Deck 12: Project Auditing

Full screen (f)
exit full mode
Question
The __________ dimension of project success includes factors relating to opening a new market,developing a new line of products or services.Alternatively,if an internal project,success factors include developing new technologies,skills,or competencies.

A)project efficiency
B)customer impact / satisfaction
C)business / direct success
D)future potential
Use Space or
up arrow
down arrow
to flip the card.
Question
Audits done early in the project lifecycle are often focused on __________.

A)technical issues
B)management issues
C)financial issues
D)personnel issues
Question
__________ appraises the progress and performance of a project compared to its planned progress and performance or to the progress and performance of other similar projects.

A)Project control
B)Project evaluation
C)Project monitoring
D)Risk management
Question
Identification of the direct goals of a project requires __________.

A)a reading of the project structure
B)a reading of the project proposal
C)a reading of the budget
D)a reading of the WBS
Question
This section of an audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach,schedule,or budget that should be made in the remaining tasks.

A)introduction
B)current status
C)future project status
D)critical management issues
Question
The __________ dimension of project success includes the obvious factors of meeting the project's technical and operational specifications.It also includes factors relating to loyalty and repurchase.

A)project efficiency
B)customer impact / satisfaction
C)business / direct success
D)future potential
Question
The project audit covers __________.

A)only financial matters
B)everything except operating matters
C)only ethical and financial matters
D)any specified scope of importance to management
Question
Identification of the ancillary goals of a project requires __________ because; for the most part the goals were not overtly identified.

A)circular reasoning
B)deductive reasoning
C)inductive reasoning
D)abductive reasoning
Question
An evaluation of the likely outcomes of a policy and their probability of occurrence,usually conducted to compare two or more scenarios or policies is known as __________.

A)technical evaluation
B)project evaluation
C)risk analysis
D)profit estimation
Question
__________ is defined as a standard for performance,commonly established early on for later comparisons.

A)Audit
B)Baseline
C)Evaluation
D)Summary
Question
Which of the following is not one of the top three project success factors,from a project manager's perspective?

A)customer impact / satisfaction
B)business / direct success
C)future potential
D)efficiency
Question
In order for an audit / evaluation team to be conducted with skill and precision,all of the following conditions must be met,EXCEPT __________.

A)proper selection of the team
B)setting a schedule convenient for the auditors
C)accessibility of all records and files
D)preservation of free contact with the project members
Question
Two of the most common limits on the depth of an investigation and level of detail presented in an audit report are __________.

A)the personality of the auditor and cooperation received
B)scope and objectives
C)word processing support and existing documentation
D)money and time
Question
For audits made late in the project's life,__________ are major matters of interest.

A)technical issues
B)management issues
C)financial issues
D)personnel issues
Question
The accumulation,storage,and maintenance of auditable data are important cost elements.Such storage may be critically important in meeting the legal test of __________.

A)completeness
B)accuracy
C)due diligence
D)capacity
Question
Postcontrol cannot change the past,but it tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.The PMBOK refers to this as

A)audits
B)lessons learned
C)feedback loops
D)evaluation cycles
Question
The __________ dimension of project success is measured primarily in terms of the level of commercial success and market share.For internal projects,however,the factors might include such measures as yields,cycle times,processing steps,quality,and so on.

A)business / direct success
B)customer impact / satisfaction
C)project efficiency
D)future potential
Question
__________ is one of the four dimensions of project success,and is focused on meeting both the budget and schedule established in the project plan.

A)Project efficiency
B)Customer impact / satisfaction
C)Business / direct success
D)Future potential
Question
Which of the following is NOT a project audit life cycle event?

A)project audit initiation
B)project baseline definition
C)establishing an audit database
D)post-completion analysis of the project
Question
In the audit report,negative comments about individuals or groups associated with the project should be __________.

A)avoided
B)included
C)highlighted
D)disguised
Question
The value of project audits / evaluations conducted during the post-project stage will depend on the __________ to future projects.

A)links
B)costs
C)applicability of findings
D)conformity
Question
A major vehicle for evaluation is the __________,which is a more or less formal inquiry into any aspect of the project.

A)ethical audit
B)project audit
C)moral compass
D)technical audit
Question
The most immediate dimension of project success is the project's __________ in meeting both budget and schedule.

