Deck 14: Operations Scheduling and Sequencing

Full screen (f)
exit full mode
Question
Scheduling problems occur almost exclusively in manufacturing.
Use Space or
up arrow
down arrow
to flip the card.
Question
Scheduling refers to determining the order in which jobs or tasks are processed.
Question
For a single processor, a first-come, first-served (FCFS) rule minimizes the average flow time because customer waiting time will be minimized.
Question
The makespan is the sum of flow times of a given set of jobs.
Question
The EDD rule minimizes the maximum of jobs past due but doesn't perform well on average flow-time, WIP inventory or resource utilization.
Question
In sequencing a set of jobs on a single processor, different sequences will have different makespans but the same average flow times.
Question
The shortest processing time rule and earliest due date rule will always provide the same sequence.
Question
A lateness measure can only be 0 or a positive number.
Question
Telling an umpire crew to work baseball games in Chicago, then Milwaukee, and then Cleveland is an example of a sequence.
Question
The SPT sequencing rule will maximize the average flow time.
Question
Flow time is the amount of time a job spends in a shop or factory.
Question
In practice, whenever processing times of a set of jobs are about equal, managers typically use a first-come, first-serve rule.
Question
A tardiness measure can be either zero (0) or a positive number.
Question
Indirectly, appointments reduce the cost of providing a service because the service provider is idle less each workday.
Question
High flow times reduce WIP inventory.
Question
Sequencing is not as much of a concern when several activities use a common resource.
Question
Tardiness measures the amount of time by which the completion time exceeds the due date.
Question
Since all jobs eventually get done, job sequencing has no effect on resource utilization.
Question
Appointments can be viewed as a reservation of service time and capacity.
Question
Scheduling and sequencing methods used in manufacturing are more beneficial in low-contact, than high-contact, service processes.
Question
Considering a two-resource sequencing problem,

A)The makespan is the same for any sequence of jobs
B)Flow time is minimized
C)The goal is to minimize makespan
D)Each job can be processed by either resource first
Question
The time to rest and travel between games for baseball umpire crews is an important factor in developing their schedule.
Question
The sequencing rule that minimizes the maximum number of jobs that are past due from a given set of jobs is

A)Shortest processing time
B)Earliest due date
C)First come, first served
D)Least work remaining
Question
The Shortest Processing Time (SPT) rule

A)Ensures that due dates are met
B)Maximizes average flow-time
C)Minimizes resource utilization
D)Minimizes work in process inventory
Question
In sequencing jobs in a flow shop with two resources, Johnson's rule finds a sequence that has the smallest makespan.
Question
The numerical difference between the completion time and the due date is called

A)Flow time
B)Lateness
C)Makespan
D)Tardiness
Question
When several products share common facilities, product sequencing affects cost.
Question
Triage by nurses in an emergency room would be an example of

A)Scheduling
B)Sequencing
C)Appointments
D)Shortest-processing-time rule
Question
Which of the following is not a consideration when designing an appointment system?

A)Determining the appointment time interval
B)Determining the appropriate sequencing rule
C)Determining the length of each workday and the time off-duty
D)Deciding on an overbooking policy
Question
Scheduling applies to all aspects of the value chain.
Question
Gantt charts can show what jobs are ahead of schedule, behind schedule, and on schedule.
Question
If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring

A)The shortest processing time
B)The smallest critical ratio
C)The least remaining operations
D)The longest processing time
Question
Staff scheduling needs all of the following except

A)Flow-time estimates
B)Accurate forecasting
C)Staffing levels required by time period
D)Determining available personnel
Question
Two examples of process-focused performance measures for sequencing rules are flow time and lateness.
Question
Rescheduling rarely occurs unless customers change their requested due dates.
Question
Scheduling refers to specifying

A)The sequence that jobs must be completed
B)The due date for each job
C)The start and completion times of jobs
D)The makespan of each job
Question
The time needed to process a given set of jobs is called

