Deck 5: Contract Management for Complex Projects
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/60
Play
Full screen (f)
Deck 5: Contract Management for Complex Projects
1
Behaviour oriented contracts specify which of the following?
A) How the contractor should deliver the work.
B) Why the contractor should deliver the work.
C) Where the contractor should deliver the work.
D) When the contractor should deliver the work.
A) How the contractor should deliver the work.
B) Why the contractor should deliver the work.
C) Where the contractor should deliver the work.
D) When the contractor should deliver the work.
A
2
Complex construction projects require which of the following?
A) Management.
B) Professional contract management.
C) Suppliers.
D) Materials.
A) Management.
B) Professional contract management.
C) Suppliers.
D) Materials.
B
3
Which of the following best explains 'conflict of interest'?
A) Buyer wants to pay as little as possible and seller charge as much as possible.
B) Buyer wants to pay as much as possible and the seller charge as little as possible.
C) Buyer wants the same things as the seller.
D) Seller wants the same things as the buyer.
A) Buyer wants to pay as little as possible and seller charge as much as possible.
B) Buyer wants to pay as much as possible and the seller charge as little as possible.
C) Buyer wants the same things as the seller.
D) Seller wants the same things as the buyer.
A
4
Which of the following best explains 'conflict system'?
A) Contractual relationship where parties pursue different objectives.
B) Contractual relationship where parties pursue the same objectives.
C) Contractual relationship where parties dispute the contract details.
D) Contractual relationship where one party fails to meet their contractual requirements.
A) Contractual relationship where parties pursue different objectives.
B) Contractual relationship where parties pursue the same objectives.
C) Contractual relationship where parties dispute the contract details.
D) Contractual relationship where one party fails to meet their contractual requirements.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
5
Which of the following best explains 'co-operative system'?
A) Contractual relationship where parties pursue different objectives.
B) Contractual relationship where parties act rationally in the name of a common objective.
C) Contractual relationship where parties dispute the contract details.
D) Contractual relationship where one party fails to meet their contractual requirements.
A) Contractual relationship where parties pursue different objectives.
B) Contractual relationship where parties act rationally in the name of a common objective.
C) Contractual relationship where parties dispute the contract details.
D) Contractual relationship where one party fails to meet their contractual requirements.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following is a stage of contract management?
A) Concept.
B) Independent evaluation.
C) Post-contractual.
D) Research.
A) Concept.
B) Independent evaluation.
C) Post-contractual.
D) Research.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
7
Which of the following is an example of a large infrastructure project?
A) Highways.
B) An office redecoration.
C) A roof repair.
D) Re-surfacing the car park.
A) Highways.
B) An office redecoration.
C) A roof repair.
D) Re-surfacing the car park.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
8
Which of the following is an example of a large infrastructure project?
A) Refurbishing the toilets.
B) Bridge construction.
C) A roof repair.
D) Re-surfacing the car park.
A) Refurbishing the toilets.
B) Bridge construction.
C) A roof repair.
D) Re-surfacing the car park.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
9
Which of the following best explains 'contracting'?
A) Engaging in contractual relationships with one or more parties.
B) Asking for the services of another organisation.
C) Decreasing the size of the organization.
D) Doing everything yourself.
A) Engaging in contractual relationships with one or more parties.
B) Asking for the services of another organisation.
C) Decreasing the size of the organization.
D) Doing everything yourself.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
10
Which of the following is an example of a large infrastructure project?
A) A roof repair.
B) An office redecoration.
C) Building a port.
D) Re-surfacing the car park.
A) A roof repair.
B) An office redecoration.
C) Building a port.
D) Re-surfacing the car park.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following is a stage of contract management?
A) Research.
B) Contract negotiations.
C) Concept.
D) Independent evaluation.
A) Research.
B) Contract negotiations.
C) Concept.
D) Independent evaluation.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following best explains 'agent opportunism'?
A) Where the agent is flexible in terms of contract pricing.
B) Where the agent is flexible in relation to delivery dates.
C) Where the agent will act primarily out of self-interest.
D) Where the agent is fully compliant with the contractual requirements.
A) Where the agent is flexible in terms of contract pricing.
B) Where the agent is flexible in relation to delivery dates.
C) Where the agent will act primarily out of self-interest.