A)timing
B)delay
C)totality
D)effectiveness
Question
A typical detailed audit is conducted when __________ is required.

A)a follow-up to the general audit
B)effectiveness
C)an ethical audit
D)full disclosure
Question
The __________ section of the audit report should contain a review of major risks associated with the project and their projected impact on project time / cost / performance.

A)risk management
B)current project status
C)future project status
D)introduction
Question
If the audit report is to serve as a communication device,there should be a __________ for such documents.

A)repository
B)predetermined distribution list
C)stakeholder register
D)communication manager
Question
The _____ section of an audit report includes all issues the auditor feels require close monitoring by senior management.

A)introduction
B)current status
C)future project status
D)critical management issues
Question
__________ is a measure of the degree to which the output of a system conforms to pre-specified characteristics.

A)Scope
B)Quality
C)Cost
D)Schedule
Question
The __________ is a thorough examination of the management of a project,its methodology and procedures,its records,its properties,its budgets and expenditures,and its degree of completion.It may deal with the project as a whole,or only with a part of the project.

A)ethical audit
B)project methodology
C)project audit
D)project well-check
Question
In the current status section of an audit report,the subheading labeled __________ will compare the work completed with the resources expended.

A)scope
B)cost
C)schedule
D)quality
Question
In the Future Project Status section of the audit report,no assumptions should be made about __________ that are still under investigation at the time of the audit.

A)financial problems
B)ethical problems
C)efficiency problems
D)technical problems
Question
The __________ section of the audit should be reported as of the time of the audit.It should contain the following measures of performance: cost,schedule,progress,and quality.

A)future project status
B)introduction
C)risk management
D)current status
Question
Research by Walker et al argues that __________ is essential for management's ability to assemble information that is both timely and accurate.

A)independence
B)knowledge
C)efficiency
D)technology
Question
The __________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach,schedule,or budget that should be made in the remaining tasks.

A)introduction
B)current project status
C)future project status
D)risk management
Question
The stated project objectives,including customer satisfaction,are part of the project's __________ goals

A)indirect
B)ancillary
C)secondary
D)direct
Question
Project morale may suffer if the project audit report is not written with a(n)__________.

A)honest tone
B)complete story
C)stakeholder's perspective
D)constructive tone
Question
The __________ section of an audit report contains a description of the project to provide a framework of understanding for the reader.Project objectives are clearly delineated.

A)current status
B)future project status
C)introduction
D)risk management
Question
Managerial audits look at __________ and their use.

A)managerial systems
B)subordinate systems
C)manual systems
D)ethical policies
Question
The __________ goals are usually not overtly identified.

A)primary
B)overall
C)ancillary
D)most important
Question
__________ tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.

A)Auditing
B)Postcontrol
C)Baselining
D)Ruling
Question
Discuss some of the problems associated with finding the ancillary goals of a project.
Question
During the audit,the auditor / evaluator must maintain __________ and treat all materials gathered as confidential until the audit is formally released.

A)political and technical independence
B)political independence
C)technical independence
D)technical dependence
Question
A formal inquiry into some issue or aspect of a system is known as a(n)__________.

A)request
B)baseline
C)evaluation procedure
D)audit
Question
Contact between the a / e team and the __________ are not made without clearance from senior management.

A)CIO
B)ethics board
C)customer
D)project manager
Question
List and describe the events that comprise the project audit life cycle.
Question
A primary purpose of evaluation is to help translate the achievement of the project's goals into a contribution to the parent organization's direct goals.List some potential benefits that could be applied to ongoing and future projects from recommendations obtained from such an evaluation.
Question
The __________ section of the audit report should contain all issues that the auditor feels require close monitoring by senior management,along with a brief explanation of the relationships between these issues and the objectives of the project.

A)introduction
B)critical management issues
C)current project status
D)future project status
Question
List the minimum points that should be contained in the formal report of a project audit.
Question
The key rule of engagement for the project auditor is to gain __________ to enter the system.

A)acceptance
B)weight
C)permission
D)money
Question
We have seen a rise in agile management for projects with

A)high costs
B)uncertain scope
C)low employee morale
D)low quality
Question
Discuss the differences between a project audit and a financial audit.
Question
Project evaluation often makes recommendations that relate to the ancillary objectives of the parent organization.List some of these potential ancillary benefits of project evaluation.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/52
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 12: Project Auditing
1
The __________ dimension of project success includes factors relating to opening a new market,developing a new line of products or services.Alternatively,if an internal project,success factors include developing new technologies,skills,or competencies.