A)Flow time
B)Ready time
C)Makespan
D)Due date
Question
Appointments systems often overbook to maximize revenue.
Question
UPS, the world's largest package delivery company, is highly dependent on scheduling but not sequencing.
Question
Like the SPT rule, the earliest due date (EDD) rule minimizes the average flow time.
Question
Explain why any sequence chosen in the single-machine scheduling problem will not change makespan time.
Question
What four (4) decisions are considered in designing an appointment system?
Question
Johnson's sequencing rule is used to sequence

A)several jobs through several work centers
B)several jobs through one work center
C)two jobs through several work centers
D)several jobs through two work centers
Question
Compare and contrast the advantages and disadvantages of the Shortest Processing Time (SPT) and the Earliest Due Date (EDD) sequencing rules.
Question
A movie theater requires the following minimum number of employees, each of which is required to have two consecutive days off. A movie theater requires the following minimum number of employees, each of which is required to have two consecutive days off.   How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.<div style=padding-top: 35px> How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.
Question
Staff scheduling attempts to match available personnel with the needs of the organization by performing what four steps?
Question
The table below includes processing times and due dates for five jobs.
The table below includes processing times and due dates for five jobs.   a.Use the Shortest Processing Time Rule (SPT) to determine the average flow time. b.Use the Earliest Due Date Rule (EDD) to determine the average lateness.<div style=padding-top: 35px>
a.Use the Shortest Processing Time Rule (SPT) to determine the average flow time.
b.Use the Earliest Due Date Rule (EDD) to determine the average lateness.
Question
Short-term capacity fluctuations necessitate changes in schedules.List at least five factors affecting short-term capacity.
Question
Which of the following is NOT a criterion for evaluating job sequencing rules?

A)average flow time
B)lateness
C)tardiness
D)sum of processing times
Question
Which of the following is an example of a situation for which a Gantt chart would be appropriate?

A)developing a factory layout
B)tracking inventory levels over time
C)monitoring job schedules
D)forecasting personnel requirements in a two-shift operation
Question
A requirement of Johnson's two-resource sequencing rule is

A)All jobs must begin at the same time
B)Jobs must be processed through each work center in the same job sequence
C)Only two jobs can be processed at a time through each work center
D)Total processing time must be minimized
Question
The chief disadvantage of the shortest processing time rule is:

A)average job completion times are excessive
B)average number of jobs in the system is excessive
C)long-duration jobs may have excessive completion times
D)average job lateness is excessive
Question
Describe Johnson's sequencing rule for the two-resource sequencing problem.
Question
Differentiate between scheduling and sequencing.
Question
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.They are job shops that handle a variety of outpatient surgical procedures.Their process is set up so that one doctor cuts and the other sews.They have five patients to sequence for tomorrow.Since the weather forecast is for a cool and sunny day, they would also like to play golf tomorrow.They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of that job.The patients and estimated times are as follows:
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.They are job shops that handle a variety of outpatient surgical procedures.Their process is set up so that one doctor cuts and the other sews.They have five patients to sequence for tomorrow.Since the weather forecast is for a cool and sunny day, they would also like to play golf tomorrow.They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of that job.The patients and estimated times are as follows:   Sequence the patients using Johnson's Method, state the schedule for each operation, and determine the minimum makespan.<div style=padding-top: 35px> Sequence the patients using Johnson's Method, state the schedule for each operation, and determine the minimum makespan.
Question
Explain the three categories of criteria used to evaluate job sequencing performance.For each category, provide two example measures.
Question
A restaurant needs the following number of wait staff to serve its evening guests.
A restaurant needs the following number of wait staff to serve its evening guests.   How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.<div style=padding-top: 35px> How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.
Question
Give at least five examples of service organizations (and employee type) where, due to high variability in customer demand, staff scheduling problems are prevalent.
Question
The following five jobs, along with their processing time and due dates, are given below.
The following five jobs, along with their processing time and due dates, are given below.   a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.<div style=padding-top: 35px>
a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs
b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.
Question
ScheduleAnywhere.com on-line software helps clients do all the following except

