Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin
Edition 7ISBN: 978-0073376301
Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin
Edition 7ISBN: 978-0073376301 Exercise 4
Nicole is an engineer on temporary assignment at a refinery operation in Seaside. She has reviewed a cost estimate for $430,000, which covers some new processing equipment for the ethylene line. The equipment itself is estimated at $250,000 with a construction cost factor of 0.30 and an installation cost factor of 0.30. No indirect cost factor is listed, but she knows from other sites that indirect cost is a sizable amount that increases the cost of the line's equipment.
a) If the indirect cost factor should be 0.40, determine whether the current estimate includes a factor comparable to this value b) Determine the cost estimate if the 0.40 indirect cost factor is used.
a) If the indirect cost factor should be 0.40, determine whether the current estimate includes a factor comparable to this value b) Determine the cost estimate if the 0.40 indirect cost factor is used.
Explanation
The formula to calculate total plant cos...
Engineering Economy 7th Edition by Leland Blank ,Anthony Tarquin
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255