Question
There are three characteristics that all projects share.Which of the following is not one of those characteristics?

A)The project is unique
B)The project is a one-time occurrence
C)The outcome of the project may change over time
D)The project has a finite duration
Use Space or
up arrow
down arrow
to flip the card.
Question
Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between projects.This is an example of project __________.

A)bottleneck
B)breakdown
C)interdependencies
D)malfunctioning
Question
Which of the following is not one of the four dimensions of project success?

A)opening new opportunities for the future
B)number of people working on the project
C)impact on the customer
D)business impact on the organization
Question
The desired outcomes or results of a project are called ____________.

A)subgroups
B)work packages
C)subprojects
D)deliverables
Question
The project to construct a highway is unique because __________.

A)the characteristics of terrain will be different for different segments.
B)consistency of the concrete will vary for different segments.
C)different types of laborers will be used to build various segments of the highway.
D)different people manage different s of the highway.
Question
The overwhelming majority of all projects are of what size?

A)Small
B)Medium
C)Large
D)Very large
Question
The __________ of the project team is a crucial but unstated element of ancillary trade-offs that the project manager must consider.

A)health
B)plan
C)task
D)effort
Question
__________ is a subset of a project consisting of work packages.

A)Task
B)Program
C)Project
D)Process
Question
The desired outcomes or results of a project are called ____________.

A)subgroups
B)work packages
C)subprojects
D)deliverables
Question
The production of weekly employment reports or the delivery of mail could be considered a(n)

A)project
B)non-project
C)quasi-projects
D)triple projects
Question
Identify the example that would not usually be considered a project.

A)building a house
B)developing a computer software application program
C)hosting a wedding reception
D)assembly line manufacturing of automobiles
Question
Projects are bound by the three objectives of scope,time,and cost.These are collectively referred to as the _______________________.

A)Triple Constraint
B)Triple Factors
C)Three Constraints
D)Triple Play
Question
As sub-elements of a task,these __________ need to be accomplished to achieve the objectives of the task.

A)subprojects
B)programs
C)work packages
D)levels of effort
Question
According to the PMBOK Guidebook,a __________ is a temporary endeavor undertaken to create a unique product or service.

A)project
B)task
C)sub-process
D)program
Question
An important implication of the project life cycle concept is that a project will resist __________ of its existence.

A)termination
B)completion
C)extending
D)logging
Question
Which of the following is not a likely attribute of quasi-projects?

A)lack of specificity in the project objective
B)a designated team working on the project
C)undefined performance parameters
D)limited scope and budget
Question
The __________ project is generally credited with beginning the era of modern project management.

A)Manhattan
B)Chicago
C)Great Wall of China
D)Egyptian pyramids
Question
Individuals or groups with a special interest in a project are called __________.

A)stakeholders
B)project managers
C)leaders
D)directors
Question
The authors discuss four dimensions of project success.Which of the following is not one of those four dimensions?

A)Project efficiency
B)Cost to the customer
C)Business impact on the organization
D)Opening new opportunities for the future
Question
According to the authors,the prime objectives of project management are

A)scope,cost,time
B)quality,scope,schedule
C)customer satisfaction,budget,schedule
D)cost,quality,customer satisfaction
Question
The Project Management Institute offers two certifications called the ______________ and the __________________.

A)PMP and CAPM
B)PMP and IBM
C)APM and PMP
D)CAPM and APM
Question
The conventional project life cycle can be described as a pattern characterized by ____________.

A)parabolic progress
B)logarithmic progress
C)slow-rapid-slow progress
D)extremely slow progress
Question
In a conventional project life cycle,as work progresses,uncertainty about the expected outcome should __________.

A)become a constant
B)decrease
C)increase
D)be fully removed
Question
The chance that project processes or outcomes will not turn out as planned is called __________.

A)risk
B)projecting
C)effort
D)negative outcome
Question
The "stretched-S" pattern observed during the project life cycle,for the most part,is a result of the _________.

A)changing levels of resources used during successive stages of the project life cycle
B)changing attitudes of the people who work in the project.
C)difficulty in performing the individual activities of a project.
D)principle that work expands to fill the allotted time
Question
Having only partial or no information about the situation or outcomes is called __________.

A)uncertainty
B)risk
C)effort
D)cluelessness
Question
When done properly,project management begins with __________.

A)stakeholder interviews
B)scope definition
C)the initial concept for the project
D)budget estimation
Question
Conflicting expectations among stakeholders related to performance,cost,and time will require the project manager to make appropriate ____________ in order to balance competing demands related to these objectives.

A)trade-offs
B)guidelines
C)weights
D)tasks
Question
The ___________________ is a project management organization headquartered in the United Kingdom,which started in the early 1970s and serves all of Europe.

A)PMI
B)APM
C)IPMA
D)PRINCE2
Question
Earned value is based on the concept that the percentage of project completion is closely correlated with __________.

