The Midlands Company is eager to develop a project schedule. They have already completed the scope statement, work breakdown structure, and schedule management plan. What is the next thing they should do in order to start creating a project schedule?
A) define activities
B) nothing; they are ready to proceed
C) sequence activities
D) estimate activity durations
A) define activities
B) nothing; they are ready to proceed
C) sequence activities
D) estimate activity durations
Explanation
So, M company's next step after they hav...