Deck 6: Managing Process Improvement Projects

Full screen (f)
exit full mode
Question
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
Use Space or
up arrow
down arrow
to flip the card.
Question
All of the following are important outputs of project scheduling,EXCEPT:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
Question
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
Question
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building MP3 players for massive distribution
D)Running political or advertising campaigns,war or fire-fighting operations
Question
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Work breakdown structure
C)Float
D)Earned value
Question
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
Question
The project life cycle typically has a stretched-s or an exponential form.
Question
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
Question
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Both A and B
Question
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
Question
An event is a series of connected activities from the start to the finish of the project.
Question
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
Question
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
Question
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
Question
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Student syndrome
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
Question
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
Question
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
Question
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
Question
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
Question
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
Question
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
Question
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
Question
The optimistic time is the amount of time the project will take under the worst-case scenario.
Question
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
Question
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
Question
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Question
Favorable variances do not require corrective action or further investigation; only unfavorable variances in performance.
Question
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
Question
Both PERT and CPM are based on variations of the __________ chart?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/29
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Managing Process Improvement Projects
1
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
True
2
All of the following are important outputs of project scheduling,EXCEPT:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
C
3
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
B
4
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building MP3 players for massive distribution
D)Running political or advertising campaigns,war or fire-fighting operations
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
5
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Work breakdown structure
C)Float
D)Earned value
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
6
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
7
The project life cycle typically has a stretched-s or an exponential form.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
8
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
9
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Both A and B
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
10
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
11
An event is a series of connected activities from the start to the finish of the project.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
12
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
13
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
14
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
15
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Student syndrome
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
16
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
17
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
18
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
19
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
20
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
21
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
22
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
23
The optimistic time is the amount of time the project will take under the worst-case scenario.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
24
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
25
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
26
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
27
Favorable variances do not require corrective action or further investigation; only unfavorable variances in performance.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
28
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
29
Both PERT and CPM are based on variations of the __________ chart?
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 29 flashcards in this deck.