A)Schedule employees from any computer with Internet access.
B)Decide how much to overbook for each day of the week.
C)See who's scheduled and who's available.
D)Avoid scheduling conflicts.
Question
An airplane repair facility has a contract to repair cargo aircraft for a regional airline.There are 62 planes in the airline company's fleet of planes.Because of the punishing workload, the planes require a considerable amount of maintenance.The repair facility is trying to determine how to schedule the needed repairs.They want to compare the shortest processing time rule and the first-come first-served rule.Currently, the following planes need repair and are in the repair facility (data given is in order of plane arrival, only one plane is worked on at a time and the shop is open 24 hours a day, 7 days a week).
An airplane repair facility has a contract to repair cargo aircraft for a regional airline.There are 62 planes in the airline company's fleet of planes.Because of the punishing workload, the planes require a considerable amount of maintenance.The repair facility is trying to determine how to schedule the needed repairs.They want to compare the shortest processing time rule and the first-come first-served rule.Currently, the following planes need repair and are in the repair facility (data given is in order of plane arrival, only one plane is worked on at a time and the shop is open 24 hours a day, 7 days a week).   a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)? b.What is the average time (in hours) in the shop using the shortest processing time rule? c.What is the average time (in hours) in the shop using the first?come first?served rule?<div style=padding-top: 35px>
a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)?
b.What is the average time (in hours) in the shop using the shortest processing time rule?
c.What is the average time (in hours) in the shop using the first?come first?served rule?
Question
A print shop has five large commercial printing jobs to finish.They are trying to decide whether to use the shortest processing time (SPT) or the first-come first-served (FCFS) sequencing rule.Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):
A print shop has five large commercial printing jobs to finish.They are trying to decide whether to use the shortest processing time (SPT) or the first-come first-served (FCFS) sequencing rule.Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):   a.What is the average flow time in hours using the FCFS rule? b.What is the average job lateness in hours using the FCFS rule? c.What is the average flow time in hours using the SPT rule? d.What is the average job lateness in hours using the SPT rule?<div style=padding-top: 35px>
a.What is the average flow time in hours using the FCFS rule?
b.What is the average job lateness in hours using the FCFS rule?
c.What is the average flow time in hours using the SPT rule?
d.What is the average job lateness in hours using the SPT rule?
Question
A young entrepreneur has just opened an electronics store.One of the many tasks that she must address is work scheduling.She plans to stay open from 9a.m.to 9 p.m.Monday through Saturday.She expects her employees to stock the shelves and also be available for cashier check-out when needed.All employees are full time and work four days in a row with two consecutive days off each week.She estimates the number of employees needed each day as follows:
A young entrepreneur has just opened an electronics store.One of the many tasks that she must address is work scheduling.She plans to stay open from 9a.m.to 9 p.m.Monday through Saturday.She expects her employees to stock the shelves and also be available for cashier check-out when needed.All employees are full time and work four days in a row with two consecutive days off each week.She estimates the number of employees needed each day as follows:   a.Use the days-off scheduling procedure to determine the minimum number of employees required? b.Based on your schedule found in part (a), which days are overstaffed and by how many workers are they overstaffed?<div style=padding-top: 35px>
a.Use the days-off scheduling procedure to determine the minimum number of employees required?
b.Based on your schedule found in part (a), which days are overstaffed and by how many workers are they overstaffed?
Question
At the end of each month, a research and development team writes status reports for the projects worked on during the month.The team leaders, Andrew and Julie, submit the reports to the R&D director on the first Monday of each month.It is late Friday evening and to their surprise, they have discovered that the month ends on Sunday and the reports are due on Monday morning.They have decided to come to work early Saturday morning, so they can finish the reports before Monday morning.They split the work as follows: Andrew will write and edit the reports while Julie collates data and draws all the necessary graphs.Assume that Julie starts her work on a report as soon as Andrew is finished with it and that Andrew works continuously.Times for the reports (in hours) are as follows:
