Exercise 3
Item A has a gross requirement of 2000 in week 6. Currently, there are 500 Item As on hand with a scheduled receipt of 500 items in week 3. The lead time for item A is three weeks with an order quantity of 500. Complete the MRP record for item A.
Explanation
Verified
like image
like image

Material requirement management (MRP):
...