Thom Company produces 100 units in 10 hours. The cycle time for Thom
A) is 10 units per hour.
B) is 10 hours per unit.
C) is 10 minutes per unit.
D) is 6 minutes per unit.
E) cannot be calculated.
A) is 10 units per hour.
B) is 10 hours per unit.
C) is 10 minutes per unit.
D) is 6 minutes per unit.
E) cannot be calculated.
Explanation
Given:
No. of units produced =...