Matching Supply with Demand 3rd Edition by Gerard Cachon,Christian Terwiesch
Edition 3ISBN: 978-0073525204
Matching Supply with Demand 3rd Edition by Gerard Cachon,Christian Terwiesch
Edition 3ISBN: 978-0073525204 Exercise 1
(Three Step) Consider a worker-paced line with three process steps, each of which is staffed with one worker. The sequence of the three steps does not matter for the completion of the product. Currently, the three steps are operated in the following sequence.
a. What would happen to the inventory in the process if the process were operated as a push system
b. Assuming you would have to operate as a push system, how would you resequence the three activities
c. How would you implement a pull system

a. What would happen to the inventory in the process if the process were operated as a push system
b. Assuming you would have to operate as a push system, how would you resequence the three activities
c. How would you implement a pull system
Explanation
The capacity of a workstation can be com...
Matching Supply with Demand 3rd Edition by Gerard Cachon,Christian Terwiesch
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255