Deck 2: Executing Strategy: Project Management

Full screen (f)
exit full mode
Question
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
Use Space or
up arrow
down arrow
to flip the card.
Question
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)Construction Projects
Question
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Slack
C)Float
D)Earned value
E)Work breakdown structure
Question
All of the following are important outputs of project scheduling,except:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
Question
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
E)None of the above
Question
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
E)Slack activities
Question
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Senioritis
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
E)Student syndrome
Question
An event is a series of connected activities from the start to the finish of the project.
Question
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building a long tunnel
D)Running political or advertising campaigns,war or fire-fighting operations
E)Building MP3 players for massive distribution
Question
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
Question
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
E)Slack time
Question
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
E)All of the above are incorrect
Question
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
E)Project slack
Question
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
E)Gantt chart
Question
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
E)Troublesome path
Question
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)None of the above
Question
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
Question
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
Question
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Give
E)Both A and B
Question
The project life cycle typically has a stretched-s or an exponential form.
Question
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
Question
How are projects not like other typical or routine processes?
Question
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
Question
What three outcomes must a project manager determine when scheduling a project with uncertain activity times and the significance of each?
Question
How does benchmarking improve operations? And give a relevant example.
Question
Give an example of Activity Time Variability with Path Interdependencies.
Question
Give an example of Resource Dependence.
Question
The optimistic time is the amount of time the project will take under the worst-case scenario.
Question
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
Question
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Question
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
Question
Why might it be useful to simulate project completion times?
Question
What is the product life cycle (PLC)?
Question
Both PERT and CPM are based on variations of the __________ chart?
Question
Briefly describe the importance of a Project charter.
Question
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
Question
Why is being able to predict activity times crucial in order to meet the demands of your customer?
Question
Why is a project portfolio a better approach to a project than the ROI approach?
Question
Give an example of Inflated Activity Time Estimates.
Question
Favorable variances do not require corrective action or further investigation;only unfavorable variances in performance.
Question
Describe the two types of project organizational structure were discussed and the advantages of both.
Question
Describe the four qualities are sought after in a project manager.
Question
Give an example of a derivative project and explain why your reasoning.
Question
Give an example of a project with the exponential life cycle and describe why this is a good example.
Question
Provide an example of how a project manager can use slack time.
Question
Compare and contrast PERT and CPM.
Question
Explain the importance of slack time and how it can impact the critical path.
Question
Many projects require different emphases during their life cycle.For example,technical performance may be crucial at the beginning,cost overruns in the middle,and on-time completion at the end.Given the project of running a political campaign,what would be there top three emphases starting from the beginning to end?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/48
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 2: Executing Strategy: Project Management
1
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
True
2
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)Construction Projects
Breakthrough projects
3
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Slack
C)Float
D)Earned value
E)Work breakdown structure
Work breakdown structure
4
All of the following are important outputs of project scheduling,except:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
5
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
E)None of the above
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
6
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
E)Slack activities
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
7
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Senioritis
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
E)Student syndrome
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
8
An event is a series of connected activities from the start to the finish of the project.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building a long tunnel
D)Running political or advertising campaigns,war or fire-fighting operations
E)Building MP3 players for massive distribution
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
10
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
11
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
E)Slack time
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
E)All of the above are incorrect
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
13
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
E)Project slack
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
14
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
E)Gantt chart
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
15
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
E)Troublesome path
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
16
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)None of the above
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
17
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
18
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
19
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Give
E)Both A and B
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
20
The project life cycle typically has a stretched-s or an exponential form.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
21
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
22
How are projects not like other typical or routine processes?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
23
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
24
What three outcomes must a project manager determine when scheduling a project with uncertain activity times and the significance of each?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
25
How does benchmarking improve operations? And give a relevant example.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
26
Give an example of Activity Time Variability with Path Interdependencies.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
27
Give an example of Resource Dependence.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
28
The optimistic time is the amount of time the project will take under the worst-case scenario.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
29
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
30
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
31
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
32
Why might it be useful to simulate project completion times?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
33
What is the product life cycle (PLC)?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
34
Both PERT and CPM are based on variations of the __________ chart?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
35
Briefly describe the importance of a Project charter.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
36
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
37
Why is being able to predict activity times crucial in order to meet the demands of your customer?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
38
Why is a project portfolio a better approach to a project than the ROI approach?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
39
Give an example of Inflated Activity Time Estimates.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
40
Favorable variances do not require corrective action or further investigation;only unfavorable variances in performance.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
41
Describe the two types of project organizational structure were discussed and the advantages of both.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
42
Describe the four qualities are sought after in a project manager.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
43
Give an example of a derivative project and explain why your reasoning.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
44
Give an example of a project with the exponential life cycle and describe why this is a good example.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
45
Provide an example of how a project manager can use slack time.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
46
Compare and contrast PERT and CPM.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
47
Explain the importance of slack time and how it can impact the critical path.
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
48
Many projects require different emphases during their life cycle.For example,technical performance may be crucial at the beginning,cost overruns in the middle,and on-time completion at the end.Given the project of running a political campaign,what would be there top three emphases starting from the beginning to end?
Unlock Deck
Unlock for access to all 48 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 48 flashcards in this deck.