expected from the program, constraints, and key objectives.
B)A document that includes a definition of each benefit of the program and how they relate to the business strategy of the organization.
C)A document detailing how the scope will be identified, administered, and controlled throughout the life of the program
D)A document that draws boundaries around the program
Question
Which of the following is not included in the program scope management plan?

A)How to create the PWBS from the scope
B)A description of how the PWBS will be approved and managed
C)A process for how to handle requests for changes to the scope statement
D)A benefits analysis
Question
Howard's program, Ferocious, has been approved. Now, Howard needs to create his Program Work Breakdown Structure, or PWBS. Which if the following are necessary input items to create the PWBS?

A)Benefits realization plan
B)Program scope statement
C)Scope management plan
D)All of the above
Question
Lori has been asked to create a PWBS dictionary for the DePaolo program. Which of the following is not a possible element that could be included in her PWBS dictionary?

A)Detailed budget for each project within DePaolo
B)A list of schedule milestones for DePaolo
C)Cost Estimate
D)List of resources Lori and her team will need to complete DePaolo
Question
Which of the following processes does not belong to the Integration Management knowledge area?

A)Interface Planning
B)Resource Planning
C)Marketing Planning
D)Transition Planning
Question
What is program scope definition?

A)A deliverable-oriented plan that includes what deliverables will be delivered and when
B)A plan for the program, including the program charter, preliminary scope statement, and the benefits realization plan
C)A definition of the key deliverable generated by the program
D)A list of the program management information system and stakeholder knowledge sets.
Question
Which of the following is part of the program management plan?

A)Stakeholder skill sets
B)Configuration management system
C)Program management information system
D)All of the above
Question
Howard is creating a program WBS hierarchy for his program, Ferocious. Which of the following components is at the lowest level of his hierarchy?

A)Schedule activities
B)Program deliverables
C)Program packages
D)Work packages
Question
Adam is creating program schedule. He is trying to define the program components and the dependencies among those components. Adam realized that some of the program components will be needed only if certain conditions are met along the program schedule. Which diagramming method should Adam use to display those components?

A)Precedence diagramming method (PDM)
B)Conditional diagramming method (CDM)
C)Arrow diagramming method (ADM)
D)Forceful diagramming method (FDM)
Question
You asked your friend Dixon, a program manager at PowerUp, to lunch. Dixon said he was swamped. He explained that he is using the coding structure to perform a certain process. Which process is Dixon most likely talking about?

A)Human Resource Planning
B)Decomposition
C)Program Cost Estimating and Budgeting
D)Program Schedule Development
Question
Which of the following structures displays the breakdown of project deliverables into smaller, more manageable components?

A)(PBS) Project breakdown structure
B)(WBS) Work breakdown structure
C)(HWS) Hierarchical work structure
D)(SND) Schedule Network Diagram
Question
Josh is a program manager who likes to keep on top of things at You Want It - We Build It Industrial. So when he's telling his project managers to prep project plans for each project based on the most current and available information, having them make changes as new information comes in, what technique is he using?

A)Delphi technique
B)Progressive elaboration
C)Continuous improvement
D)Slow start
Question
Which of the following is stage two of a program life cycle?

A)Planning
B)Program setup
C)Initiating
D)Pre-program setup
Question
Integration Management includes which program Planning processes?

A)Develop Program Management Plan, Transition Planning, and Plan Program Contracting
B)Develop Program Management Plan, Transition Planning, and Resource Planning
C)Develop Program Management Plan, Integrated Change Control, and Resource Planning
D)Develop Program Management Plan, Quality Planning, and Resource Planning
Question
Which knowledge area does Transition Planning belong to?

A)Communication Management
B)Procurement Management
C)Human Resource Management
D)Integration Management
Question
What program Planning processes belong to Scope Management?

A)Scope Definition and Schedule Development
B)(PWBS) Create Program Work Breakdown Structure and Plan Scope
C)Scope Definition and Scope Control
D)Scope Definition and (PWBS) Create Program Work Breakdown Structure
Question
Fae's program, Don't Be Boxed Out, is in the planning stage, and she would like to determine the resource requirements for her program. What process should Fae perform?

