Exercise 2
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is $30 per hour. Determine the following:
a. The fixed cost.
b. The variable cost.
c. The total cost and unit cost for a lot of 600.
d. The total cost and unit cost for a lot of 1200.
Explanation
Verified
like image
like image

Introduction:
• Fixed cost: Fixed costs...