At the end of each month, a research and development team writes status reports for the projects worked on during the month.The team leaders, Andrew and Julie, submit the reports to the R&D director on the first Monday of each month.It is late Friday evening and to their surprise, they have discovered that the month ends on Sunday and the reports are due on Monday morning.They have decided to come to work early Saturday morning, so they can finish the reports before Monday morning.They split the work as follows: Andrew will write and edit the reports while Julie collates data and draws all the necessary graphs.Assume that Julie starts her work on a report as soon as Andrew is finished with it and that Andrew works continuously.Times for the reports (in hours) are as follows:   a.What is the order of the projects using Johnson's rule? b.How many hours will it take them to finish all the reports? c.How many hours is Andrew idle? d.How many hours is Julie idle?<div style=padding-top: 35px>
a.What is the order of the projects using Johnson's rule?
b.How many hours will it take them to finish all the reports?
c.How many hours is Andrew idle?
d.How many hours is Julie idle?
Question
A print shop has four jobs that have to be processed through their only five-color press.They usually use the first-come first-served method of scheduling jobs.However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time.They are going to use the shortest processing time rule to do so.Processing times for each job are as follows (assume this is the arrival order): Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; Job D, 39 minutes.
a.In what order should the four jobs be done using the shortest processing time rule?
b.What is the average waiting (flow) time for all jobs using the shortest processing time rule?
c.What is the averaging waiting (flow) time using their usual first-come first-served rule?
Question
A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II.Assume work center I works continuously and that they are using Johnson's rule.Work centers need not change over to new jobs at the same time.Data appears below in hours:
A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II.Assume work center I works continuously and that they are using Johnson's rule.Work centers need not change over to new jobs at the same time.Data appears below in hours:   a.What is the sequence of tasks? b.What is the time in hours to complete all the tasks in both work centers? c.What is the total idle time in hours for work center I? d.What is the total idle time in hours for work center II?<div style=padding-top: 35px>
a.What is the sequence of tasks?
b.What is the time in hours to complete all the tasks in both work centers?
c.What is the total idle time in hours for work center I?
d.What is the total idle time in hours for work center II?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/66
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 14: Operations Scheduling and Sequencing
1
Scheduling problems occur almost exclusively in manufacturing.
False
2
Scheduling refers to determining the order in which jobs or tasks are processed.
False
3
For a single processor, a first-come, first-served (FCFS) rule minimizes the average flow time because customer waiting time will be minimized.
False
4
The makespan is the sum of flow times of a given set of jobs.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
5
The EDD rule minimizes the maximum of jobs past due but doesn't perform well on average flow-time, WIP inventory or resource utilization.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
6
In sequencing a set of jobs on a single processor, different sequences will have different makespans but the same average flow times.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
7
The shortest processing time rule and earliest due date rule will always provide the same sequence.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
8
A lateness measure can only be 0 or a positive number.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
9
Telling an umpire crew to work baseball games in Chicago, then Milwaukee, and then Cleveland is an example of a sequence.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
10
The SPT sequencing rule will maximize the average flow time.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
11
Flow time is the amount of time a job spends in a shop or factory.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
12
In practice, whenever processing times of a set of jobs are about equal, managers typically use a first-come, first-serve rule.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
13
A tardiness measure can be either zero (0) or a positive number.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
14
Indirectly, appointments reduce the cost of providing a service because the service provider is idle less each workday.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
15
High flow times reduce WIP inventory.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
16
Sequencing is not as much of a concern when several activities use a common resource.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
17
Tardiness measures the amount of time by which the completion time exceeds the due date.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
18
Since all jobs eventually get done, job sequencing has no effect on resource utilization.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
19
Appointments can be viewed as a reservation of service time and capacity.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
20
Scheduling and sequencing methods used in manufacturing are more beneficial in low-contact, than high-contact, service processes.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
21
Considering a two-resource sequencing problem,

