expand icon
book Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb cover

Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb

Edition 1ISBN: 9780134110219
book Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb cover

Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb

Edition 1ISBN: 9780134110219
Exercise 21
A company uses an electronic part. One tool the company uses to monitor the supplier of the part is a supplier scorecard. The number of defects is carefully monitored each quarter, and the results are used to help assess the supplier's performance. Two primary performance metrics are parts per million (PPM) defects and percent PPM improvement. The following measurements and scoring criteria are used:
A company uses an electronic part. One tool the company uses to monitor the supplier of the part is a supplier scorecard. The number of defects is carefully monitored each quarter, and the results are used to help assess the supplier's performance. Two primary performance metrics are parts per million (PPM) defects and percent PPM improvement. The following measurements and scoring criteria are used:        Data collected on this electronic part over the last quarter indicated 15 defects and 400,000 parts received with the PPM defect rate in the prior quarter equal to 50. Calculate the performance measures and update the scorecard using the latest quarter's results.
A company uses an electronic part. One tool the company uses to monitor the supplier of the part is a supplier scorecard. The number of defects is carefully monitored each quarter, and the results are used to help assess the supplier's performance. Two primary performance metrics are parts per million (PPM) defects and percent PPM improvement. The following measurements and scoring criteria are used:        Data collected on this electronic part over the last quarter indicated 15 defects and 400,000 parts received with the PPM defect rate in the prior quarter equal to 50. Calculate the performance measures and update the scorecard using the latest quarter's results.
Data collected on this electronic part over the last quarter indicated 15 defects and 400,000 parts received with the PPM defect rate in the prior quarter equal to 50. Calculate the performance measures and update the scorecard using the latest quarter's results.
Explanation
Verified
like image
like image

Supplier scorecard:
It is the way of co...