Exercise 5
Slippery Rock College is planning a basketball tournament. The following information has been collected on each activity in the project:
Slippery Rock College is planning a basketball tournament. The following information has been collected on each activity in the project:     a. Draw a network diagram of this project, and label the activities and events. b. Calculate the total slack and scheduling times for all activities. What is the critical path? c. When should team selection begin if the tournament is scheduled to start on the morning of December 27? (Include Saturday and Sunday as working days.)
a. Draw a network diagram of this project, and label the activities and events.
b. Calculate the total slack and scheduling times for all activities. What is the critical path?
c. When should team selection begin if the tournament is scheduled to start on the morning of December 27? (Include Saturday and Sunday as working days.)
Explanation
Verified
like image
like image

PERT and CPM:
In order to keep track of...