Deck 13: Project Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/98
Play
Full screen (f)
Deck 13: Project Management
1
Issues of cultural diversity in project management should only be addressed if and when they arise.
False
2
A work breakdown structure provides a common understanding of and justification for a project.
False
3
The three primary elements of project management include planning,scheduling,and costing.
False
4
A unique,one-time operational activity or effort is referred to as a process.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
5
A typical project team is cross-functional consisting of members throughout an organization.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
6
Management and control of a companywide portfolio of projects is known as enterprise project management.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
7
The principles of total quality management (TQM)cannot be applied to project management.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
8
Managing quality is not an important part of project management.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
9
Asian cultures tend to embrace project management's methodical approach more than western cultures.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
10
Project scheduling is recognized as the most critical element in the project management process.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
11
Global projects are rarely concerned with cultural differences among team members because English is the universal business language.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
12
Control,one of the basic elements of a project plan,involves a set of procedures for monitoring and evaluating progress and performance.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
13
Earned value analysis reports a project's performance by tracking its forecasted completion date and anticipated budget variations.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
14
A Gantt chart provides a visual display of the project schedule that includes scheduled start times,finish times,and available slack.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
15
Project control involves monitoring a project and measuring its progress toward a successful completion.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
16
Project scope,one of the basic elements of a project plan,involves a set of procedures for anticipating and assessing uncertainties that might increase the risk of delaying the project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
17
The upper level of a work breakdown structure for a project highlights summary activities and/or major components.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
18
Two key elements of project control are time management and cost management.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
19
Enterprise project management refers to the management and control of a large,complex project.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
20
In general,projects are subject to less uncertainty than other types of processes.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
21
In general,crashing costs decrease as a project's duration is systematically reduced to a target value.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
22
The earliest start time for the first activity in a project is generally at time zero.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
23
Slack represents the amount of time an activity can be delayed without delaying the project completion time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
24
A dummy variable is an activity inserted into the AOA network diagram to show a precedence relationship,but does not represent any passage of time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
25
Microsoft Project is a software package that supports CPM/PERT analysis.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
26
A project's duration can be reduced by crashing activities on the critical path.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
27
Crashing activities with positive slack reduces a project's duration.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
28
Which of the following is not a basic element in a project plan?
A)Objectives
B)Personnel
C)Contract requirements
D)All of these answer choices are correct.
A)Objectives
B)Personnel
C)Contract requirements
D)All of these answer choices are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
29
Unlike PERT,CPM incorporates probabilistic time estimates into the project management process.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
30
The project management process encompasses
A)planning.
B)scheduling.
C)control.
D)All of these answer choices are correct.
A)planning.
B)scheduling.
C)control.
D)All of these answer choices are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
31
Because the critical path is the shortest path through a network,it defines the project completion time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
32
A(n)______________ breaks down a project into components,subcomponents,activities,and tasks.
A)work breakdown structure (WBS)
B)scope statement
C)responsibility assignment matrix (RAM)
D)organizational breakdown structure (OBS)
A)work breakdown structure (WBS)
B)scope statement
C)responsibility assignment matrix (RAM)
D)organizational breakdown structure (OBS)
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
33
The _______________ is a document that provides a common understanding,justification,and expected result for a project.
A)statement of work
B)work breakdown structure
C)scope statement
D)responsibility assignment matrix
A)statement of work
B)work breakdown structure
C)scope statement
D)responsibility assignment matrix
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
34
Which of the following is not a general characteristic of a project?
A)a project has a unique purpose
B)a project has more certainty
C)a project has more uncertainty
D)a project often draws resources from various areas in the organization
A)a project has a unique purpose
B)a project has more certainty
C)a project has more uncertainty
D)a project often draws resources from various areas in the organization
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
35
With an activity-on-node (AON)network diagram,the nodes indicate the precedence relationships and the arrows represent the project's activities.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
36
PERT stands for program enterprise and resource technique.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
37
A(n)_______________ is a project team structure that includes members from different functional areas.
A)matrix organization
B)project network
C)organizational breakdown structure
D)work breakdown structure
A)matrix organization
B)project network
C)organizational breakdown structure
D)work breakdown structure
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
38
The critical path is the longest path through the project's network.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
39
Indirect costs always increase as a project's duration increases.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
40
Activities that are not on a project's critical path have zero slack.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
41
Diversity among project team members brings different