A)project efficiency
B)customer impact / satisfaction
C)business / direct success
D)future potential
D
2
Audits done early in the project lifecycle are often focused on __________.

A)technical issues
B)management issues
C)financial issues
D)personnel issues
A
3
__________ appraises the progress and performance of a project compared to its planned progress and performance or to the progress and performance of other similar projects.

A)Project control
B)Project evaluation
C)Project monitoring
D)Risk management
B
4
Identification of the direct goals of a project requires __________.

A)a reading of the project structure
B)a reading of the project proposal
C)a reading of the budget
D)a reading of the WBS
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
5
This section of an audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach,schedule,or budget that should be made in the remaining tasks.

A)introduction
B)current status
C)future project status
D)critical management issues
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
6
The __________ dimension of project success includes the obvious factors of meeting the project's technical and operational specifications.It also includes factors relating to loyalty and repurchase.

A)project efficiency
B)customer impact / satisfaction
C)business / direct success
D)future potential
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
7
The project audit covers __________.

A)only financial matters
B)everything except operating matters
C)only ethical and financial matters
D)any specified scope of importance to management
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
8
Identification of the ancillary goals of a project requires __________ because; for the most part the goals were not overtly identified.

A)circular reasoning
B)deductive reasoning
C)inductive reasoning
D)abductive reasoning
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
9
An evaluation of the likely outcomes of a policy and their probability of occurrence,usually conducted to compare two or more scenarios or policies is known as __________.

A)technical evaluation
B)project evaluation
C)risk analysis
D)profit estimation
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
10
__________ is defined as a standard for performance,commonly established early on for later comparisons.

A)Audit
B)Baseline
C)Evaluation
D)Summary
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following is not one of the top three project success factors,from a project manager's perspective?

A)customer impact / satisfaction
B)business / direct success
C)future potential
D)efficiency
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
12
In order for an audit / evaluation team to be conducted with skill and precision,all of the following conditions must be met,EXCEPT __________.

A)proper selection of the team
B)setting a schedule convenient for the auditors
C)accessibility of all records and files
D)preservation of free contact with the project members
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
13
Two of the most common limits on the depth of an investigation and level of detail presented in an audit report are __________.

A)the personality of the auditor and cooperation received
B)scope and objectives
C)word processing support and existing documentation
D)money and time
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
14
For audits made late in the project's life,__________ are major matters of interest.

A)technical issues
B)management issues
C)financial issues
D)personnel issues
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
15
The accumulation,storage,and maintenance of auditable data are important cost elements.Such storage may be critically important in meeting the legal test of __________.

A)completeness
B)accuracy
C)due diligence
D)capacity
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
16
Postcontrol cannot change the past,but it tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.The PMBOK refers to this as

A)audits
B)lessons learned
C)feedback loops
D)evaluation cycles
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
17
The __________ dimension of project success is measured primarily in terms of the level of commercial success and market share.For internal projects,however,the factors might include such measures as yields,cycle times,processing steps,quality,and so on.

A)business / direct success
B)customer impact / satisfaction
C)project efficiency
D)future potential
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
18
__________ is one of the four dimensions of project success,and is focused on meeting both the budget and schedule established in the project plan.

A)Project efficiency
B)Customer impact / satisfaction
C)Business / direct success
D)Future potential
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
19
Which of the following is NOT a project audit life cycle event?

A)project audit initiation
B)project baseline definition
C)establishing an audit database
D)post-completion analysis of the project
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
20
In the audit report,negative comments about individuals or groups associated with the project should be __________.

A)avoided
B)included
C)highlighted
D)disguised
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
21
The value of project audits / evaluations conducted during the post-project stage will depend on the __________ to future projects.

A)links
B)costs
C)applicability of findings
D)conformity
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
22
A major vehicle for evaluation is the __________,which is a more or less formal inquiry into any aspect of the project.

A)ethical audit
B)project audit
C)moral compass
D)technical audit
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
23
The most immediate dimension of project success is the project's __________ in meeting both budget and schedule.

A)timing
B)delay
C)totality
D)effectiveness
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
24
A typical detailed audit is conducted when __________ is required.

