expand icon
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
Exercise 19
A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse.
Distribution Center A
Transit Time: 2 weeks
Order Quantity: 500 units A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse. Distribution Center A Transit Time: 2 weeks Order Quantity: 500 units   Distribution Center B Transit Time: 2 weeks Order Quantity: 200 units   Central Supply Lead Time: 1 week Order Quantity: 600 units  Distribution Center B
Transit Time: 2 weeks
Order Quantity: 200 units A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse. Distribution Center A Transit Time: 2 weeks Order Quantity: 500 units   Distribution Center B Transit Time: 2 weeks Order Quantity: 200 units   Central Supply Lead Time: 1 week Order Quantity: 600 units  Central Supply
Lead Time: 1 week
Order Quantity: 600 units A company that manufactures snow shovels has one plant and two distribution centers (DCs). Given the following information for the two DCs, calculate the gross requirements, projected available, and planned order releases for the two DCs and the gross requirements, projected available, and planned order releases for the central warehouse. Distribution Center A Transit Time: 2 weeks Order Quantity: 500 units   Distribution Center B Transit Time: 2 weeks Order Quantity: 200 units   Central Supply Lead Time: 1 week Order Quantity: 600 units
Explanation
Verified
like image
like image

Distribution requirement planning:
Dist...

close menu
Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
cross icon