D) Where the agent is fully compliant with the contractual requirements.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
13
Which of the following best explains 'contract management'?
A) Engaging in contractual relationships with one or more parties.
B) Asking for the services of another organisation.
C) Decreasing the size of the organization.
D) The process that ensures all parties to a contract fully meet their obligations.
A) Engaging in contractual relationships with one or more parties.
B) Asking for the services of another organisation.
C) Decreasing the size of the organization.
D) The process that ensures all parties to a contract fully meet their obligations.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
14
Which of the following best describes the concept of bounded rationality in the context of contracts?
A) Complete information available to decision takers.
B) All options appraised.
C) Objectivity.
D) Different contractual perspectives due to incomplete information and self-interest.
A) Complete information available to decision takers.
B) All options appraised.
C) Objectivity.
D) Different contractual perspectives due to incomplete information and self-interest.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
15
Which of the following best explains 'moral hazard'?
A) Risks not subject to systematic assessment.
B) Risks that both contractual parties will primarily pursue their own interest.
C) Risk that one party will pursue their own interest.
D) Risk of a breach of legislation.
A) Risks not subject to systematic assessment.
B) Risks that both contractual parties will primarily pursue their own interest.
C) Risk that one party will pursue their own interest.
D) Risk of a breach of legislation.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
16
Which of the following is not a requirement of complex construction projects?
A) Professional contract management.
B) Multiple decision-takers.
C) Professional procurement.
D) Professional project management.
A) Professional contract management.
B) Multiple decision-takers.
C) Professional procurement.
D) Professional project management.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
17
Complex construction projects require which of the following?
A) Suppliers.
B) Budgets.
C) Professional procurement.
D) Materials.
A) Suppliers.
B) Budgets.
C) Professional procurement.
D) Materials.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
18
Complex construction projects require which of the following?
A) Professional project management.
B) Budgets.
C) Suppliers.
D) Materials.
A) Professional project management.
B) Budgets.
C) Suppliers.
D) Materials.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
19
Which of the following is a stage of contract management?
A) Independent evaluation.
B) Political approval.
C) Deciding to decide.
D) Pre-contractual.
A) Independent evaluation.
B) Political approval.
C) Deciding to decide.
D) Pre-contractual.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
20
Which of the following best explains 'outcome-oriented contract'?
A) How the contractor should deliver the work.
B) Specification of desired outcomes of contractor work.
C) Where the contractor should deliver the work.
D) Specification of required inputs.
A) How the contractor should deliver the work.
B) Specification of desired outcomes of contractor work.
C) Where the contractor should deliver the work.
D) Specification of required inputs.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
21
Which of the following best explains 'reimbursable time and materials contracts'?
A) Contractor receives a fixed sum per annum.
B) Contractor receives a fixed sum per month.
C) Contractor receives a variable sum based on work completed.
D) Contractor receives a fixed sum per unit of work completed.
A) Contractor receives a fixed sum per annum.
B) Contractor receives a fixed sum per month.
C) Contractor receives a variable sum based on work completed.
D) Contractor receives a fixed sum per unit of work completed.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
22
Which of the following best explains 'network perspective'?
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain network.
C) Contracts are closed recognizing value network interdependencies.
D) Contracts are based on interests of seller only.
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain network.
C) Contracts are closed recognizing value network interdependencies.
D) Contracts are based on interests of seller only.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
23
Which of the following best explains 'design and construct contract'?
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
24
Which of the following best explains 'value chain perspective'?
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain.
C) Contracts are closed based upon the client's key interests and requirements.
D) Contracts are based on interests of seller only.
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain.
C) Contracts are closed based upon the client's key interests and requirements.
D) Contracts are based on interests of seller only.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
25
Which of the following best explains 'liquidated damages'?
A) Written guarantee from a third-party guarantor.
B) The contractor guarantees the actual output or outcome of the work to be delivered.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Sum that will be paid in case the contractor fails to deliver works according to the client's specifications.
A) Written guarantee from a third-party guarantor.
B) The contractor guarantees the actual output or outcome of the work to be delivered.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Sum that will be paid in case the contractor fails to deliver works according to the client's specifications.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
26
Which of the following best explains 'basic design and engineering'?
A) Activities needed to formulate a concept.
B) Activities needed to develop technical specification of the work.