A)views.
B)experiences.
C)values.
D)All of these answer choices are correct.
A)views.
B)experiences.
C)values.
D)All of these answer choices are correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
42
The single most important criterion for the success of many projects is that
A)it be finished on time.
B)the quality meet minimum standards.
C)the costs are minimized.
D)None of these answer choices is correct.
A)it be finished on time.
B)the quality meet minimum standards.
C)the costs are minimized.
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
43
Which area of the world takes a lot of holidays potentially impacting project schedules?
A)Asia.
B)Southern Europe
C)North America
D)None of these answer choices is correct.
A)Asia.
B)Southern Europe
C)North America
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
44
In general,the latest finish time for an activity is equal to
A)latest finish time minus the activity time estimate.
B)the minimum of the latest start times for the activities that immediately follow.
C)the maximum of the latest start times for the activities that immediately follow.
D)the average of the latest start times for the activities that immediately follow.
A)latest finish time minus the activity time estimate.
B)the minimum of the latest start times for the activities that immediately follow.
C)the maximum of the latest start times for the activities that immediately follow.
D)the average of the latest start times for the activities that immediately follow.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
45
Which area of the world employs a more methodically approach to business that values patience and relationship building?
A)Asia.
B)Southern Europe
C)North America
D)None of these answer choices is correct.
A)Asia.
B)Southern Europe
C)North America
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
46
A standard procedure for numerically measuring a project's progress is referred to as
A)program evaluation and review technique (PERT).
B)critical path method (CPM).
C)Gantt chart.
D)earned value analysis.
A)program evaluation and review technique (PERT).
B)critical path method (CPM).
C)Gantt chart.
D)earned value analysis.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
47
In general,the earliest finish time for an activity is equal to
A)earliest start time + activity time estimate.
B)earliest start time - activity time estimate.
C)earliest start time - slack time.
D)earliest start time + slack time.
A)earliest start time + activity time estimate.
B)earliest start time - activity time estimate.
C)earliest start time - slack time.
D)earliest start time + slack time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
48
Project managers must address cultural diversity in
A)project planning
B)project scheduling.
C)project control.
D)None of these answer choices is correct.
A)project planning
B)project scheduling.
C)project control.
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
49
Which of the following is one of the oldest and most widely used scheduling technique?
A)PERT
B)CPM
C)Gantt
D)Microsoft Project
A)PERT
B)CPM
C)Gantt
D)Microsoft Project
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
50
The key elements of project control include all the following except
A)time management.
B)cost management.
C)material management.
D)communication.
A)time management.
B)cost management.
C)material management.
D)communication.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
51
Which of the following is not used to calculate probabilistic time estimates?
A)optimistic
B)most likely
C)least likely
D)pessimistic
A)optimistic
B)most likely
C)least likely
D)pessimistic
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
52
A bar graph displaying when activities are scheduled to start,when they will be finished,and where extra time is available is known as a
A)PERT chart.
B)work breakdown structure (WBS).
C)Gantt chart.
D)responsibility assignment matrix (RAM).
A)PERT chart.
B)work breakdown structure (WBS).
C)Gantt chart.
D)responsibility assignment matrix (RAM).
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
53
In project management the term slack refers to the amount of time
A)to complete an activity without delaying the project.
B)an activity can be delayed without delaying the project.
C)needed to complete the entire project.
D)required to complete the project's critical activities.
A)to complete an activity without delaying the project.
B)an activity can be delayed without delaying the project.
C)needed to complete the entire project.
D)required to complete the project's critical activities.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
54
The longest path through a project network is referred to as the
A)activity-on-node path.
B)path of greatest slack.
C)critical path.
D)noncritical path.
A)activity-on-node path.
B)path of greatest slack.
C)critical path.
D)noncritical path.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
55
For an activity-on-node (AON)network,
A)arrows represent activities and nodes represent events.
B)nodes represent activities and arrows indicate precedence relationships.
C)arrows represent events and nodes indicate precedence relationships.
D)nodes indicate precedence relationships and arrows indicates the length of the activity time.
A)arrows represent activities and nodes represent events.
B)nodes represent activities and arrows indicate precedence relationships.
C)arrows represent events and nodes indicate precedence relationships.
D)nodes indicate precedence relationships and arrows indicates the length of the activity time.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
56
_______________ relationship is the sequential relationship of project activities to each other.
A)Precedence
B)Scheduling
C)Slack
D)Prior
A)Precedence
B)Scheduling
C)Slack
D)Prior
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
57
One disadvantage of Gantt charts,especially for large projects,is that it does not
A)clearly show precedence relationships.
B)indicate activity start times.
C)indicate activity finish times.
D)use bars to represent activities.
A)clearly show precedence relationships.
B)indicate activity start times.
C)indicate activity finish times.
D)use bars to represent activities.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
58
Which of the following is not one of the basic steps involved in developing a schedule?
A)define the activities
B)sequence the activities
C)estimate the time required to complete each activity
D)identify the project cost
A)define the activities
B)sequence the activities
C)estimate the time required to complete each activity
D)identify the project cost
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
59
Which of the following is the universal business language most often utilized when managing global projects?
A)French
B)Spanish
C)English
D)Chinese
A)French
B)Spanish
C)English
D)Chinese
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
60
________________ is the process of making sure a project progresses to a successful completion.
A)Project planning
B)Project scheduling
C)Project control
D)None of these answer choices is correct.
A)Project planning
B)Project scheduling
C)Project control
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
61
A project consists of the following activities:
Table XX
Using Table XX,the earliest finish (EF)time for activity D is
A)7 weeks.
B)13 weeks.
C)20 weeks.
D)30 weeks.