A)Resource Management
B)Activity Resource Estimating
C)Create PWBS
D)Resource Planning
Question
Which is NOT an input item to the Scope Definition process?

A)Preliminary program scope statement
B)Program charter
C)Program scope statement
D)Benefits realization plan
Question
Barkley wants to develop a scope management plan for his Pet Groomers program. Which process should Barkley perform?

A)Create PWBS
B)Scope Definition
C)Scope Planning
D)Develop Scope Management plan
Question
The Scope Definition process generates which of the following:

A)Scope management plan
B)Preliminary program scope statement
C)Benefits realization plan
D)PWBS
Question
What are the components at the lowest level of a program WBS hierarchy called?

A)Program deliverables
B)Program packages
C)Work packages
D)Schedule activity
Question
Dixon is performing the Interface Planning process for his Art-2 Unit program. Which is not a tool or technique that can be used for this process?

A)Pareto diagram
B)Organizational theory
C)Stakeholder analysis
D)Human resource practices
Question
A resource histogram is used in which process?

A)Resource Optimization
B)Develop Program Management Plan
C)Resource Planning
D)Interface Planning
Question
Josh is working on a brand new program, Need a Date!, and he's going to be performing the following processes for the first time for his program. Which is the first process he should perform?

A)Create PWBS
B)Schedule Development
C)Scope Definition
D)Transition Planning
Question
The schedule management plan is an output of which of the following processes?

A)Schedule Development
B)Program Planning
C)Schedule Planning
D)Schedule Definition
Question
The Black Forest Tie Affair program is currently in the planning stages. Its program sponsor, Randolph Moneypenny, says to Miguel, the program manager, "I need an organizational chart. Please perform this process." Which process is Mr. Moneypenny speaking of?

A)Human Resource Planning
B)Resource Planning
C)Organizational Planning
D)Schedule Development
Question
David is the program manager of the Make It Look Good program, which is in the planning stage. David isn't certain if items should be purchased or produced in-house. Which process should David perform to decide?

A)Procurement Planning
B)Plan Program Contracting
C)Risk Management Planning
D)Plan Program Purchases and Acquisitions
Question
It was Bob's job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?

A)Arrow diagramming method only
B)Precedence diagramming method only
C)Either the PDM or the ADM
D)Critical diagramming method
Question
In order to determine the program budget, which program management process must be performed?

A)Develop Program Budget
B)Plan Program Purchases and Acquisitions
C)Resource Planning
D)Cost Estimating and Budgeting
Question
Boris is the manager of the Yes I Read book-publishing program. He has decided to procure book cover images from a digital design company for the next fiscal year. Currently Boris has no idea how many books he will publish in the year. What type of contract is most suitable for Boris to use when he signs with the digital design company?

A)Fixed price
B)Time and material
C)Cost plus fee
D)Lump sum
Question
From which of the following do risks originate?

A)Quality requirements
B)Strategic plan
C)Constraints
D)Uncertainty
Question
Which is NOT included in the Communication Planning process?

A)Determine the technology requirements for the communication
B)Determine the information needs of the program stakeholders
C)Determine who needs what information and when
D)Issue a request for information, a request for proposal, and a request for quotation
Question
What is needed before performing the Quality Planning process?

A)Program cost of quality and quality metrics
B)Product description and quality checklists
C)Program scope statement and operational definitions
D)Program scope statement and product description
Question
What are the two main types of project reserve accounts? Select two:

A)Management reserve
B)Mitigation reserve
C)Resource bench
D)Contingency reserve
E)Injured reserve
Question
Which statement is correct?

A)Quality metrics are an input to Perform Quality Control
B)Quality metrics are an output of Perform Quality Assurance
C)Quality metrics are an input to Quality Planning
D)Quality metrics are an output of Quality Planning
Question
What is a risk response plan for a program an output of?