C) Activities need to evaluate a project.
D) Activities need to implement a technical specification.
A) Activities needed to formulate a concept.
B) Activities needed to develop technical specification of the work.
C) Activities need to evaluate a project.
D) Activities need to implement a technical specification.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
27
Which of the following best explains 'design-build-finance-maintain (DBFM) contract'?
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
28
Which of the following best explains 'milestone payments'?
A) Payments for wages and salaries of key managers and workers.
B) Payments made based on deliveries made for each project planning stage.
C) Monthly payments
D) Weekly payments.
A) Payments for wages and salaries of key managers and workers.
B) Payments made based on deliveries made for each project planning stage.
C) Monthly payments
D) Weekly payments.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
29
Which of the following best explains 'tendering'?
A) Activities needed to select contractor for the work based on competitive bids.
B) Activities needed to develop technical specification of the work.
C) Activities needed to select contractor.
D) Activities need to implement a technical specification.
A) Activities needed to select contractor for the work based on competitive bids.
B) Activities needed to develop technical specification of the work.
C) Activities needed to select contractor.
D) Activities need to implement a technical specification.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
30
Which of the following best explains 'construction-only contract'?
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
31
Which of the following best explains 'dyadic perspective'?
A) Contracts are closed based on interests of seller only.
B) Contracts are open to any seller.
C) Contracts are closed based upon interests of buyer and seller only.
D) Contracts are based on interests of buyer only.
A) Contracts are closed based on interests of seller only.
B) Contracts are open to any seller.
C) Contracts are closed based upon interests of buyer and seller only.
D) Contracts are based on interests of buyer only.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
32
Which of the following best explains 'contract for design-procure-construct (EPC)'?
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
A) Contractor designs and provides in accordance with the client's requirements, plant and/or other works.
B) Contractor constructs the project in accordance with the design provided by the client.
C) Contractor delivers project or work turnkey.
D) Contractor completes work at own risk and gets paid long-term payments after delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
33
Which of the following is an element of cost-reimbursable contracts?
A) Wages and salaries of key managers and workers.
B) Contractor losses incurred.
C) Costs of contractor future investments.
D) Costs of unsuccessful bidders.
A) Wages and salaries of key managers and workers.
B) Contractor losses incurred.
C) Costs of contractor future investments.
D) Costs of unsuccessful bidders.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
34
Which of the following best explains 'concern guarantee'?
A) Guarantee issue by supplier.
B) Guarantee issued by the bank of the supplier.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
A) Guarantee issue by supplier.
B) Guarantee issued by the bank of the supplier.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following best explains 'supply chain perspective'?
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain.
C) Contracts are closed based upon interests of buyer.
D) Contracts are based on interests of seller only.
A) Contracts are closed based on recognizing interests of key supply chain partners.
B) Contracts are open to any seller in the supply chain.
C) Contracts are closed based upon interests of buyer.
D) Contracts are based on interests of seller only.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following best explains 'bank guarantee'?
A) Guarantee issue by supplier.
B) Guarantee issued by the bank of the supplier.
C) Guarantee issued by the purchaser.
D) Guarantee issued by the bank of the purchaser.
A) Guarantee issue by supplier.
B) Guarantee issued by the bank of the supplier.
C) Guarantee issued by the purchaser.
D) Guarantee issued by the bank of the purchaser.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
37
Which of the following best explains 'performance bond'?
A) Written guarantee from a third-party guarantor.
B) Guarantee issued by the bank of the supplier.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
A) Written guarantee from a third-party guarantor.
B) Guarantee issued by the bank of the supplier.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
38
Which of the following best explains 'fixed price contract'?
A) Contractor is allowed to fix the price of the contract.
B) Contractor has the price fixed by a third party.
C) Contractor can vary the price during the contract.
D) Contractor agrees to work based on a fixed contract.
A) Contractor is allowed to fix the price of the contract.
B) Contractor has the price fixed by a third party.
C) Contractor can vary the price during the contract.
D) Contractor agrees to work based on a fixed contract.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
39
Which of the following best explains 'performance guarantee'?
A) Written guarantee from a third-party guarantor.
B) The contractor guarantees the actual output or outcome of the work to be delivered.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
A) Written guarantee from a third-party guarantor.
B) The contractor guarantees the actual output or outcome of the work to be delivered.
