Deck 6: Getting to a Contract

Full screen (f)
exit full mode
Question
A request for quotation may be used as a preliminary step when negotiation is anticipated.
Use Space or
up arrow
down arrow
to flip the card.
Question
Standing offers are typically open for a short period.
Question
What consequences result from tender documents that place risks on parties not well positioned to deal with those risks?
Question
If an owner wants to negotiate with bidders after bids have been submitted, what steps should be taken?
Question
In which of the following project delivery models is the contractor most involved throughout the entire life of the project?

A) design-bid-build
B) design-build
C) design-build-operate-finance
D) construction management
Question
An owner urgently wants to select a contractor. However, the project details have not been finalized. Therefore, the owner wants to have a few contractors give rough price estimates, and then enter into negotiations with one or more of them. What type of delivery system is most appropriate for this situation?

A) request for qualifications
B) invitation to tender
C) request for quotation
D) request for standing offer
Question
A large private developer anticipates a complicated multi-stage residential development to be implemented over a six-year period. It is important that a good working relationship exist between the owner and the contractor because the owner wishes to have a single contractor for all stages. What type of delivery system is most appropriate for this situation?

A) request for qualifications
B) invitation to tender
C) request for quotation
D) request for standing offer
Question
Which of the following is good practice for an owner awarding a contract?

A) seeking clarity from a bidder regarding an ambiguity in a bid before awarding the contract
B) awarding the contract based on criteria not stated in the invitation for tenders
C) accepting a bid that does not comply with all the mandatory criteria stated in the invitation for tenders
D) refusing to negotiate with any bidders
Question
Which of the following models for project delivery would be inappropriate for a single residence project?

A) design-bid-build
B) design-build
C) design-build-operate
D) construction management
Question
If a call for tenders specifically requires that certain work be subcontracted out, and that the names of subcontractors that the contractor intends to use be given in the tender, why might a contractor intentionally omit the name of the subcontractor? What are the risks of doing this?
Question
An owner wants to implement a project which requires synergy between many different mechanical systems. How suitable is the construction management model of project implementation for this situation?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/11
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Getting to a Contract
1
A request for quotation may be used as a preliminary step when negotiation is anticipated.
True
2
Standing offers are typically open for a short period.
False
3
What consequences result from tender documents that place risks on parties not well positioned to deal with those risks?
The prices submitted by tenderers will be disproportionately high compared to the risk they are required to bear. Potential bidders will be discouraged from submitting bids.
4
If an owner wants to negotiate with bidders after bids have been submitted, what steps should be taken?
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
5
In which of the following project delivery models is the contractor most involved throughout the entire life of the project?

A) design-bid-build
B) design-build
C) design-build-operate-finance
D) construction management
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
6
An owner urgently wants to select a contractor. However, the project details have not been finalized. Therefore, the owner wants to have a few contractors give rough price estimates, and then enter into negotiations with one or more of them. What type of delivery system is most appropriate for this situation?

A) request for qualifications
B) invitation to tender
C) request for quotation
D) request for standing offer
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
7
A large private developer anticipates a complicated multi-stage residential development to be implemented over a six-year period. It is important that a good working relationship exist between the owner and the contractor because the owner wishes to have a single contractor for all stages. What type of delivery system is most appropriate for this situation?

A) request for qualifications
B) invitation to tender
C) request for quotation
D) request for standing offer
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
8
Which of the following is good practice for an owner awarding a contract?

A) seeking clarity from a bidder regarding an ambiguity in a bid before awarding the contract
B) awarding the contract based on criteria not stated in the invitation for tenders
C) accepting a bid that does not comply with all the mandatory criteria stated in the invitation for tenders
D) refusing to negotiate with any bidders
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following models for project delivery would be inappropriate for a single residence project?

A) design-bid-build
B) design-build
C) design-build-operate
D) construction management
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
10
If a call for tenders specifically requires that certain work be subcontracted out, and that the names of subcontractors that the contractor intends to use be given in the tender, why might a contractor intentionally omit the name of the subcontractor? What are the risks of doing this?
Unlock Deck
Unlock for access to all 11 flashcards in this deck.
Unlock Deck
k this deck
11
An owner wants to implement a project which requires synergy between many different mechanical systems. How suitable is the construction management model of project implementation for this situation?
Unlock Deck
Unlock for access to all 11 flashcards in this deck.