A)Identify Risks
B)Risk Management Planning and Analysis
C)Qualitative Risks Analysis
D)Plan Risk Responses
Question
Which process must be performed to develop a contract statement of work?

A)Plan Program Contracting
B)Plan Program Purchases and Acquisitions
C)Develop Statement Work
D)Develop Program Management Plan
Question
Boris wants to figure out how much more his company should invest into the quality of a certain product. What tool would be most effective for this exercise?

A)Fishbone diagram
B)Control chart
C)Run chart
D)Pareto chart
E)Marginal analysis
Question
Boris hires an outside vendor to maintain their servers. However, he is extremely concerned about uptime. In order to remain profitable, Boris' company needs to have 99% uptime. Which of the following would be a clause Boris would want to include in the contract to directly address this requirement?

A)Privity
B)VC
C)SLA
D)CPPF
E)Retainage
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/170
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 1: Program and Project Management
1
What are the two defining characteristics of a project?

A)Projects are ongoing and have repetitive tasks.
B)Projects are temporary and create a unique product.
C)Projects are ongoing and create a unique product.
D)Projects are temporary and have repetitive tasks.
Projects are temporary and create a unique product.
2
What of the following is NOT a characteristic that both projects and operations share?

A)Both projects and operations have objectives.
B)Both projects and operations are managed.
C)Both projects and operations require resources, including funding and human resources.
D)Both projects and operations are temporary.
Both projects and operations are temporary.
3
Which of the following describes the definition of a functional organization?

A)Functional organizations have a traditional organizational structure, in which each
B)In functional organizations, each member of an individual department reports to the functional manager, who in turn reports to an executive.
C)For the most part, each department runs its projects entirely independent of the other organization's departments.
D)All of the above.
All of the above.
4
In which of the following organizations does a project manager have the most authority?

A)Functional Organizations
B)Projectized Organizations
C)Matrix Organizations
D)Developmental Organizations
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
5
Which of the following is a disadvantage to Matrix Management Organizations?

A)Organizational Synergy
B)Resource Optimization
C)Functional Gap
D)Information Sharing
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following is not one of the nine knowledge areas of project and/or program management?

A)Quality Management
B)Risk Management
C)Technical Management
D)Scope Management
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
7
Which of the following is an example of a project?

A)Building a new zoo for the city
B)Running the city's Food Bank
C)Maintaining the collection at the local library
D)Running a farmer's market
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
8
What is the main difference between project management and program management?

A)A project is focused on its product, service, or result; a program is focused on operations.
B)A project is focused on its product, service, or result; a program is focused on the benefits it will deliver in line with the organization's business strategy.
C)A project does not have stakeholders, whereas a program does.
D)There are no differences between project and program management.
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following is not true about a program?

A)As with projects, programs are ways of reaching an organization's goals and objectives. Programs, however, do this within the context of the organization's strategic plan.
B)Programs offer organizational benefits, including improving upon and adding to current systems.
C)A program never needs to be managed.
D)Programs may include work related to the program, but out of the scope of any individual projects included in the program.
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
10
Microsoft Project is an acceptable Project Management Information System (PMIS).
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
11
What are Key Performance Indicators used for at the strategic-plan level?

A)KPIs assess the current state of the organization and recommend appropriate actions.
B)KPIs monitor business activity in real time
C)KPIs measure otherwise-difficult activities, such as customer satisfaction and employee skill development.
D)All of the above
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
12
Finn's boss asked him to put together a list of SMART key performance indicators for their organization, Iron Man, Inc. Which of the following lists correctly identifies SMART indicators?

A)Specific, Measurable, Achievable, Realistic, Timely
B)Solitary, Monetary, Accessible, Realistic, Timely
C)Strategic, Measurable, Authorized, Related, Targeted
D)Strong, Monetary, Achievable, Reactionary, Targeted
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
13
Annika is a Program Manager for Serenity Now, Inc. which has recently launched a new program. Annika has been assigned to perform an analysis to verify that the metrics for the program are aligned with Serenity Now's strategic plan. Which analysis will she perform?

