Miller Landscaping is attempting to project costs for future quarters. Miller has compiled data and decided to use the high-low costing method. The low value is $250,000 for 5,000 hours and the high value is $400,000 for 8,000 hours. What is the variable cost per hour
Explanation
High - Low method:
High - Low cost esti...