Using Table XX,the earliest finish (EF)time for activity D is
A)7 weeks.
B)13 weeks.
C)20 weeks.
D)30 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
62
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the latest start (LS)time for activity D is
A)8 days.
B)11 days.
C)19 days.
D)12 days.

Using Table YY,the latest start (LS)time for activity D is
A)8 days.
B)11 days.
C)19 days.
D)12 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
63
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the critical path for this project is
A)A-B-C.
B)A-C-D.
C)A-B-D.
D)A-B-C-D.

Using Table YY,the critical path for this project is
A)A-B-C.
B)A-C-D.
C)A-B-D.
D)A-B-C-D.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
64
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the amount of slack associated with activity C is
A)4 days.
B)3 days.
C)2 days.
D)1 day.

Using Table YY,the amount of slack associated with activity C is
A)4 days.
B)3 days.
C)2 days.
D)1 day.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
65
A project consists of the following activities:
Table XX
Using Table XX,the time complete the entire project is
A)20 weeks.
B)30 weeks.
C)36 weeks.
D)39 weeks.

Using Table XX,the time complete the entire project is
A)20 weeks.
B)30 weeks.
C)36 weeks.
D)39 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
66
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the time to complete the entire project would be
A)23 days.
B)19 days.
C)17 days.
D)11 days.

Using Table YY,the time to complete the entire project would be
A)23 days.
B)19 days.
C)17 days.
D)11 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
67
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the earliest finish (EF)time for activity C is
A)4 days.
B)6 days.
C)10 days.
D)11 days.

Using Table YY,the earliest finish (EF)time for activity C is
A)4 days.
B)6 days.
C)10 days.
D)11 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
68
The _______________ probability distribution is typically used to describe uncertain activity times in a project.
A)beta
B)normal
C)binomial
D)exponential
A)beta
B)normal
C)binomial
D)exponential
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
69
A project consists of the following four activities with activity times in days:
Table YY
Using Table YY,the earliest start (ES)time for activity B is
A)5 days.
B)6 days.
C)11 days.
D)14 days.