A)Alignment analysis
B)Stakeholder analysis
C)Gap analysis
D)Benefits analysis
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
14
What is the metric that refers to organization earning called?

A)ROI
B)KPI
C)EBIT
D)Market share
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
15
Boris is preparing to present his new program to the program board at Hiram Corp. As part of his pre-program setup, Boris is creating a high-level business plan that demonstrates of number of key attributes about his program. Which of the following attributes would Boris hope to demonstrate?

A)Feasibility
B)Justification
C)Need
D)All of the above
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
16
Howard is a Program Manager and is preparing for an organization-wide kickoff meeting of his new program, Ferocious. Part of the kickoff will include a Q&A period about Ferocious, so Howard needs to gather some information about the program's potential risks. Which of the following is not a standard information-gathering technique that Howard could use?

A)Interviews
B)Internet Search
C)Delphi technique
D)SWOT Analysis
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
17
While Howard is gathering information on potential risks for Ferocious, he decides to use a technique to reach a consensus among all the experts who are weighing in on the program. He facilitates a program for sharing ideas and information anonymously. What technique is Howard using?

A)SWOT Analysis
B)Brainstorming
C)Delphi technique
D)Surveys
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
18
Howard's program, Ferocious, has been well-received at his company. Now, he needs to create a program charter. Which of the following will not be included in Howard's program charter to launch Ferocious?

A)Key objectives
B)List of high-level executives who will be involved in program planning
C)Expected benefits the program will deliver
D)The program vision
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
19
What is the primary purpose of the pre-program setup phase?

A)To write a strategic plan for the organization
B)Write a scope statement for each project that will be part of the larger program
C)Prepare a detailed plan for program management
D)Gain approval for the new program
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
20
Which of the following is not an output item of the Initiate Program phase?

A)Program management plan
B)Program benefits statement
C)Program charter
D)Business case
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
21
Howard is using the standard Initiate Program process for his new program, Ferocious. What is the main document that will establish the feasibility of Ferocious called?

A)Statement of work
B)Program charter
C)Benefits realization plan
D)Feasibility Management plan
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
22
Lori is a program manager for OMG Awesome Toys. OMG Awesome Toys uses matrix management. Where can matrix management be used?

A)In program management
B)In project management
C)In both program and project management
D)At the executive level only
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
23
Choose the answer that is not part of a program.

A)Projects
B)Operations
C)Project schedules
D)Project portfolio
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
24
As a program manager, Dixon must interview candidates for project manager positions for his program. Dixon's bosses at Eureka Binary Farms have told him to make sure the candidates are informed of the culture of their organization. The organizational culture of Eureka Binary Farms is reflected by:

A)Values, norms, and strategic plan
B)Policies, annual revenue, and values
C)Authority levels of the managers, policies, values, and work environment
D)Beliefs, norms, and employee turnover rate
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
25
The program life cycle is defined as:

A)A combination of nine knowledge areas
B)A combination of seven phases
C)A combination of five phases
D)A combination of five process groups
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
26
You are taking a class on Program Management with Professor Wrothgar. Wrothgar's seminar, "Themes of program management that run through the program cycle," would discuss the following themes:

A)PMO, benefits management, and program stakeholder management
B)Program governance, program stakeholder management, and benefits management
C)Program control, benefits management, and program governance
D)Program governance, program stakeholder management, and benefits realization
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
27
Suzanne has been putting in long hours and her program has finally reached the execution stage. Her manager, Finn, has called her in on a Saturday to produce a list of the program's key stakeholders. This list would include:

A)Customers, project team members, and project managers
B)Facility managers, program sponsors, and program team members
C)(CIO) chief information officer, program director, and program team members
D)Database administrator, program governance board, and program manager
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
28
Program Initiating is which of the following?

A)A phase
B)A process group
C)A knowledge area
D)A process
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
29
The first phase of a program life cycle is called:

A)Program setup
B)Initiating
C)Planning
D)Pre-program setup
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
30
Howard is about to initiate a program for Start Up! Blow Up! Candies. What would Howard's program Initiating process group include?

