Edition 12ISBN: 978-0133778847 Exercise 61
The Americo Oil Company is considering making a bid for a shale oil development contract to be awarded by the federal government. The company has decided to bid $112 million. The company estimates that it has a 60% chance of winning the contract with this bid. If the firm wins the contract, it can choose one of three methods for getting the oil from the shale. It can develop a new method for oil extraction, use an existing (inefficient) process, or subcontract the processing to a number of smaller companies once the shale has been excavated. The results from these alternatives are as follows:
Develop new process:
Use present process:
Subcontract:
The cost of preparing the contract proposal is $2 million. If the company does not make a bid, it will invest in an alternative venture with a guaranteed profit of $30 million. Construct a sequential decision tree for this decision situation and determine whether the company should make a bid.
Develop new process:



Explanation
Company AO is considering for making a b...