A)a follow-up to the general audit
B)effectiveness
C)an ethical audit
D)full disclosure
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
25
The __________ section of the audit report should contain a review of major risks associated with the project and their projected impact on project time / cost / performance.

A)risk management
B)current project status
C)future project status
D)introduction
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
26
If the audit report is to serve as a communication device,there should be a __________ for such documents.

A)repository
B)predetermined distribution list
C)stakeholder register
D)communication manager
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
27
The _____ section of an audit report includes all issues the auditor feels require close monitoring by senior management.

A)introduction
B)current status
C)future project status
D)critical management issues
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
28
__________ is a measure of the degree to which the output of a system conforms to pre-specified characteristics.

A)Scope
B)Quality
C)Cost
D)Schedule
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
29
The __________ is a thorough examination of the management of a project,its methodology and procedures,its records,its properties,its budgets and expenditures,and its degree of completion.It may deal with the project as a whole,or only with a part of the project.

A)ethical audit
B)project methodology
C)project audit
D)project well-check
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
30
In the current status section of an audit report,the subheading labeled __________ will compare the work completed with the resources expended.

A)scope
B)cost
C)schedule
D)quality
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
31
In the Future Project Status section of the audit report,no assumptions should be made about __________ that are still under investigation at the time of the audit.

A)financial problems
B)ethical problems
C)efficiency problems
D)technical problems
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
32
The __________ section of the audit should be reported as of the time of the audit.It should contain the following measures of performance: cost,schedule,progress,and quality.

A)future project status
B)introduction
C)risk management
D)current status
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
33
Research by Walker et al argues that __________ is essential for management's ability to assemble information that is both timely and accurate.

A)independence
B)knowledge
C)efficiency
D)technology
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
34
The __________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach,schedule,or budget that should be made in the remaining tasks.

A)introduction
B)current project status
C)future project status
D)risk management
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
35
The stated project objectives,including customer satisfaction,are part of the project's __________ goals

A)indirect
B)ancillary
C)secondary
D)direct
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
36
Project morale may suffer if the project audit report is not written with a(n)__________.

A)honest tone
B)complete story
C)stakeholder's perspective
D)constructive tone
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
37
The __________ section of an audit report contains a description of the project to provide a framework of understanding for the reader.Project objectives are clearly delineated.

A)current status
B)future project status
C)introduction
D)risk management
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
38
Managerial audits look at __________ and their use.

A)managerial systems
B)subordinate systems
C)manual systems
D)ethical policies
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
39
The __________ goals are usually not overtly identified.

A)primary
B)overall
C)ancillary
D)most important
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
40
__________ tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.

A)Auditing
B)Postcontrol
C)Baselining
D)Ruling
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
41
Discuss some of the problems associated with finding the ancillary goals of a project.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
42
During the audit,the auditor / evaluator must maintain __________ and treat all materials gathered as confidential until the audit is formally released.

A)political and technical independence
B)political independence
C)technical independence
D)technical dependence
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
43
A formal inquiry into some issue or aspect of a system is known as a(n)__________.

A)request
B)baseline
C)evaluation procedure
D)audit
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
44
Contact between the a / e team and the __________ are not made without clearance from senior management.

A)CIO
B)ethics board
C)customer
D)project manager
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
45
List and describe the events that comprise the project audit life cycle.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
46
A primary purpose of evaluation is to help translate the achievement of the project's goals into a contribution to the parent organization's direct goals.List some potential benefits that could be applied to ongoing and future projects from recommendations obtained from such an evaluation.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
47
The __________ section of the audit report should contain all issues that the auditor feels require close monitoring by senior management,along with a brief explanation of the relationships between these issues and the objectives of the project.

A)introduction
B)critical management issues
C)current project status
D)future project status
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
48
List the minimum points that should be contained in the formal report of a project audit.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
49
The key rule of engagement for the project auditor is to gain __________ to enter the system.

A)acceptance
B)weight
C)permission
D)money
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
50
We have seen a rise in agile management for projects with

A)high costs
B)uncertain scope
C)low employee morale
D)low quality
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
51
Discuss the differences between a project audit and a financial audit.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
52
Project evaluation often makes recommendations that relate to the ancillary objectives of the parent organization.List some of these potential ancillary benefits of project evaluation.
Unlock Deck
Unlock for access to all 52 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 52 flashcards in this deck.