A)The makespan is the same for any sequence of jobs
B)Flow time is minimized
C)The goal is to minimize makespan
D)Each job can be processed by either resource first
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
22
The time to rest and travel between games for baseball umpire crews is an important factor in developing their schedule.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
23
The sequencing rule that minimizes the maximum number of jobs that are past due from a given set of jobs is

A)Shortest processing time
B)Earliest due date
C)First come, first served
D)Least work remaining
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
24
The Shortest Processing Time (SPT) rule

A)Ensures that due dates are met
B)Maximizes average flow-time
C)Minimizes resource utilization
D)Minimizes work in process inventory
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
25
In sequencing jobs in a flow shop with two resources, Johnson's rule finds a sequence that has the smallest makespan.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
26
The numerical difference between the completion time and the due date is called

A)Flow time
B)Lateness
C)Makespan
D)Tardiness
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
27
When several products share common facilities, product sequencing affects cost.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
28
Triage by nurses in an emergency room would be an example of

A)Scheduling
B)Sequencing
C)Appointments
D)Shortest-processing-time rule
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
29
Which of the following is not a consideration when designing an appointment system?

A)Determining the appointment time interval
B)Determining the appropriate sequencing rule
C)Determining the length of each workday and the time off-duty
D)Deciding on an overbooking policy
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
30
Scheduling applies to all aspects of the value chain.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
31
Gantt charts can show what jobs are ahead of schedule, behind schedule, and on schedule.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
32
If the highest priority is to minimize the average job lateness, then the jobs sequence should begin with those jobs requiring

A)The shortest processing time
B)The smallest critical ratio
C)The least remaining operations
D)The longest processing time
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
33
Staff scheduling needs all of the following except

A)Flow-time estimates
B)Accurate forecasting
C)Staffing levels required by time period
D)Determining available personnel
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
34
Two examples of process-focused performance measures for sequencing rules are flow time and lateness.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
35
Rescheduling rarely occurs unless customers change their requested due dates.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
36
Scheduling refers to specifying

A)The sequence that jobs must be completed
B)The due date for each job
C)The start and completion times of jobs
D)The makespan of each job
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
37
The time needed to process a given set of jobs is called

A)Flow time
B)Ready time
C)Makespan
D)Due date
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
38
Appointments systems often overbook to maximize revenue.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
39
UPS, the world's largest package delivery company, is highly dependent on scheduling but not sequencing.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
40
Like the SPT rule, the earliest due date (EDD) rule minimizes the average flow time.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
41
Explain why any sequence chosen in the single-machine scheduling problem will not change makespan time.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
42
What four (4) decisions are considered in designing an appointment system?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
43
Johnson's sequencing rule is used to sequence

A)several jobs through several work centers
B)several jobs through one work center
C)two jobs through several work centers
D)several jobs through two work centers
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
44
Compare and contrast the advantages and disadvantages of the Shortest Processing Time (SPT) and the Earliest Due Date (EDD) sequencing rules.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
45
A movie theater requires the following minimum number of employees, each of which is required to have two consecutive days off. A movie theater requires the following minimum number of employees, each of which is required to have two consecutive days off.   How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees. How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
46
Staff scheduling attempts to match available personnel with the needs of the organization by performing what four steps?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
47
The table below includes processing times and due dates for five jobs.
The table below includes processing times and due dates for five jobs.   a.Use the Shortest Processing Time Rule (SPT) to determine the average flow time. b.Use the Earliest Due Date Rule (EDD) to determine the average lateness.
a.Use the Shortest Processing Time Rule (SPT) to determine the average flow time.
b.Use the Earliest Due Date Rule (EDD) to determine the average lateness.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
48
Short-term capacity fluctuations necessitate changes in schedules.List at least five factors affecting short-term capacity.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following is NOT a criterion for evaluating job sequencing rules?

A)average flow time
B)lateness
C)tardiness
D)sum of processing times
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
50
Which of the following is an example of a situation for which a Gantt chart would be appropriate?