A)Authorize Program, Initiate Team, and Initiate Program
B)Initiate Program, Initiate Team, and Authorize Projects
C)Scope Definition, Initiate Program, and Initiate Team
D)Develop Program Charter, Authorize Projects, and Initiate Program
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
31
Which of the following are appointments either made or identified during the Initiate Program phase?

A)Program manager, sponsor, and principle team members
B)Sponsor and principle team members
C)Program manager and sponsor
D)Program manager and principle team members
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
32
Finn is preparing for a kick-off meeting of his new program at Iron Man, Inc. Which of the following is the main goal of his upcoming kick-off?

A)Finn wants to familiarize everyone at Iron Man, Inc. with his new program.
B)Finn can only schedule one kickoff meeting
C)Finn's main goal is to raise money for the new program.
D)Finn's main goal is to gather and introduce all of the principle team members.
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
33
Lori's boss has asked her to establish the selection criteria for projects in the program she is managing, DePaolo. Which process will she perform?

A)Select Project
B)Initiate Program
C)Initiate Principle Team
D)Authorize Project
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
34
Benjamin is performing the resource planning process for the Frescata program. Which of the following is not a tool or technique that Benjamin can use for this process?

A)Pareto diagram
B)Project-management software
C)Expert judgment
D)Alternative identification
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
35
You are launching a brand new program at your company. Listed below are a set of processes that you will be performing for your program for the first time. Which of the processes will you perform first?

A)Create PWBS
B)Cost Estimating/Budgeting
C)Schedule Development
D)Resource Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
36
Lori is all fired up and at a stage to initiate a program for OMG Awesome Toys. But her manager Rudy Ninibocker pops his head into Lori's office and says, "Now hold on, Lori, don't forget to work on the business case before performing this process." What process is Ninibocker referring to?

A)Initiate Team
B)Initiate Program
C)Authorize Projects
D)Develop Program Charter
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
37
Which is NOT an output item of the Initiate Program process?

A)Project Selection criteria
B)Program charter
C)Benefits realization plan
D)Detailed program scope statement
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
38
Which process determines the program reporting requirements for the projects?

A)Authorize Programs
B)Authorize Projects
C)Initiate Projects
D)Initiate Program
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
39
Finnian is the program manager of a program called Too Cute for Comfort. Annika's Pink Emporium, the program's sponsor, is asking for the program team directory. Which process does Finnian need to perform to create this document?

A)Initiate Program
B)Initiate Projects
C)Initiate Team
D)Authorize Projects
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
40
Which is NOT a tool or technique common to most of the program management process?

A)Delphi
B)Expert judgment
C)Policies and procedures
D)Meetings
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
41
Bovary McHumphrey is making a list of the techniques and tools she will need to perform the Initiate Program. Her list should include:

A)Expert judgment, benefits analysis, and benefits realization plan
B)Expert judgment, benefits analysis, and project selection methods
C)Expert judgment, benefits analysis, and project selection criteria
D)Expert judgment, benefits analysis, and Ishikawa diagram
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
42
What is a program scope management plan?

A)A document that contains the program vision, benefits expected from the program, constraints, and key objectives.
B)A document that includes a definition of each benefit of the program and how they relate to the business strategy of the organization.
C)A document detailing how the scope will be identified, administered, and controlled throughout the life of the program
D)A document that draws boundaries around the program
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
43
Which of the following is not included in the program scope management plan?

A)How to create the PWBS from the scope
B)A description of how the PWBS will be approved and managed
C)A process for how to handle requests for changes to the scope statement
D)A benefits analysis
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
44
Howard's program, Ferocious, has been approved. Now, Howard needs to create his Program Work Breakdown Structure, or PWBS. Which if the following are necessary input items to create the PWBS?

A)Benefits realization plan
B)Program scope statement
C)Scope management plan
D)All of the above
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
45
Lori has been asked to create a PWBS dictionary for the DePaolo program. Which of the following is not a possible element that could be included in her PWBS dictionary?

