Exercise 1
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified:
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified:     a. Draw a project network diagram. b. Calculate the scheduling times and total slack for each activity. c. List the critical path activities and project duration. d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?
a. Draw a project network diagram.
b. Calculate the scheduling times and total slack for each activity.
c. List the critical path activities and project duration.
d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?
Explanation
Verified
like image
like image

PERT and CPM:
In order to keep track of...