A)developing a factory layout
B)tracking inventory levels over time
C)monitoring job schedules
D)forecasting personnel requirements in a two-shift operation
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
51
A requirement of Johnson's two-resource sequencing rule is

A)All jobs must begin at the same time
B)Jobs must be processed through each work center in the same job sequence
C)Only two jobs can be processed at a time through each work center
D)Total processing time must be minimized
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
52
The chief disadvantage of the shortest processing time rule is:

A)average job completion times are excessive
B)average number of jobs in the system is excessive
C)long-duration jobs may have excessive completion times
D)average job lateness is excessive
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
53
Describe Johnson's sequencing rule for the two-resource sequencing problem.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
54
Differentiate between scheduling and sequencing.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
55
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.They are job shops that handle a variety of outpatient surgical procedures.Their process is set up so that one doctor cuts and the other sews.They have five patients to sequence for tomorrow.Since the weather forecast is for a cool and sunny day, they would also like to play golf tomorrow.They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of that job.The patients and estimated times are as follows:
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.They are job shops that handle a variety of outpatient surgical procedures.Their process is set up so that one doctor cuts and the other sews.They have five patients to sequence for tomorrow.Since the weather forecast is for a cool and sunny day, they would also like to play golf tomorrow.They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of that job.The patients and estimated times are as follows:   Sequence the patients using Johnson's Method, state the schedule for each operation, and determine the minimum makespan. Sequence the patients using Johnson's Method, state the schedule for each operation, and determine the minimum makespan.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
56
Explain the three categories of criteria used to evaluate job sequencing performance.For each category, provide two example measures.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
57
A restaurant needs the following number of wait staff to serve its evening guests.
A restaurant needs the following number of wait staff to serve its evening guests.   How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees. How many employees are needed so that each as two consecutive days off? Construct a work schedule for these employees.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
58
Give at least five examples of service organizations (and employee type) where, due to high variability in customer demand, staff scheduling problems are prevalent.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
59
The following five jobs, along with their processing time and due dates, are given below.
The following five jobs, along with their processing time and due dates, are given below.   a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.
a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs
b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
60
ScheduleAnywhere.com on-line software helps clients do all the following except