A)Detailed budget for each project within DePaolo
B)A list of schedule milestones for DePaolo
C)Cost Estimate
D)List of resources Lori and her team will need to complete DePaolo
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
46
Which of the following processes does not belong to the Integration Management knowledge area?

A)Interface Planning
B)Resource Planning
C)Marketing Planning
D)Transition Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
47
What is program scope definition?

A)A deliverable-oriented plan that includes what deliverables will be delivered and when
B)A plan for the program, including the program charter, preliminary scope statement, and the benefits realization plan
C)A definition of the key deliverable generated by the program
D)A list of the program management information system and stakeholder knowledge sets.
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
48
Which of the following is part of the program management plan?

A)Stakeholder skill sets
B)Configuration management system
C)Program management information system
D)All of the above
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
49
Howard is creating a program WBS hierarchy for his program, Ferocious. Which of the following components is at the lowest level of his hierarchy?

A)Schedule activities
B)Program deliverables
C)Program packages
D)Work packages
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
50
Adam is creating program schedule. He is trying to define the program components and the dependencies among those components. Adam realized that some of the program components will be needed only if certain conditions are met along the program schedule. Which diagramming method should Adam use to display those components?

A)Precedence diagramming method (PDM)
B)Conditional diagramming method (CDM)
C)Arrow diagramming method (ADM)
D)Forceful diagramming method (FDM)
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
51
You asked your friend Dixon, a program manager at PowerUp, to lunch. Dixon said he was swamped. He explained that he is using the coding structure to perform a certain process. Which process is Dixon most likely talking about?

A)Human Resource Planning
B)Decomposition
C)Program Cost Estimating and Budgeting
D)Program Schedule Development
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
52
Which of the following structures displays the breakdown of project deliverables into smaller, more manageable components?

A)(PBS) Project breakdown structure
B)(WBS) Work breakdown structure
C)(HWS) Hierarchical work structure
D)(SND) Schedule Network Diagram
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
53
Josh is a program manager who likes to keep on top of things at You Want It - We Build It Industrial. So when he's telling his project managers to prep project plans for each project based on the most current and available information, having them make changes as new information comes in, what technique is he using?

A)Delphi technique
B)Progressive elaboration
C)Continuous improvement
D)Slow start
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
54
Which of the following is stage two of a program life cycle?

A)Planning
B)Program setup
C)Initiating
D)Pre-program setup
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
55
Integration Management includes which program Planning processes?

A)Develop Program Management Plan, Transition Planning, and Plan Program Contracting
B)Develop Program Management Plan, Transition Planning, and Resource Planning
C)Develop Program Management Plan, Integrated Change Control, and Resource Planning
D)Develop Program Management Plan, Quality Planning, and Resource Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
56
Which knowledge area does Transition Planning belong to?

A)Communication Management
B)Procurement Management
C)Human Resource Management
D)Integration Management
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
57
What program Planning processes belong to Scope Management?

A)Scope Definition and Schedule Development
B)(PWBS) Create Program Work Breakdown Structure and Plan Scope
C)Scope Definition and Scope Control
D)Scope Definition and (PWBS) Create Program Work Breakdown Structure
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
58
Fae's program, Don't Be Boxed Out, is in the planning stage, and she would like to determine the resource requirements for her program. What process should Fae perform?

A)Resource Management
B)Activity Resource Estimating
C)Create PWBS
D)Resource Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
59
Which is NOT an input item to the Scope Definition process?

A)Preliminary program scope statement
B)Program charter
C)Program scope statement
D)Benefits realization plan
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
60
Barkley wants to develop a scope management plan for his Pet Groomers program. Which process should Barkley perform?

A)Create PWBS
B)Scope Definition
C)Scope Planning
D)Develop Scope Management plan
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
61
The Scope Definition process generates which of the following:

A)Scope management plan
B)Preliminary program scope statement
C)Benefits realization plan
D)PWBS
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
62
What are the components at the lowest level of a program WBS hierarchy called?

