( Appendix 12A ) Cycle Time and Velocity
Prakesh Company has the following data for one of its manufacturing cells:
Maximum units produced in a month: 50,000 units
Actual units produced in a month: 40,000 units
Hours of production labor in one month: 10,000 hours
Required:
Compute the (1) theoretical cycle time (in minutes), (2) actual cycle time (in minutes), (3) theoretical velocity (in units per hour), and (4) actual velocity (in units per hour).
Prakesh Company has the following data for one of its manufacturing cells:
Maximum units produced in a month: 50,000 units
Actual units produced in a month: 40,000 units
Hours of production labor in one month: 10,000 hours
Required:
Compute the (1) theoretical cycle time (in minutes), (2) actual cycle time (in minutes), (3) theoretical velocity (in units per hour), and (4) actual velocity (in units per hour).
Explanation
• Cycle time is the length of time it ta...