Question
In earned value analysis,the 50-50 rule assumes that __________.

A)50 percent is earned when the task is half done and 50 percent is earned at completion
B)50 percent is earned when the task begins and 50 percent is earned at completion
C)50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D)50 percent is earned when the project is planned and 50 percent is earned when the project is over
Use Space or
up arrow
down arrow
to flip the card.
Question
According to the authors,the project manager can tolerate almost any kind of behavior,EXCEPT __________.

A)tardiness
B)negative attitude
C)unpunctuality
D)dishonesty
Question
For each factor to be measured during monitoring; performance criteria,standards,and __________ should be established.

A)data collection procedures
B)mechanized systems
C)automated systems
D)audit checks
Question
In earned value analysis,if the cost variance is (-$10,000),__________.

A)the cost variance is favorable
B)the cost variance is unfavorable
C)the scheduled variance is favorable
D)the scheduled cost avoidance is unfavorable
Question
In earned value analysis,the 0 - 100 percent rule allows __________.

A)100 percent credit before starting work and 0 percent credit after the completion
B)0 percent credit when work begins and 100 percent credit when the project is complete
C)0 percent credit when work begins and 100 percent credit at completion of the activity
D)0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Question
Management by exception has the disadvantage of being __________.

A)too expensive
B)too difficult to implement
C)a quantitative approach
D)an "after the fact" type of approach
Question
The first step in setting up a monitoring system is to __________.

A)collect existing data to see what data is relevant and available
B)collect every available piece of information so it can be analyzed
C)use whatever information is available
D)identify the key factors to be controlled
Question
Monitoring,as an activity,should be kept distinct from __________,which is the process of making judgments about the quality and effectiveness of project performance.

A)collecting
B)reporting
C)evaluation
D)recording
Question
According to the authors,in the planning - monitoring - controlling cycle,the directions of the flows indicate that __________.

A)information flows from the top to bottom and authority flows from the bottom to the top
B)information flows from the bottom to the top and authority flows from the top to the bottom
C)authority flows from the bottom to the top
D)information flows from the top to the bottom
Question
The most common mistake made when monitoring data is to gather information that is clearly related to project performance but __________.

A)is so volatile that trends cannot be detected
B)has little or no probability of changing significantly between collection periods
C)is too unusual to use
D)cannot be captured in the mechanized PMIS
Question
An appropriate and common secondary user for monitoring includes __________.

A)auditing,learning from mistakes,and reporting progress and status
B)exercising effective control over the project
C)evaluating current status of the project
D)fixing the blame when things go wrong
Question
A large proportion of all data collected takes one of the following forms EXCEPT __________.

A)indicators
B)verbal measures
C)raw numbers
D)individual perceptions
Question
Measuring characteristics such as "quality of team member cooperation" and "morale of team members" generally takes the form of __________characterizations.

A)verbal
B)raw number
C)indicative
D)all of the above
Question
__________ is when individuals are overwhelmed with too many reports,too much detail,and too much dat a.

A)Information overload
B)PMIS verification
C)Project isolation
D)Computer paralysis
Question
Which of the following is NOT a common difficulty in the design of project reports?

A)Providing too much detail
B)Having too many interface modules
C)Poor correspondence to the parent firm's reporting system
D)Poor correspondence between the planning and monitoring systems
Question
One of the most common errors when collecting data is __________.

A)collecting rapidly changing data frequently
B)collecting data infrequently because data collection is so time consuming
C)collecting data that rarely changes
D)reporting to management after collecting data.
Question
ETC + AC = __________.

A)BAC
B)EAC
C)SPI
D)CPI
Question
According to the authors,the key items to be planned,monitored,and controlled are __________.

A)schedule,budget,and financial stability
B)schedule,quality,performance,and customer satisfaction
C)schedule,budget,and feasibility
D)schedule,budget,and performance
Question
If CPI = 1.05,then __________ is favorable.

A)time variance
B)schedule variance
C)cost variance
D)performance variance
Question
Monitoring,as an activity,should be kept distinct from __________,which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

A)recording
B)controlling
C)collecting
D)reporting
Question
In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.

A)schedule variance
B)cost variance
C)time variance
D)CPI
Question
If EV = $500,AC = $450,PV = $475; CPI = __________.

