(2009 CPA Exam)
Merry Co. has two major categories of factory overhead: materials handling and quality control. The costs expected for these categories for the coming year are as follows:
The plant currently applies overhead based on direct labor hours. The estimated direct labor hours are 80,000 per year. The plant manager is asked to submit a bid and assembles the following data on a proposed job.
What amount is the estimated product cost on the proposed job?
a. $8,000
b. $10,000
c. $14,000
d. $18,000
Merry Co. has two major categories of factory overhead: materials handling and quality control. The costs expected for these categories for the coming year are as follows:

The plant currently applies overhead based on direct labor hours. The estimated direct labor hours are 80,000 per year. The plant manager is asked to submit a bid and assembles the following data on a proposed job.

What amount is the estimated product cost on the proposed job?
a. $8,000
b. $10,000
c. $14,000
d. $18,000
Explanation
The overhead costs of Merry Co. are ment...
Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
Why donβt you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255