A)Program deliverables
B)Program packages
C)Work packages
D)Schedule activity
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
63
Dixon is performing the Interface Planning process for his Art-2 Unit program. Which is not a tool or technique that can be used for this process?

A)Pareto diagram
B)Organizational theory
C)Stakeholder analysis
D)Human resource practices
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
64
A resource histogram is used in which process?

A)Resource Optimization
B)Develop Program Management Plan
C)Resource Planning
D)Interface Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
65
Josh is working on a brand new program, Need a Date!, and he's going to be performing the following processes for the first time for his program. Which is the first process he should perform?

A)Create PWBS
B)Schedule Development
C)Scope Definition
D)Transition Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
66
The schedule management plan is an output of which of the following processes?

A)Schedule Development
B)Program Planning
C)Schedule Planning
D)Schedule Definition
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
67
The Black Forest Tie Affair program is currently in the planning stages. Its program sponsor, Randolph Moneypenny, says to Miguel, the program manager, "I need an organizational chart. Please perform this process." Which process is Mr. Moneypenny speaking of?

A)Human Resource Planning
B)Resource Planning
C)Organizational Planning
D)Schedule Development
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
68
David is the program manager of the Make It Look Good program, which is in the planning stage. David isn't certain if items should be purchased or produced in-house. Which process should David perform to decide?

A)Procurement Planning
B)Plan Program Contracting
C)Risk Management Planning
D)Plan Program Purchases and Acquisitions
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
69
It was Bob's job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?

A)Arrow diagramming method only
B)Precedence diagramming method only
C)Either the PDM or the ADM
D)Critical diagramming method
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
70
In order to determine the program budget, which program management process must be performed?

A)Develop Program Budget
B)Plan Program Purchases and Acquisitions
C)Resource Planning
D)Cost Estimating and Budgeting
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
71
Boris is the manager of the Yes I Read book-publishing program. He has decided to procure book cover images from a digital design company for the next fiscal year. Currently Boris has no idea how many books he will publish in the year. What type of contract is most suitable for Boris to use when he signs with the digital design company?

A)Fixed price
B)Time and material
C)Cost plus fee
D)Lump sum
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
72
From which of the following do risks originate?

A)Quality requirements
B)Strategic plan
C)Constraints
D)Uncertainty
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
73
Which is NOT included in the Communication Planning process?

A)Determine the technology requirements for the communication
B)Determine the information needs of the program stakeholders
C)Determine who needs what information and when
D)Issue a request for information, a request for proposal, and a request for quotation
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
74
What is needed before performing the Quality Planning process?

A)Program cost of quality and quality metrics
B)Product description and quality checklists
C)Program scope statement and operational definitions
D)Program scope statement and product description
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
75
What are the two main types of project reserve accounts? Select two:

A)Management reserve
B)Mitigation reserve
C)Resource bench
D)Contingency reserve
E)Injured reserve
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
76
Which statement is correct?

A)Quality metrics are an input to Perform Quality Control
B)Quality metrics are an output of Perform Quality Assurance
C)Quality metrics are an input to Quality Planning
D)Quality metrics are an output of Quality Planning
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
77
What is a risk response plan for a program an output of?

A)Identify Risks
B)Risk Management Planning and Analysis
C)Qualitative Risks Analysis
D)Plan Risk Responses
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
78
Which process must be performed to develop a contract statement of work?

A)Plan Program Contracting
B)Plan Program Purchases and Acquisitions
C)Develop Statement Work
D)Develop Program Management Plan
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
79
Boris wants to figure out how much more his company should invest into the quality of a certain product. What tool would be most effective for this exercise?

A)Fishbone diagram
B)Control chart
C)Run chart
D)Pareto chart
E)Marginal analysis
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
80
Boris hires an outside vendor to maintain their servers. However, he is extremely concerned about uptime. In order to remain profitable, Boris' company needs to have 99% uptime. Which of the following would be a clause Boris would want to include in the contract to directly address this requirement?

A)Privity
B)VC
C)SLA
D)CPPF
E)Retainage
Unlock Deck
Unlock for access to all 170 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 170 flashcards in this deck.