Introduction to Management Science 12th Edition by Bernard Taylor
Edition 12ISBN: 978-0133778847
Introduction to Management Science 12th Edition by Bernard Taylor
Edition 12ISBN: 978-0133778847 Exercise 22
A group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in weeks.
Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.

Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.
Explanation
Calculate the ES, EF, LS, LF and slack u...
Introduction to Management Science 12th Edition by Bernard Taylor
Why donât you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255