A)1)05
B)1)11
C))95
D))90
Question
EV - PV = __________.

A)SV
B)CV
C)CPI
D)TV
Question
When collecting raw project data,it is important to make sure that all data are collected from sources that operate on the same __________ and with the same rules for data collection.

A)continent
B)floor of the building
C)time intervals
D)scope plan
Question
Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?

A)The 50-50 rule
B)The 0-100 percent rule
C)Critical input use rule
D)The proportionality rule
Question
Ordinal rankings of performance are examples of a __________ type of measure.

A)frequency count
B)raw number
C)verbal measure
D)subjective numeric rating
Question
If EV = $500,AC = $475,PV = $450; SV = ________.

A)$50
B)$25
C)90%
D)95%
Question
__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.

A)Initiating
B)Planning
C)Controlling
D)Monitoring
Question
The project __________ describes what is being done,when and the planned level of resource usage for each task,work-package or element in the project.

A)WBS
B)risk management plan
C)schedule
D)quality report
Question
In general,__________ tend to bias data advertently or inadvertently.

A)project managers
B)stakeholders
C)those who report them
D)those who use them
Question
In earned value analysis,BAC refers to the __________.

A)budgeted annual cost
B)budget at completion
C)budget at close-out
D)big annual cost
Question
__________ are used when some aspect of system performance cannot be measured directly.

A)Indicators
B)Frequency counts
C)Raw numbers
D)Verbal measures
Question
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the __________ rule.

A)50-50
B)0-100 percent
C)critical input use
D)proportionality
Question
__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

A)Detailed and timely reports
B)Executive summaries
C)Scope change reports
D)The WBS
Question
A(n)__________ can be used to deal with issues of honesty related to the monitoring system.

A)WBS
B)executive summary
C)internal audit
D)quality control chart
Question
The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

A)schedule
B)WBS
C)quality report
D)resource report
Question
In earned value analysis,EAC refers to the __________.

A)estimated cost at completion
B)estimated actual cost
C)eliminated annual cost
D)estimated annual cost
Question
The project control process should be viewed as a(n)__________,with revised plans and schedules (if warranted)following corrective actions.The project control process should run continuously until the project is completed.

A)closed loop system
B)open loop system
C)open environment
D)earned value plan
Question
Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.

A)top executives
B)lower-level personnel
C)all the stakeholders
D)project managers
Question
A(n)__________ is a simple tally of the occurrence of an event.This type of measure is easy to collect and is often reported as events per unit of time or reported as events as a percent of a standard number.

A)frequency count
B)raw number
C)subjective numeric rating
D)verbal measure
Question
In earned value analysis,(CPI)(SPI)= __________.

A)CV
B)TPI
C)CSI
D)SV
Question
Describe the three common difficulties in designing project reports.
Question
ST-AT =

A)TV
B)EV
C)CV
D)SV
Question
Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.
Question
Suggest some practical measures that can be used to improve the perception about the benefits of meetings.
Question
Conceptually,EAC represents the amount spent to date plus __________.

A)the delay costs
B)BAC
C)CV
D)ETC
Question
Excessive computer involvement with computer activity replacing project management; loss of touch with the project and its realities,is referred to as __________.

A)computer simulation
B)computer paralysis
C)information overload
D)robotic automation
Question
Identify the main complaints associated with meetings.
Question
Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?

A)Muddy waters
B)Mysterious stakeholders
C)Unconstrained constraints
D)Scope creep
Question
A status report that is vague or contains overly optimistic language like "very soon" or "marginal increase" in costs is referred to as

A)suspicious
B)paralyzed
C)incomplete
D)risky
Question
List the four conventions used to aid in estimating percent completion.
Question
(BAC + EV) / CPI = __________.

A)EAC
B)TPI
C)CPI
D)ETC
Question
If CSI is less than 1,it is indicative of a(n)__________.

A)problem
B)good project
C)efficient project
D)budget error
Question
When using earned value analysis,identify the three conditions that can exist with respect to the completion of activities in a project.
Question
Unfortunately,it is common to focus monitoring activities on data that are easily __________ but not necessarily important.

A)gathered
B)purchased
C)analyzed
D)reported
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/55
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Monitoring and Information Systems
1
In earned value analysis,the 50-50 rule assumes that __________.

