Deck 5: Selected Contract Issues

Full screen (f)
exit full mode
Question
A statement by an architect to a contractor may be sufficient to establish that the architect is the owner's agent.
Use Space or
up arrow
down arrow
to flip the card.
Question
A sub-subcontractor would be covered by a one-tier labour and material payment bond.
Question
What type of agency relationship may be established by representations the owner makes in the construction contract documents? Who is that agency relationship between?
Question
What name is given to an agreement in which one party agrees to bear the financial loss of another party for a specified event?
Question
Under a pay-when-paid clause, if the owner never pays the main contractor, when must the main contractor pay the subcontractors?

A) on the date the owner was due to pay the main contractor
B) a reasonable time after the payment was due
C) when the subcontractor has completed work under the subcontract
D) if the owner never pays, the main contractor is not required to pay the subcontractor
Question
Which of the following is true for pay-if-paid clauses between contractors and subcontractors where the contractor is unpaid by the owner?

A) in the absence of default by a subcontractor, they create the only possible excuse for a contractor who has not paid a subcontractor
B) they are never enforced by the courts
C) the triggering event for a pay-if-paid clause is a breach of contract between the contractor and the subcontractor
D) none of the above
Question
Terms from which contract are typically incorporated by reference into subcontracts?

A) a similar subcontract between the main contractor and another subcontractor
B) the contract between the owner and the main contractor
C) a contract between the main contractor and a supplier
D) none of the above
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/7
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Selected Contract Issues
1
A statement by an architect to a contractor may be sufficient to establish that the architect is the owner's agent.
False
2
A sub-subcontractor would be covered by a one-tier labour and material payment bond.
False
3
What type of agency relationship may be established by representations the owner makes in the construction contract documents? Who is that agency relationship between?
Apparent agency. Representations in the contract between the owner and the contractor may imply that an architect is the agent of the owner. To the extent the owner states in the contract documents that the architect may act for the owner, the owner will be accountable if the contractor relies on the architect.
4
What name is given to an agreement in which one party agrees to bear the financial loss of another party for a specified event?
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
5
Under a pay-when-paid clause, if the owner never pays the main contractor, when must the main contractor pay the subcontractors?

A) on the date the owner was due to pay the main contractor
B) a reasonable time after the payment was due
C) when the subcontractor has completed work under the subcontract
D) if the owner never pays, the main contractor is not required to pay the subcontractor
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following is true for pay-if-paid clauses between contractors and subcontractors where the contractor is unpaid by the owner?

A) in the absence of default by a subcontractor, they create the only possible excuse for a contractor who has not paid a subcontractor
B) they are never enforced by the courts
C) the triggering event for a pay-if-paid clause is a breach of contract between the contractor and the subcontractor
D) none of the above
Unlock Deck
Unlock for access to all 7 flashcards in this deck.
Unlock Deck
k this deck
7
Terms from which contract are typically incorporated by reference into subcontracts?

A) a similar subcontract between the main contractor and another subcontractor
B) the contract between the owner and the main contractor
C) a contract between the main contractor and a supplier
D) none of the above