Using Table YY,the earliest start (ES)time for activity B is
A)5 days.
B)6 days.
C)11 days.
D)14 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
70
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table ZZ
Using Table ZZ,the expected time to complete activity A is
A)5.00 weeks.
B)7.33 weeks.
C)7.67 weeks.
D)8.00 weeks.

Using Table ZZ,the expected time to complete activity A is
A)5.00 weeks.
B)7.33 weeks.
C)7.67 weeks.
D)8.00 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
71
The estimated variance for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is
A)3.75 weeks.
B)1.50 weeks.
C)5.25 weeks.
D)0.25 weeks.
A)3.75 weeks.
B)1.50 weeks.
C)5.25 weeks.
D)0.25 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
72
The slack time for an activity can be computed as
A)latest start time (LS)- latest finish time (LF).
B)earliest start time (ES)+ earliest finish time (EF).
C)latest start time (LS)- earliest start time (ES).
D)latest finish time (LF)+ earliest finish time (EF).
A)latest start time (LS)- latest finish time (LF).
B)earliest start time (ES)+ earliest finish time (EF).
C)latest start time (LS)- earliest start time (ES).
D)latest finish time (LF)+ earliest finish time (EF).
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
73
The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is
A)2 days.
B)4 days.
C)6 days.
D)11 days.
A)2 days.
B)4 days.
C)6 days.
D)11 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
74
The estimated mean time for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is
A)13.0 weeks.
B)12.75 weeks.
C)12.5 weeks.
D)9.0 weeks.
A)13.0 weeks.
B)12.75 weeks.
C)12.5 weeks.
D)9.0 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
75
A project consists of the following activities:
Table XX
Using Table XX,the earliest start time for activity F is
A)30 weeks.
B)20 weeks.
C)14 weeks.
D)13 weeks.

Using Table XX,the earliest start time for activity F is
A)30 weeks.
B)20 weeks.
C)14 weeks.
D)13 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
76
A project consists of the following activities:
Table XX
Using Table XX,the latest start (LS)time for activity B is
A)5 weeks.
B)8 weeks.
C)13 weeks.
D)14 weeks.

Using Table XX,the latest start (LS)time for activity B is
A)5 weeks.
B)8 weeks.
C)13 weeks.
D)14 weeks.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
77
A project consists of the following activities:
Table XX
Using Table XX,the amount of slack associated with activity C is
A)0 weeks.
B)3 weeks.
C)6 weeks.
D)None of these answer choices is correct.

Using Table XX,the amount of slack associated with activity C is
A)0 weeks.
B)3 weeks.
C)6 weeks.
D)None of these answer choices is correct.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
78
The estimated mean time for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is
A)9.67 days.
B)11 days.
C)11.33 days.
D)11.67 days.
A)9.67 days.
B)11 days.
C)11.33 days.
D)11.67 days.
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
79
For activities on a project's critical path,
A)earliest start time (ES)equals latest start time (LS).
B)earliest start time (ES)is greater than latest start time (LS).
C)earliest start time (ES)is less than latest start time (LS).
D)earliest start time (ES)equals latest finish time (LF).
A)earliest start time (ES)equals latest start time (LS).
B)earliest start time (ES)is greater than latest start time (LS).
C)earliest start time (ES)is less than latest start time (LS).
D)earliest start time (ES)equals latest finish time (LF).
Unlock Deck
Unlock for access to all 98 flashcards in this deck.
Unlock Deck
k this deck
80
A project consists of the following activities:
Table XX
Using Table XX,the critical path for this project consists of activities
A)A-B-C-D-E-F.
B)A-C-E-F.
C)A-B-C-F.
D)A-B-D-F.

Using Table XX,the critical path for this project consists of activities
A)A-B-C-D-E-F.
B)A-C-E-F.
C)A-B-C-F.
D)A-B-D-F.