For the network in Problem, determine the earliest and latest activity times and the slack for each activity. Indicate how the critical path would be determined from this information.
Problem
Identify all the paths in the following network, compute the length of each, and indicate the Critical path (activity times are in weeks):
Explanation
Verified
like image
like image

Consider the following activity network ...