C) Holding company secures payment for agreed sum in case business unit fails to make payments.
D) Business unit guarantees to pay holding company.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
40
Which of the following best explains 'unit rate/charter contracts'?
A) Contractor agrees to work based upon compensation of all actual costs incurred plus profit margin.
B) Contractor agrees to work based upon compensation of all actual cost.
C) Contractor agrees to work based on projected costs only.
D) Contractor agree to work based on outcome of further negotiations.
A) Contractor agrees to work based upon compensation of all actual costs incurred plus profit margin.
B) Contractor agrees to work based upon compensation of all actual cost.
C) Contractor agrees to work based on projected costs only.
D) Contractor agree to work based on outcome of further negotiations.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
41
Which of the following is a cause of 'agency problem'?
A) Conflict of interest between buyer and seller due to conflicting goals.
B) Sub-contractors fail to meet project milestones.
C) Detailed project engineering and planning problems.
D) Sub-contractors failure to perform due to poor quality performance.
A) Conflict of interest between buyer and seller due to conflicting goals.
B) Sub-contractors fail to meet project milestones.
C) Detailed project engineering and planning problems.
D) Sub-contractors failure to perform due to poor quality performance.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
42
In the key elements of the contracting process which element comes before subcontracting and procurement and after contract negotiation and closure?
A) Basic design and engineering.
B) Claims.
C) Detailed project engineering and planning.
D) Testing and delivery.
A) Basic design and engineering.
B) Claims.
C) Detailed project engineering and planning.
D) Testing and delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
43
In the key elements of the contracting process which element comes before claims and after testing and delivery?
A) Maintenance and guarantee.
B) Project execution.
C) Detailed project engineering and planning.
D) Claims.
A) Maintenance and guarantee.
B) Project execution.
C) Detailed project engineering and planning.
D) Claims.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
44
Which of the following is a cause of 'agency problem'?
A) Sub-contractors failure to perform due to poor quality performance.
B) Conflict of interest between buyer and seller due to information asymmetry.
C) Detailed project engineering and planning problems.
D) Sub-contractors failure to perform due to poor quality performance.
A) Sub-contractors failure to perform due to poor quality performance.
B) Conflict of interest between buyer and seller due to information asymmetry.
C) Detailed project engineering and planning problems.
D) Sub-contractors failure to perform due to poor quality performance.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
45
Which of the following should be incorporated into the general information on supplier selection?
A) Number of employees of suppliers.
B) Turnover of suppliers.
C) Contract value.
D) How bids are evaluated.
A) Number of employees of suppliers.
B) Turnover of suppliers.
C) Contract value.
D) How bids are evaluated.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
46
Which of the following best explains a 'handing invoices procedure'?
A) A procedure incorporating a two-way matching principle (order matches delivery document and delivery document matches with invoice).
B) A procedure incorporating a three-way matching principle (order matches delivery document, delivery document matches with invoice, invoice matches the order).
C) A procedure incorporating a two-way matching principle (delivery document matches with invoice and invoice matches the order).
D) A procedure incorporating a four-way matching principle (order matches delivery document, delivery document matches with invoice, invoice matches the order, invoice is paid).
A) A procedure incorporating a two-way matching principle (order matches delivery document and delivery document matches with invoice).
B) A procedure incorporating a three-way matching principle (order matches delivery document, delivery document matches with invoice, invoice matches the order).
C) A procedure incorporating a two-way matching principle (delivery document matches with invoice and invoice matches the order).
D) A procedure incorporating a four-way matching principle (order matches delivery document, delivery document matches with invoice, invoice matches the order, invoice is paid).
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
47
Which of the following is a cause of 'agency problem'?
A) Sub-contractors failure to meet milestone deadlines.
B) Conflict of interest between buyer and seller due to moral hazard.
C) Conflict of interest between buyer and seller due to engineering and planning problems.
D) Conflict of interest between buyer and seller due to poor quality performance.
A) Sub-contractors failure to meet milestone deadlines.
B) Conflict of interest between buyer and seller due to moral hazard.
C) Conflict of interest between buyer and seller due to engineering and planning problems.
D) Conflict of interest between buyer and seller due to poor quality performance.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
48
In the key elements of the contracting process which element comes before detailed project engineering and planning and after sending out the invitation to tender?
A) Basic design and engineering.
B) Contract negotiation and closure.
C) Claims.
D) Testing and delivery.
A) Basic design and engineering.
B) Contract negotiation and closure.
C) Claims.
D) Testing and delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following is a dimension of contract management?
A) Information flow.
B) Tendering.
C) Contracting
D) Evaluating.
A) Information flow.
B) Tendering.
C) Contracting
D) Evaluating.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
50
In the key elements of the contracting process which element comes before testing and delivery and after subcontracting and procurement?
A) Basic design and engineering.
B) Project execution.
C) Detailed project engineering and planning.
D) Claims.
A) Basic design and engineering.
B) Project execution.
C) Detailed project engineering and planning.
D) Claims.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
51
In the key elements of the contracting process which element comes before project execution and after detailed project engineering and planning?
A) Basic design and engineering.
B) Claims.
C) Sending out the invitation to tender.
D) Subcontracting and procurement.
A) Basic design and engineering.
B) Claims.
C) Sending out the invitation to tender.
D) Subcontracting and procurement.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
52
Which of the following is a dimension of contract management?
A) Tendering.
B) Financial flow
C) Contracting
D) Evaluating.
A) Tendering.
B) Financial flow
C) Contracting
D) Evaluating.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
53
Which of the following is a dimension of contract management?
A) Tendering.
B) Contracting.
C) Goods flow.
D) Evaluating.
A) Tendering.
B) Contracting.
C) Goods flow.
D) Evaluating.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
54
Which of the following is a cause of 'agency problem'?
A) Sub-contractors failure to meet milestone deadlines.
B) Conflict of interest between buyer and seller due to engineering and planning problems.
C) Conflict of interest between buyer and seller due to risk allocation.
D) Conflict of interest between buyer and seller due to poor quality performance.
A) Sub-contractors failure to meet milestone deadlines.
B) Conflict of interest between buyer and seller due to engineering and planning problems.
C) Conflict of interest between buyer and seller due to risk allocation.
D) Conflict of interest between buyer and seller due to poor quality performance.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
55
In the key elements of the contracting process which element comes before contract negotiation and closure and after basic design and engineering?
A) Sending out the invitation to tender.
B) Project execution.
C) Claims.
D) Testing and delivery.
A) Sending out the invitation to tender.
B) Project execution.
C) Claims.
D) Testing and delivery.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
56
Which of the following best explains an 'order-to-pay' system?
A) A system allowing project support staff to order materials and services using the company's corporate purchasing agreements.
B) A system allowing orders to be placed with any supplier.
C) A cash ordering system.
D) A system where project support staff pay for their own orders then claim the expenditure back from their employers.
A) A system allowing project support staff to order materials and services using the company's corporate purchasing agreements.
B) A system allowing orders to be placed with any supplier.
C) A cash ordering system.
D) A system where project support staff pay for their own orders then claim the expenditure back from their employers.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
57
Which of the following best explains 'back-to-back agreements'?
A) Key subcontractor contracts reflect all conditions of the main contract.
B) Key subcontractor secures rolling contract from purchaser.
C) Key subcontractor is awarded two contracts to run consecutively.
D) Key subcontractor is awarded two contracts to run concurrently.
A) Key subcontractor contracts reflect all conditions of the main contract.
B) Key subcontractor secures rolling contract from purchaser.
C) Key subcontractor is awarded two contracts to run consecutively.
D) Key subcontractor is awarded two contracts to run concurrently.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
58
Which of the following best describes the way in which the four dimensions of contract management should be managed?
A) Sequentially.
B) One at a time.
C) In parallel.
D) Two at a time.
A) Sequentially.
B) One at a time.
C) In parallel.
D) Two at a time.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
59
Which of the following is the prevailing co-ordination mechanism for settling contractual disputes and conflicts?
A) Negotiation.
B) Arbitration.
C) Mediation
D) A court case.
A) Negotiation.
B) Arbitration.
C) Mediation
D) A court case.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck
60
Which of the following is a dimension of contract management?
A) Tendering.
B) Contracting.
C) Evaluating.
D) Relationship.
A) Tendering.
B) Contracting.
C) Evaluating.
D) Relationship.
Unlock Deck
Unlock for access to all 60 flashcards in this deck.
Unlock Deck
k this deck