Exercise 78
A mechanical engineer estimated that the equipment cost for a multitube cyclone system with a capacity of 60,000 cfm would be $400,000. If the direct cost factor is 3.1 and the indirect cost factor is 0.38, what is the estimated total plant cost The indirect cost factor applies to the total direct cost.
Explanation
Verified
like image
like image

The formula to calculate total plant cos...