A)the number of levels in the project
B)relevance of the project
C)cost or the use of resources
D)final assembly of the output
Question
The process of creating artificial deadlines and budgets to accomplish specific,though routine,tasks within a functional department is called ______.

A)programming
B)routinizing
C)accepting
D)projectizing
Question
The organization that has the responsibility for maintaining and publishing The PMBOK Guidebook is the

A)PMI
B)APM
C)PRINCE2
D)IPMA
Question
The foundational basis for education for project managers is the __________.

A)PMBOK Guidebook
B)Triple Play
C)PMI Guidebook
D)Project Management Rulebook
Question
The largest amount of effort applied to a project is during its __________

A)conception
B)planning,scheduling,monitoring,and control
C)selection
D)evaluation and termination
Question
Who,according to the authors,has played a significant role in the development of techniques for project management?

A)European navigators
B)Trader community
C)Brokerage firms
D)The military
Question
Which of the following is not a trend that we see in project management?

A)Increase in virtual projects
B)Decreasing importance of project managers
C)Importance given to strategic goals
D)Regular accomplishment of routine goals
Question
A ____ is responsible for the evaluation and improvement of an organization's project management skill and experience in managing projects.

A)vice president of project management
B)project management office
C)office of projects
D)project manager
Question
The authors identify three forces that combine to mandate the use of teams to solve problems.Identify the force that the authors did not name.

A)Explosion in the growth of certified project managers
B)Worldwide acceptance of the Project Management Institute
C)Interaction of supply and demand
D)Evolution of worldwide competitive markets for the production and consumption of goods and services
Question
Relations between organizational functions,where one function or task is dependent on others,are known as __________.

A)interdependencies
B)links
C)projects
D)tasks
Question
A project that involves global teams with team members operating in different physical geographic locations and different time zones.

A)International project
B)Program
C)Online project
D)Virtual project
Question
Name four benefits of project management.
Question
The attributes that characterize a project are __________.

A)purpose,repetition,interdependencies,consistency,uncertainty,conflict,and one-time occurrence
B)life cycle,schedule,cost,uncertainty,independence,uniqueness,and purpose
C)resources,uniqueness,conflict,interdependencies,one-time occurrence,and finite duration,
D)purpose,life cycle,conflict,certainty,independence,performance,and finite duration
Question
Briefly describe the three characteristics that are common to all projects.
Question
Describe the project life cycle.
Question
What are some of the benefits of using project management?
Question
Discuss the factors that have contributed to the growth of the Project Management Institute.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/46
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 1: Projects in Contemporary Organizations
1
There are three characteristics that all projects share.Which of the following is not one of those characteristics?

A)The project is unique
B)The project is a one-time occurrence
C)The outcome of the project may change over time
D)The project has a finite duration
C
2
Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between projects.This is an example of project __________.

A)bottleneck
B)breakdown
C)interdependencies
D)malfunctioning
C
3
Which of the following is not one of the four dimensions of project success?

A)opening new opportunities for the future
B)number of people working on the project
C)impact on the customer
D)business impact on the organization
B
4
The desired outcomes or results of a project are called ____________.

A)subgroups
B)work packages
C)subprojects
D)deliverables
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
5
The project to construct a highway is unique because __________.

A)the characteristics of terrain will be different for different segments.
B)consistency of the concrete will vary for different segments.
C)different types of laborers will be used to build various segments of the highway.
D)different people manage different s of the highway.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
6
The overwhelming majority of all projects are of what size?

A)Small
B)Medium
C)Large
D)Very large
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
7
The __________ of the project team is a crucial but unstated element of ancillary trade-offs that the project manager must consider.

A)health
B)plan
C)task
D)effort
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
8
__________ is a subset of a project consisting of work packages.

A)Task
B)Program
C)Project
D)Process
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
9
The desired outcomes or results of a project are called ____________.

A)subgroups
B)work packages
C)subprojects
D)deliverables
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
10
The production of weekly employment reports or the delivery of mail could be considered a(n)

A)project
B)non-project
C)quasi-projects
D)triple projects
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
11
Identify the example that would not usually be considered a project.

A)building a house
B)developing a computer software application program
C)hosting a wedding reception
D)assembly line manufacturing of automobiles
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
12
Projects are bound by the three objectives of scope,time,and cost.These are collectively referred to as the _______________________.

A)Triple Constraint
B)Triple Factors
C)Three Constraints
D)Triple Play
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
13
As sub-elements of a task,these __________ need to be accomplished to achieve the objectives of the task.

A)subprojects
B)programs
C)work packages
D)levels of effort
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
14
According to the PMBOK Guidebook,a __________ is a temporary endeavor undertaken to create a unique product or service.

A)project
B)task
C)sub-process
D)program
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
15
An important implication of the project life cycle concept is that a project will resist __________ of its existence.

A)termination
B)completion
C)extending
D)logging
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
16
Which of the following is not a likely attribute of quasi-projects?

A)lack of specificity in the project objective
B)a designated team working on the project
C)undefined performance parameters
D)limited scope and budget
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
17
The __________ project is generally credited with beginning the era of modern project management.

