Deck 1: Construction and Costing Projects
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/24
Play
Full screen (f)
Deck 1: Construction and Costing Projects
1
_____________is required for preliminary studies of various aspects of a work or project.
A)supplementary estimate
B)plinth area estimate
C)revised estimate
D)abstract estimate
A)supplementary estimate
B)plinth area estimate
C)revised estimate
D)abstract estimate
abstract estimate
2
Per kilometre basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 50000/- per 1 km works out as Rs. 5 lakh.
False
3
Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span comes to 3*50*30000 = Rs. 45 lakhs.
True
4
Approximate cost of sewerage project for a population of one Rs. 10/- head works out as Rs. 10 lakh.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
5
_____________is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.
A)cube rate estimate
B)supplementary estimate
C)maintenance estimate
D)plinth area estimate
A)cube rate estimate
B)supplementary estimate
C)maintenance estimate
D)plinth area estimate
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
6
_____________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.
A)prime cost
B)provisional sum
C)capital cost
D)building cost index
A)prime cost
B)provisional sum
C)capital cost
D)building cost index
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
7
___________estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.
A)supplementary and revised estimate
B)maintenance estimate
C)item rate estimate
D)revised estimate
A)supplementary and revised estimate
B)maintenance estimate
C)item rate estimate
D)revised estimate
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
8
A large work or project may consists of several building or small works and each of these work is known as _____________
A)sub-work
B)sub-project
C)sub-head
D)sub-construction
A)sub-work
B)sub-project
C)sub-head
D)sub-construction
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
9
The term _____________is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.
A)prime cost
B)hour-work
C)day-work
D)sub-work
A)prime cost
B)hour-work
C)day-work
D)sub-work
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
10
The surface of the highway pavement should be designed to allow _____________
A)high rolling resistance
B)low rolling resistance
C)no rolling resistance
D)very high rolling resistance
A)high rolling resistance
B)low rolling resistance
C)no rolling resistance
D)very high rolling resistance
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
11
The soil becomes weak in _____________
A)summer
B)winter
C)rainy season
D)spring season
A)summer
B)winter
C)rainy season
D)spring season
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following pavement has greater life?
A)bituminous pavements
B)cement concrete pavements
C)gravel roads
D)earth roads
A)bituminous pavements
B)cement concrete pavements
C)gravel roads
D)earth roads
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
13
Which of the following requirement is given most importance in highway design?
A)structural
B)functional
C)seasonal
D)maintenance
A)structural
B)functional
C)seasonal
D)maintenance
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
14
The surface of the pavement should be
A)smooth
B)rough
C)sufficient enough to resist skid
D)very rough
A)smooth
B)rough
C)sufficient enough to resist skid
D)very rough
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
15
The drainage layer is _____________
A)surface course
B)sub base
C)base
D)sub grade
A)surface course
B)sub base
C)base
D)sub grade
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
16
The maximum stress sustained by concrete pavements in kg/cm2 is _____________
A)40
B)45
C)50
D)55
A)40
B)45
C)50
D)55
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
17
The ICPB type of pavement uses
A)concrete paver blocks
B)fly ash
C)ggbs
D)rmc
A)concrete paver blocks
B)fly ash
C)ggbs
D)rmc
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
18
The ICPB may be used in _____________
A)water logged areas
B)parks
C)footpaths
D)highways
A)water logged areas
B)parks
C)footpaths
D)highways
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
19
The maximum length of vehicle that can be used on Indian roads is _____________
A)11
B)12
C)13
D)14
A)11
B)12
C)13
D)14
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
20
The design period of cement concrete road is taken as _____________
A)20
B)25
C)30
D)35
A)20
B)25
C)30
D)35
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
21
In India the flexible pavement is designed as per _____________
A)msa
B)ksa
C)csa
D)fsa
A)msa
B)ksa
C)csa
D)fsa
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following materials is not used in the construction of a septic tank?
A)concrete
B)rubber
C)fibreglass
D)plastic
A)concrete
B)rubber
C)fibreglass
D)plastic
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
23
Septic tank is a small scale treatment unit.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
24
The shape of the tank is circular.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck