Deck 4: Chartering Projects
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/39
Play
Full screen (f)
Deck 4: Chartering Projects
1
A background statement is a mandatory element of the project charter that sets the stage for creation of the scope overview and business case.
False
2
The scope overview and business case sections of the project charter provide the high-level "what and where" of the project.
False
3
A deliverable is any unique and verifiable product,result or capability to perform a service that is required to be produced to complete a process,phase,or project.
True
4
The signing of the project charter signals the transition from the high-level project initiating stage into the more detailed project planning stage.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
5
One purpose of the project charter is to help the project team and sponsor commit to the project.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
6
Which of the following documents serves as an informal contract between the project team and the project sponsor?
A) team members' employment contracts
B) project charter
C) project roadmap
D) business case
A) team members' employment contracts
B) project charter
C) project roadmap
D) business case
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
7
Assumptions identified in the project charter include events that,if they occur,will have either a positive or a negative effect on a project's objectives
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
8
A charter is used to quickly screen potential projects and to eliminate the poor choices.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
9
A background statement is often added to a project charter to help stakeholders better understand the background behind the scope overview and business case.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
10
The project charter grants the project team the right to:
A) begin project execution
B) develop the project mission statement
C) create a detailed project plan
D) write a detailed business case
A) begin project execution
B) develop the project mission statement
C) create a detailed project plan
D) write a detailed business case
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
11
The signing of the project portfolio statement signals the transition from the high-level project initiating stage into the more detailed project planning stage.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
12
In contrast to the case that exists with a legal contract,the parties to a signed project charter are merely obligated to the spirit of the charter since specific details will certainly change.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
13
A well-written business case should persuade decision-makers to support the project.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
14
Charters used in different industries and in different companies have somewhat different elements and formats.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
15
The project charter serves as a formal legal contract between the project team and the project sponsor.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
16
A key concept in agile projects is that something of value will be delivered at each iteration.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
17
Risks,assumptions and constraints are included in the project charter so that key participants will be aware of what could prevent them from successfully completing the project.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
18
At the time the project charter is prepared there is typically a very general understanding of the project,so if a budget is included it can only be a rough estimate.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
19
The project business case provides a high-level description of what the project will accomplish and how it will be done.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
20
The project master network is a summary-level schedule that identifies the major schedule milestones or significant points and events in the project.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
21
A project sponsor is wise not to sign a project charter authorizing work until the project manager and team show that they have ____:
A) learned to work together well.
B) gathered requirements from key stakeholders.
C) reviewed lessons learned from previous projects in order to avoid similar mistakes.
D) prepared a comprehensive schedule and budget.
A) learned to work together well.
B) gathered requirements from key stakeholders.
C) reviewed lessons learned from previous projects in order to avoid similar mistakes.
D) prepared a comprehensive schedule and budget.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
22
Briefly discuss the importance of the project charter,and compare the roles played by the project sponsor and the project manager with respect to the preparation of this document.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
23
Which of the following charter elements should inspire team members to develop a passion for the project and to work hard on it?
A) the project vision statement
B) the business case
C) the project motto
D) the team operating principles
A) the project vision statement
B) the business case
C) the project motto
D) the team operating principles
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
24
Which section of the project charter publicly acknowledges the commitment of the sponsor,managers and team members to the project?
A) business case
B) signatures and commitment
C) decisions and findings
D) contract section
A) business case
B) signatures and commitment
C) decisions and findings
D) contract section
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
25
Project managers and teams should consider risks and include them in the project charter for all the following reasons EXCEPT:
A) risks that may have a negative impact on project objectives should be identified and addressed.
B) all project risks should be eliminated before the project charter is signed.
C) risks that may have a positive impact on the project create opportunities and should be capitalized upon.
D) the sponsor and core team should be aware of what could prevent them from successfully completing the project.
A) risks that may have a negative impact on project objectives should be identified and addressed.
B) all project risks should be eliminated before the project charter is signed.
C) risks that may have a positive impact on the project create opportunities and should be capitalized upon.
D) the sponsor and core team should be aware of what could prevent them from successfully completing the project.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
26
Which of the following charter elements defines the project purpose and justifies the necessity of the project?
A) scope control plan
B) acceptance criteria
C) business case
D) scope overview
A) scope control plan
B) acceptance criteria
C) business case
D) scope overview
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
27
The project charter serves all of the following purposes EXCEPT:
A) authorizes the project manager to proceed
B) develops a common understanding between the sponsor and the project team
C) quickly screens out obviously poor projects
D) describes skill sets needed for the project
A) authorizes the project manager to proceed
B) develops a common understanding between the sponsor and the project team
C) quickly screens out obviously poor projects
D) describes skill sets needed for the project
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
28
During iteration planning in an agile project,agreement is reached regarding:
A) the length of the next sprint.
B) detailed stakeholder requirements.
C) the definition of done.
D) positive and negative risks.
A) the length of the next sprint.
B) detailed stakeholder requirements.
C) the definition of done.
D) positive and negative risks.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
29
Within the project charter,the scope overview accomplishes all of the following EXCEPT:
A) identifies the major schedule milestones for the project
B) describes the work that must be performed to deliver a product,service or result.
C) distinguishes between what the project will and will not do.
D) describes at a high level what needs to be accomplished and how it will be done.
A) identifies the major schedule milestones for the project
B) describes the work that must be performed to deliver a product,service or result.
C) distinguishes between what the project will and will not do.
D) describes at a high level what needs to be accomplished and how it will be done.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
30
What are risks,and why is it important to identify them in the project charter?
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
31
Project charters typically include all of the following elements EXCEPT:
A) positive and negative risks
B) project assumptions
C) detailed resource requirements
D) project constraints
A) positive and negative risks
B) project assumptions
C) detailed resource requirements
D) project constraints
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
32
In the project charter,what types of resources might be estimated and how detailed should the project budget or resource requirements be? Give some examples of how they might be expressed.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
33
On agile projects the first iteration is planned as a milestone with acceptance criteria.However,subsequent milestones and acceptance criteria are determined on a ___:
A) need-to-know basis
B) first in first out (FIFO)basis
C) just in time (JIT)basis
D) first come first served basis
A) need-to-know basis
B) first in first out (FIFO)basis
C) just in time (JIT)basis
D) first come first served basis
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
34
The addition of acceptance criteria factors to the milestones in a project charter helps the team understand who will judge the quality of the deliverable associated with each milestone,and _____:
A) that stakeholder's role on the team.
B) the risk associated with each milestone.
C) the penalties for not achieving the desired quality.
D) the criteria or standards they will use.
A) that stakeholder's role on the team.
B) the risk associated with each milestone.
C) the penalties for not achieving the desired quality.
D) the criteria or standards they will use.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following statements most accurately identifies the typical contents of the project charter?
A) requirements,specifications,test protocols and test results
B) statement of work,terms and conditions,clauses and delivery instructions
C) business case,milestone schedule,resource estimates and team operating principles
D) purpose,literature review,methodology,results and conclusions
A) requirements,specifications,test protocols and test results
B) statement of work,terms and conditions,clauses and delivery instructions
C) business case,milestone schedule,resource estimates and team operating principles
D) purpose,literature review,methodology,results and conclusions
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following statements accurately describes the responsibilities typically associated with the development of the project charter?
A) the project sponsor typically prepares the detailed first draft of the charter
B) the project manager typically prepares the business case and scope overview
C) the customer typically prepares and signs the charter
D) the project manager and team typically prepare the majority of the rough draft for the project charter
A) the project sponsor typically prepares the detailed first draft of the charter
B) the project manager typically prepares the business case and scope overview
C) the customer typically prepares and signs the charter
D) the project manager and team typically prepare the majority of the rough draft for the project charter
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
37
The project charter should help the project team and the project sponsor to develop a common understanding of what the project is all about.All of the following items are elements of that common understanding EXCEPT:
A) understanding how the project aligns with the goals of the organization
B) understanding the detailed project schedule
C) understanding project success measures
D) understanding what is included and excluded
A) understanding how the project aligns with the goals of the organization
B) understanding the detailed project schedule
C) understanding project success measures
D) understanding what is included and excluded
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
38
The milestone schedule in the project charter:
A) is a schedule that provides detailed data for when each project activity should begin.
B) is a detailed schedule that shows the planned duration for every activity in the project.
C) is a summary-level schedule that identifies significant points or events in the project.
D) is a summary-level schedule that shows how major project tasks are sequenced.
A) is a schedule that provides detailed data for when each project activity should begin.
B) is a detailed schedule that shows the planned duration for every activity in the project.
C) is a summary-level schedule that identifies significant points or events in the project.
D) is a summary-level schedule that shows how major project tasks are sequenced.
Unlock Deck
Unlock for access to all 39 flashcards in this deck.
Unlock Deck
k this deck
39
Team operating principles are sometimes included in a project charter to enhance team performance.Which of the following statements accurately describes the value of establishing team operating principles?
A) Operating principles that address the conduct of meetings and how decisions are made are especially useful in helping the team get off to a good start.
B) Operating principles typically detail the specific work that each team member will perform and ensure a more complete understanding of the project.
C) Operating principles identify the rules along with the punishments to be administered when the rules are broken.
D) Operating principles are especially helpful for a routine project where participants have worked together before
A) Operating principles that address the conduct of meetings and how decisions are made are especially useful in helping the team get off to a good start.
B) Operating principles typically detail the specific work that each team member will perform and ensure a more complete understanding of the project.
C) Operating principles identify the rules along with the punishments to be administered when the rules are broken.
D) Operating principles are especially helpful for a routine project where participants have worked together before
Unlock Deck
Unlock for access to all 39 flashcards in this deck.