expand icon
book Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin cover

Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin

Edition 7ISBN: 978-0073376301
book Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin cover

Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin

Edition 7ISBN: 978-0073376301
Exercise 21
A public water utility is trying to decide between two different sizes of pipe for a new water main. A 250-mm line will have an initial cost of $155,000, whereas a 300-mm line will cost $210,000. Since there is more head loss through the 250-mm pipe, the pumping cost is expected to be $3000 more per year than for the 250-mm line. If the lines are expected to last for 30 years, which size should be selected on the basis of a present worth analysis using an interest rate of 10% per year
Explanation
Verified
like image
like image

The formula for calculating the present ...

close menu
Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin
cross icon