A)Schedule employees from any computer with Internet access.
B)Decide how much to overbook for each day of the week.
C)See who's scheduled and who's available.
D)Avoid scheduling conflicts.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
61
An airplane repair facility has a contract to repair cargo aircraft for a regional airline.There are 62 planes in the airline company's fleet of planes.Because of the punishing workload, the planes require a considerable amount of maintenance.The repair facility is trying to determine how to schedule the needed repairs.They want to compare the shortest processing time rule and the first-come first-served rule.Currently, the following planes need repair and are in the repair facility (data given is in order of plane arrival, only one plane is worked on at a time and the shop is open 24 hours a day, 7 days a week).
An airplane repair facility has a contract to repair cargo aircraft for a regional airline.There are 62 planes in the airline company's fleet of planes.Because of the punishing workload, the planes require a considerable amount of maintenance.The repair facility is trying to determine how to schedule the needed repairs.They want to compare the shortest processing time rule and the first-come first-served rule.Currently, the following planes need repair and are in the repair facility (data given is in order of plane arrival, only one plane is worked on at a time and the shop is open 24 hours a day, 7 days a week).   a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)? b.What is the average time (in hours) in the shop using the shortest processing time rule? c.What is the average time (in hours) in the shop using the first?come first?served rule?
a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)?
b.What is the average time (in hours) in the shop using the shortest processing time rule?
c.What is the average time (in hours) in the shop using the first?come first?served rule?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
62
A print shop has five large commercial printing jobs to finish.They are trying to decide whether to use the shortest processing time (SPT) or the first-come first-served (FCFS) sequencing rule.Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):
A print shop has five large commercial printing jobs to finish.They are trying to decide whether to use the shortest processing time (SPT) or the first-come first-served (FCFS) sequencing rule.Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):   a.What is the average flow time in hours using the FCFS rule? b.What is the average job lateness in hours using the FCFS rule? c.What is the average flow time in hours using the SPT rule? d.What is the average job lateness in hours using the SPT rule?
a.What is the average flow time in hours using the FCFS rule?
b.What is the average job lateness in hours using the FCFS rule?
c.What is the average flow time in hours using the SPT rule?
d.What is the average job lateness in hours using the SPT rule?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
63
A young entrepreneur has just opened an electronics store.One of the many tasks that she must address is work scheduling.She plans to stay open from 9a.m.to 9 p.m.Monday through Saturday.She expects her employees to stock the shelves and also be available for cashier check-out when needed.All employees are full time and work four days in a row with two consecutive days off each week.She estimates the number of employees needed each day as follows:
A young entrepreneur has just opened an electronics store.One of the many tasks that she must address is work scheduling.She plans to stay open from 9a.m.to 9 p.m.Monday through Saturday.She expects her employees to stock the shelves and also be available for cashier check-out when needed.All employees are full time and work four days in a row with two consecutive days off each week.She estimates the number of employees needed each day as follows:   a.Use the days-off scheduling procedure to determine the minimum number of employees required? b.Based on your schedule found in part (a), which days are overstaffed and by how many workers are they overstaffed?
a.Use the days-off scheduling procedure to determine the minimum number of employees required?
b.Based on your schedule found in part (a), which days are overstaffed and by how many workers are they overstaffed?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
64
At the end of each month, a research and development team writes status reports for the projects worked on during the month.The team leaders, Andrew and Julie, submit the reports to the R&D director on the first Monday of each month.It is late Friday evening and to their surprise, they have discovered that the month ends on Sunday and the reports are due on Monday morning.They have decided to come to work early Saturday morning, so they can finish the reports before Monday morning.They split the work as follows: Andrew will write and edit the reports while Julie collates data and draws all the necessary graphs.Assume that Julie starts her work on a report as soon as Andrew is finished with it and that Andrew works continuously.Times for the reports (in hours) are as follows:
At the end of each month, a research and development team writes status reports for the projects worked on during the month.The team leaders, Andrew and Julie, submit the reports to the R&D director on the first Monday of each month.It is late Friday evening and to their surprise, they have discovered that the month ends on Sunday and the reports are due on Monday morning.They have decided to come to work early Saturday morning, so they can finish the reports before Monday morning.They split the work as follows: Andrew will write and edit the reports while Julie collates data and draws all the necessary graphs.Assume that Julie starts her work on a report as soon as Andrew is finished with it and that Andrew works continuously.Times for the reports (in hours) are as follows:   a.What is the order of the projects using Johnson's rule? b.How many hours will it take them to finish all the reports? c.How many hours is Andrew idle? d.How many hours is Julie idle?
a.What is the order of the projects using Johnson's rule?
b.How many hours will it take them to finish all the reports?
c.How many hours is Andrew idle?
d.How many hours is Julie idle?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
65
A print shop has four jobs that have to be processed through their only five-color press.They usually use the first-come first-served method of scheduling jobs.However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time.They are going to use the shortest processing time rule to do so.Processing times for each job are as follows (assume this is the arrival order): Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; Job D, 39 minutes.
a.In what order should the four jobs be done using the shortest processing time rule?
b.What is the average waiting (flow) time for all jobs using the shortest processing time rule?
c.What is the averaging waiting (flow) time using their usual first-come first-served rule?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
66
A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II.Assume work center I works continuously and that they are using Johnson's rule.Work centers need not change over to new jobs at the same time.Data appears below in hours:
A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II.Assume work center I works continuously and that they are using Johnson's rule.Work centers need not change over to new jobs at the same time.Data appears below in hours:   a.What is the sequence of tasks? b.What is the time in hours to complete all the tasks in both work centers? c.What is the total idle time in hours for work center I? d.What is the total idle time in hours for work center II?
a.What is the sequence of tasks?
b.What is the time in hours to complete all the tasks in both work centers?
c.What is the total idle time in hours for work center I?
d.What is the total idle time in hours for work center II?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 66 flashcards in this deck.