A)50 percent is earned when the task is half done and 50 percent is earned at completion
B)50 percent is earned when the task begins and 50 percent is earned at completion
C)50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D)50 percent is earned when the project is planned and 50 percent is earned when the project is over
B
2
According to the authors,the project manager can tolerate almost any kind of behavior,EXCEPT __________.

A)tardiness
B)negative attitude
C)unpunctuality
D)dishonesty
D
3
For each factor to be measured during monitoring; performance criteria,standards,and __________ should be established.

A)data collection procedures
B)mechanized systems
C)automated systems
D)audit checks
A
4
In earned value analysis,if the cost variance is (-$10,000),__________.

A)the cost variance is favorable
B)the cost variance is unfavorable
C)the scheduled variance is favorable
D)the scheduled cost avoidance is unfavorable
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
5
In earned value analysis,the 0 - 100 percent rule allows __________.

A)100 percent credit before starting work and 0 percent credit after the completion
B)0 percent credit when work begins and 100 percent credit when the project is complete
C)0 percent credit when work begins and 100 percent credit at completion of the activity
D)0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
6
Management by exception has the disadvantage of being __________.

A)too expensive
B)too difficult to implement
C)a quantitative approach
D)an "after the fact" type of approach
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
7
The first step in setting up a monitoring system is to __________.

A)collect existing data to see what data is relevant and available
B)collect every available piece of information so it can be analyzed
C)use whatever information is available
D)identify the key factors to be controlled
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
8
Monitoring,as an activity,should be kept distinct from __________,which is the process of making judgments about the quality and effectiveness of project performance.

A)collecting
B)reporting
C)evaluation
D)recording
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
9
According to the authors,in the planning - monitoring - controlling cycle,the directions of the flows indicate that __________.

A)information flows from the top to bottom and authority flows from the bottom to the top
B)information flows from the bottom to the top and authority flows from the top to the bottom
C)authority flows from the bottom to the top
D)information flows from the top to the bottom
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
10
The most common mistake made when monitoring data is to gather information that is clearly related to project performance but __________.

A)is so volatile that trends cannot be detected
B)has little or no probability of changing significantly between collection periods
C)is too unusual to use
D)cannot be captured in the mechanized PMIS
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
11
An appropriate and common secondary user for monitoring includes __________.

A)auditing,learning from mistakes,and reporting progress and status
B)exercising effective control over the project
C)evaluating current status of the project
D)fixing the blame when things go wrong
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
12
A large proportion of all data collected takes one of the following forms EXCEPT __________.

A)indicators
B)verbal measures
C)raw numbers
D)individual perceptions
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
13
Measuring characteristics such as "quality of team member cooperation" and "morale of team members" generally takes the form of __________characterizations.

A)verbal
B)raw number
C)indicative
D)all of the above
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
14
__________ is when individuals are overwhelmed with too many reports,too much detail,and too much dat a.

A)Information overload
B)PMIS verification
C)Project isolation
D)Computer paralysis
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
15
Which of the following is NOT a common difficulty in the design of project reports?

A)Providing too much detail
B)Having too many interface modules
C)Poor correspondence to the parent firm's reporting system
D)Poor correspondence between the planning and monitoring systems
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
16
One of the most common errors when collecting data is __________.

A)collecting rapidly changing data frequently
B)collecting data infrequently because data collection is so time consuming
C)collecting data that rarely changes
D)reporting to management after collecting data.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
17
ETC + AC = __________.

A)BAC
B)EAC
C)SPI
D)CPI
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
18
According to the authors,the key items to be planned,monitored,and controlled are __________.

A)schedule,budget,and financial stability
B)schedule,quality,performance,and customer satisfaction
C)schedule,budget,and feasibility
D)schedule,budget,and performance
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
19
If CPI = 1.05,then __________ is favorable.

A)time variance
B)schedule variance
C)cost variance
D)performance variance
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
20
Monitoring,as an activity,should be kept distinct from __________,which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

A)recording
B)controlling
C)collecting
D)reporting
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
21
In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.

A)schedule variance
B)cost variance
C)time variance
D)CPI
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
22
If EV = $500,AC = $450,PV = $475; CPI = __________.

A)1)05
B)1)11
C))95
D))90
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
23
EV - PV = __________.