A)Manhattan
B)Chicago
C)Great Wall of China
D)Egyptian pyramids
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
18
Individuals or groups with a special interest in a project are called __________.

A)stakeholders
B)project managers
C)leaders
D)directors
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
19
The authors discuss four dimensions of project success.Which of the following is not one of those four dimensions?

A)Project efficiency
B)Cost to the customer
C)Business impact on the organization
D)Opening new opportunities for the future
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
20
According to the authors,the prime objectives of project management are

A)scope,cost,time
B)quality,scope,schedule
C)customer satisfaction,budget,schedule
D)cost,quality,customer satisfaction
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
21
The Project Management Institute offers two certifications called the ______________ and the __________________.

A)PMP and CAPM
B)PMP and IBM
C)APM and PMP
D)CAPM and APM
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
22
The conventional project life cycle can be described as a pattern characterized by ____________.

A)parabolic progress
B)logarithmic progress
C)slow-rapid-slow progress
D)extremely slow progress
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
23
In a conventional project life cycle,as work progresses,uncertainty about the expected outcome should __________.

A)become a constant
B)decrease
C)increase
D)be fully removed
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
24
The chance that project processes or outcomes will not turn out as planned is called __________.

A)risk
B)projecting
C)effort
D)negative outcome
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
25
The "stretched-S" pattern observed during the project life cycle,for the most part,is a result of the _________.

A)changing levels of resources used during successive stages of the project life cycle
B)changing attitudes of the people who work in the project.
C)difficulty in performing the individual activities of a project.
D)principle that work expands to fill the allotted time
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
26
Having only partial or no information about the situation or outcomes is called __________.

A)uncertainty
B)risk
C)effort
D)cluelessness
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
27
When done properly,project management begins with __________.

A)stakeholder interviews
B)scope definition
C)the initial concept for the project
D)budget estimation
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
28
Conflicting expectations among stakeholders related to performance,cost,and time will require the project manager to make appropriate ____________ in order to balance competing demands related to these objectives.

A)trade-offs
B)guidelines
C)weights
D)tasks
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
29
The ___________________ is a project management organization headquartered in the United Kingdom,which started in the early 1970s and serves all of Europe.

A)PMI
B)APM
C)IPMA
D)PRINCE2
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
30
Earned value is based on the concept that the percentage of project completion is closely correlated with __________.

A)the number of levels in the project
B)relevance of the project
C)cost or the use of resources
D)final assembly of the output
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
31
The process of creating artificial deadlines and budgets to accomplish specific,though routine,tasks within a functional department is called ______.

A)programming
B)routinizing
C)accepting
D)projectizing
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
32
The organization that has the responsibility for maintaining and publishing The PMBOK Guidebook is the

A)PMI
B)APM
C)PRINCE2
D)IPMA
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
33
The foundational basis for education for project managers is the __________.

A)PMBOK Guidebook
B)Triple Play
C)PMI Guidebook
D)Project Management Rulebook
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
34
The largest amount of effort applied to a project is during its __________

A)conception
B)planning,scheduling,monitoring,and control
C)selection
D)evaluation and termination
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
35
Who,according to the authors,has played a significant role in the development of techniques for project management?

A)European navigators
B)Trader community
C)Brokerage firms
D)The military
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following is not a trend that we see in project management?

A)Increase in virtual projects
B)Decreasing importance of project managers
C)Importance given to strategic goals
D)Regular accomplishment of routine goals
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
37
A ____ is responsible for the evaluation and improvement of an organization's project management skill and experience in managing projects.

A)vice president of project management
B)project management office
C)office of projects
D)project manager
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
38
The authors identify three forces that combine to mandate the use of teams to solve problems.Identify the force that the authors did not name.

A)Explosion in the growth of certified project managers
B)Worldwide acceptance of the Project Management Institute
C)Interaction of supply and demand
D)Evolution of worldwide competitive markets for the production and consumption of goods and services
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
39
Relations between organizational functions,where one function or task is dependent on others,are known as __________.

A)interdependencies
B)links
C)projects
D)tasks
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
40
A project that involves global teams with team members operating in different physical geographic locations and different time zones.

A)International project
B)Program
C)Online project
D)Virtual project
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
41
Name four benefits of project management.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
42
The attributes that characterize a project are __________.

A)purpose,repetition,interdependencies,consistency,uncertainty,conflict,and one-time occurrence
B)life cycle,schedule,cost,uncertainty,independence,uniqueness,and purpose
C)resources,uniqueness,conflict,interdependencies,one-time occurrence,and finite duration,
D)purpose,life cycle,conflict,certainty,independence,performance,and finite duration
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
43
Briefly describe the three characteristics that are common to all projects.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
44
Describe the project life cycle.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
45
What are some of the benefits of using project management?
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
46
Discuss the factors that have contributed to the growth of the Project Management Institute.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 46 flashcards in this deck.