A company that manufactures stoves has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse.
Distribution Center A
Transit Time: 2 weeks
Order Quantity: 100 units
Distribution Center B
Transit Time: 1 week
Order Quantity: 200 units
Central Supply
Lead Time: 2 weeks
Order Quantity: 500 units
Distribution Center A
Transit Time: 2 weeks
Order Quantity: 100 units

Transit Time: 1 week
Order Quantity: 200 units

Lead Time: 2 weeks
Order Quantity: 500 units

Explanation
Distribution requirement planning:
Dist...