Exercise 39
The following table provides the information necessary to construct a project network and project crash data:
The following table provides the information necessary to construct a project network and project crash data:    a. Construct the project network. b. Manually crash the network to 28 weeks. c. Formulate the general linear programming model for this network. d. Formulate the linear programming crashing model that would crash this model by the maximum amount. a. Construct the project network.
b. Manually crash the network to 28 weeks.
c. Formulate the general linear programming model for this network.
d. Formulate the linear programming crashing model that would crash this model by the maximum amount.
Explanation
Verified
like image
like image

Crashing is a method used to reduce or s...