Exercise 25
Shown below are the planning period's demand and the standard hours required for four products from a company's sales and operations plan. Assuming that the company has 65,000 hours of labor available during the planning period, determine whether the sales and operations plan is feasible. Shown below are the planning period's demand and the standard hours required for four products from a company's sales and operations plan. Assuming that the company has 65,000 hours of labor available during the planning period, determine whether the sales and operations plan is feasible.
Explanation
Verified
like image
like image

Rough-cut capacity planning:
It is the ...