A)SV
B)CV
C)CPI
D)TV
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
24
When collecting raw project data,it is important to make sure that all data are collected from sources that operate on the same __________ and with the same rules for data collection.

A)continent
B)floor of the building
C)time intervals
D)scope plan
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
25
Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?

A)The 50-50 rule
B)The 0-100 percent rule
C)Critical input use rule
D)The proportionality rule
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
26
Ordinal rankings of performance are examples of a __________ type of measure.

A)frequency count
B)raw number
C)verbal measure
D)subjective numeric rating
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
27
If EV = $500,AC = $475,PV = $450; SV = ________.

A)$50
B)$25
C)90%
D)95%
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
28
__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.

A)Initiating
B)Planning
C)Controlling
D)Monitoring
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
29
The project __________ describes what is being done,when and the planned level of resource usage for each task,work-package or element in the project.

A)WBS
B)risk management plan
C)schedule
D)quality report
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
30
In general,__________ tend to bias data advertently or inadvertently.

A)project managers
B)stakeholders
C)those who report them
D)those who use them
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
31
In earned value analysis,BAC refers to the __________.

A)budgeted annual cost
B)budget at completion
C)budget at close-out
D)big annual cost
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
32
__________ are used when some aspect of system performance cannot be measured directly.

A)Indicators
B)Frequency counts
C)Raw numbers
D)Verbal measures
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
33
The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the __________ rule.

A)50-50
B)0-100 percent
C)critical input use
D)proportionality
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
34
__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

A)Detailed and timely reports
B)Executive summaries
C)Scope change reports
D)The WBS
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
35
A(n)__________ can be used to deal with issues of honesty related to the monitoring system.

A)WBS
B)executive summary
C)internal audit
D)quality control chart
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
36
The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.

A)schedule
B)WBS
C)quality report
D)resource report
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
37
In earned value analysis,EAC refers to the __________.

A)estimated cost at completion
B)estimated actual cost
C)eliminated annual cost
D)estimated annual cost
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
38
The project control process should be viewed as a(n)__________,with revised plans and schedules (if warranted)following corrective actions.The project control process should run continuously until the project is completed.

A)closed loop system
B)open loop system
C)open environment
D)earned value plan
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
39
Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.

A)top executives
B)lower-level personnel
C)all the stakeholders
D)project managers
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
40
A(n)__________ is a simple tally of the occurrence of an event.This type of measure is easy to collect and is often reported as events per unit of time or reported as events as a percent of a standard number.

A)frequency count
B)raw number
C)subjective numeric rating
D)verbal measure
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
41
In earned value analysis,(CPI)(SPI)= __________.

A)CV
B)TPI
C)CSI
D)SV
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
42
Describe the three common difficulties in designing project reports.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
43
ST-AT =

A)TV
B)EV
C)CV
D)SV
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
44
Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
45
Suggest some practical measures that can be used to improve the perception about the benefits of meetings.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
46
Conceptually,EAC represents the amount spent to date plus __________.

A)the delay costs
B)BAC
C)CV
D)ETC
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
47
Excessive computer involvement with computer activity replacing project management; loss of touch with the project and its realities,is referred to as __________.

A)computer simulation
B)computer paralysis
C)information overload
D)robotic automation
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
48
Identify the main complaints associated with meetings.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
49
Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?

A)Muddy waters
B)Mysterious stakeholders
C)Unconstrained constraints
D)Scope creep
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
50
A status report that is vague or contains overly optimistic language like "very soon" or "marginal increase" in costs is referred to as

A)suspicious
B)paralyzed
C)incomplete
D)risky
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
51
List the four conventions used to aid in estimating percent completion.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
52
(BAC + EV) / CPI = __________.

A)EAC
B)TPI
C)CPI
D)ETC
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
53
If CSI is less than 1,it is indicative of a(n)__________.

A)problem
B)good project
C)efficient project
D)budget error
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
54
When using earned value analysis,identify the three conditions that can exist with respect to the completion of activities in a project.
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
55
Unfortunately,it is common to focus monitoring activities on data that are easily __________ but not necessarily important.

A)gathered
B)purchased
C)analyzed
D)reported
Unlock Deck
Unlock for access to all 55 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 55 flashcards in this deck.