Exercise 40
A customer's order is delivered (received by the customer) on December 1, 2013. This order was placed with the company on September 1, 2013, and received by the manufacturing department on September 15, 2013. Actual production on the order began on October 15, 2013, and was completed November 15, 2013. Based on this information, calculate the following for this order: total customer-response time (CRT); order receipt time; manufacturing lead time (processing time); manufacturing wait time; manufacturing time; and delivery time. ( Hint: Refer to Exhibit 14.14.) Prepare your answers in days.
Reference:
A customer's order is delivered (received by the customer) on December 1, 2013. This order was placed with the company on September 1, 2013, and received by the manufacturing department on September 15, 2013. Actual production on the order began on October 15, 2013, and was completed November 15, 2013. Based on this information, calculate the following for this order: total customer-response time (CRT); order receipt time; manufacturing lead time (processing time); manufacturing wait time; manufacturing time; and delivery time. ( Hint: Refer to Exhibit 14.14.) Prepare your answers in days. Reference:
Explanation
Verified
like image
like image

Here we are provided with the data of or...